[2025] VCC 466
General information, not legal advice.
County Court of Victoria
2025-04-16
Original judgment source is linked above.
(a) The contracting party was not the defendant, but rather a company of which the defendant was a director, Unico Investments Pty Ltd ().
(b) The payment claim is invalid as it does not comply with s 14(2)(c) and s 14(2)(d) of the Act as:
(i) the claim does not identify the "construction work" to which it relates; and/or
(ii) the amount claimed is not apparent from the claim.
(c) The payment claim is invalid as it includes "excluded amounts", being matters that are not "claimable variations" in breach of s 14(3)(b) and s 16(4)(a)(ii) of the Act, being the claims for "tiles" and "plastering".
(d) The parties agree that the plaintiff is not entitled to a progress payment which includes the amount for invoice INV-0696, because that amount had already been paid.
(e) The claim was served out of time. The plaintiff claimed the "reference date" was the "last date the builder was on site". There was a dispute as to whether this was 23 October 2023 or 25 October 2023. The claim was served on 25 January 2024.
(f) There is a dispute about whether the margin payable was 10% or 30%, and whether it has been paid.
Additional works Inv 696 instructed by Frank Basile
Scaffolding - Select Access 3 x Inv instructed by Frank Basile
Slab excavation and slab pour for disability ramp (materials included)
Hire of Quick Stage aluminium scaffolding from 1 August 2023 to 4 September 2023
Delivery and hire of scaffold tower from 6 July 2023 to 30 September 2023
Installation, delivery and hire of Quick Stage aluminium scaffolding from 20-31 July 2023
(a) the existence of a construction contract for the progress payment;
(b) the existence of a reference date for the progress payment;
(c) a valid payment claim for the progress payment;
(d) no payment schedule having been given; and
(e) that the respondent has failed to pay the whole or part of the claimed amount.
Is there a construction contract between the plaintiff and the defendant?
(a) That the defendant was a director of Unico;
(b) Unico was the registered proprietor of the land and building on which the contract works were to be performed;
(c) Unico was the advertised "builder" on the project;
(d) Unico paid the deposit, being the essential element of consideration in formation;
(e) Unico made other payments to the plaintiff for the works; and
(f) Unico was the ultimate beneficiary of the works.
LTP was a party to the construction contract, but even if it was not a party in the formal sense, it was nevertheless a person who, under the construction contract, was at least arguably liable to make the payments under the Payment Claims, and thus a person who "may be liable" within the meaning of s 14(1) of the SOP Act.
Discussion and conclusion: the defendant is the contracting party
Does the payment claim satisfy the requirement to clearly identify the work and the amounts - s 14(2)(c) and s 14(2)(d) of the Act?
Discussion and conclusion: the payment claim does not comply with s 14(2)
Does the payment claim include excluded amounts - s14(3)(b) and 16(4)(a)(ii) of the Act?
(a) the work was carried out under a construction contract; and
(b) the person for whom the work has been carried out (the defendant) requested or directed the carrying out of the work; and
(c) the parties do not agree as to, amongst other things, the value of the amount payable or the method of valuing the amount payable.
Discussion and conclusion: the payment claim does include 'excluded amounts'
I certify that these 22 pages are a true copy of the judgment of her Honour Judge Kirton delivered on 16 April 2025.
[1] Building and Construction Industry Security of Payment Act 2002 (Vic) s 7(2)(b) (the 'Act' or 'SOP Act').
[2] Plaintiff's Outline of Submissions dated 13 June 2024.
[3] Defendant's Outline of Submissions dated 13 June 2024 and 15 August 2024.
[4] Affidavit of Jeremy Martinez dated 24 April 2024 (**'First Martinez Affidavit'); Supplementary Affidavit of Jeremy Martinez affirmed 13 June 2024 ('Second Martinez Affidavit'); Supplementary Affidavit of Jeremy Martinez affirmed 25 June 2024 ('Third Martinez Affidavit'); Supplementary Affidavit of Jeremy Martinez affirmed 26 July 2024 ('**Fourth Martinez Affidavit').
[5] Affidavit of Frank Basile affirmed 11 June 2024 (**'First Basile Affidavit'); Affidavit of Frank Basile affirmed 10 July 2024 ('**Second Basile Affidavit').
[6] [2018] VCC 674 ('3D Flow').
[9] Boral Limited v Foley & Bear Pty Ltd trading as J&R Industries [2016] NSWCA 373 [22]
[10] First Basile Affidavit [6]-[7].
[12] Façade Designs International Pty Ltd v Yuanda Vic Pty Ltd [2020] VSC 570, 18 [36].
[13] [2023] VCC 1527, 21 [100]
[14] [2019] VCC 1878, 9 [13].
[15] Yuanda Vic Pty Ltd v Façade Designs International Pty Ltd [2021] VSCA 44, 6 [22]-[23], 8-9 [31] ('Yuanda').
[16] Yuanda (n 15) 11 [38] (per McLeish and Niall JJA).
[21] Yuanda (n 15) 47 [120] (per Sifris JA).
[22] Ibid (n 15) 9 [31] (per McLeish and Niall JJA).
JMT Construction and Project Management Pty Ltd
Basile [2025] VCC 466