[2025] WASAT 121
General information, not legal advice.
State Administrative Tribunal (WA)
2025-11-03
Ms J
Original judgment source is linked above.
(b) any prejudice to the applicant if a stay, or an adjournment, is not granted, the latter of which includes consideration of the prospects of success in the Supreme Court proceedings;
(c) any prejudice to the respondents if a stay, or an adjournment, is granted, which includes consideration of the impact of delay;
(d) whether there is a serious question to be determined in the review proceedings;
(f) the impact of an adjournment on the Tribunal's objectives; and
(1) Subject to regulations made under section 11(5), if the Building Commissioner is satisfied that a regulated building service that is the subject of a building service complaint has not been carried out in a proper and proficient manner or is faulty or unsatisfactory, the Building Commissioner may deal with the building service complaint by making a building remedy order.
(2) The Building Commissioner cannot make a building remedy order requiring -
(a) work to be done of a value estimated by the Building Commissioner to exceed the prescribed amount; or
(b) an amount exceeding the prescribed amount to be paid,
unless the respondent consents to the order being made.
(3) Unless a greater amount is prescribed by the regulations, in subsection (2) the prescribed amount is $100 000.
(4) The Building Commissioner may make any ancillary or incidental order the Building Commissioner considers appropriate.
(1) A building remedy order consists of one of the following -
(a) an order that a person who carried out a regulated building service remedy the building service as specified in the order;
(b) an order that a person who carried out a regulated building service pay to an aggrieved person such costs of remedying the building service as the Building Commissioner or State Administrative Tribunal, as the case requires, considers reasonable and specifies in the order;
(c) an order that a person who carried out a regulated building service pay to an aggrieved person a sum of money specified in the order to compensate the aggrieved person for the failure to carry out the building service in a proper and proficient manner or for faulty or unsatisfactory building work.
Prejudice to the applicant if the review proceedings are not adjourned
Prospects of success in the Supreme Court proceedings
(a) there are currently two actions on foot in the Federal Court of Australia involving BGC Group companies, the pipes' manufacturer, Iplex Pipelines Australia Pty Ltd (Iplex), and the owners of houses in which the pipes were installed (homeowners);
(b) the scope of the 'matter' in each of the Federal Court actions includes whether the homeowners have claims against BGC Group companies or Iplex in respect of defects in the manufacture, supply, or installation of the pipes;
(c) the decision to make a BRO in relation to the pipes forms part of the 'matter' in the Federal Court actions, and is a 'matter' arising under a law of the Commonwealth Parliament, namely the Competition and Consumer Act 2010 (Cth); and
(d) by reason of s 75, s 76 and s 77 of the Commonwealth Constitution, the Western Australian Parliament cannot confer judicial power in relation to that 'matter' on an entity, namely the Building Commissioner or its delegates, that is not a Court of the State and s 37 of the Building Services Act is invalid to the extent it purports to confer such power.
(a) is the Building Commissioner exercising judicial power when making a BRO; and
(b) if the Building Commissioner is exercising judicial power when making a BRO, does the making of the BRO fall within a 'matter' arising under a law of the Commonwealth.
Prejudice to the applicant if the stay is not granted
Respondents' further submissions in relation to the applicant's prejudice
Prejudice to the respondents if the stay or adjournment are granted
Length of the delay if there is a stay but no adjournment
Length of the delay if there is a stay and an adjournment
(a) the delegate's estimate of the cost of the re-pipe work as falling under the statutory limit of $100,000 did not include relevant costs in relation to the respondents' house, but rather were based on the probable costs of hypothetical works that were different to that house, and that there was no estimate of the damage to the contents of the house, which is a category of remedial work included in the BRO;
(b) on a proper construction of s 5(1) of the Building Services Act, the regulated building service provided by the applicant was not faulty or unsatisfactory merely because the applicant had installed pipes containing an unknown latent defect;
(c) the delegate did not have power to include an order in the BRO requiring the applicant to remedy damage directly caused by the plumbing failures to the house, and alternatively damage to the contents of the house, because these are not orders requiring the applicant to remedy the building service it carried out within the meaning of s 36(1)(a) of the Building Services Act;
(d) the applicant is not able to comply with the BRO within the meaning of cl 10.5 of the Plumbing Policy without reallocating resources already committed to the applicant's contractual obligations to construct other houses and its attendance on emergency burst pipe repairs, rectification works, ceiling re-pipes and zone re-pipes; and
(e) the delegate failed to have regard to cl 10.3(d) of the Plumbing Policy, requiring that the delegate consider whether the respondents are able to receive a remedy in relation to the pipes, including through an insurance or other claim.
(a) to achieve the resolution of questions, complaints, or disputes, and to make or review decisions, fairly and according to the substantial merits of the case; and
(b) to act as speedily and with as little formality as is practicable and minimise the costs to the parties.[30]
The orders made on 18 September 2025 were as follows:
J-Corp Pty Ltd hereby undertakes to the Tribunal to pay to any party restrained or affected by the Tribunal's order dated 18 September 2025 staying the operation of Building Remedy Order O2024-979 pending further order of the Tribunal such compensation as the Tribunal may in its discretion consider in the circumstances to be just, such compensation to be assessed by the Tribunal or in accordance with such directions as the Tribunal may make and to be paid in such manner as the Tribunal may direct.
I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.
[1] Ventura Home Group Pty Ltd and Simon Bosnich & Ors, CC 459 of 2025; Ventura Home Group Pty Ltd and Timothy Cox & Ors, CC 462 of 2025; Ventura Home Group Pty Ltd and Jamie Wright & Ors, CC 480 of 2025 (Ventura Home Group and Wright proceedings).
[3] Ventura Home Group and Wright proceedings.
[4] Dobson and Legal Practice Board of Western Australia [2022] WASAT 80 [57] to [58].
[5] Soutorine and The Medical Board of Australia [2020] WASAT 5 (Soutorine) [24] to [28].
[6] PAG (WA) Pty Ltd and Commissioner for Consumer Protection [2018] WASAT 57 [25].
[7] Nugawela and Medical Board of Australia [2023] WASAT 82 (Nugawela).
[8] Nugawela [28]; State Administrative Tribunal Act 2004 (WA) (SAT Act), s 27(1).
[10] Forrest & Forrest Pty Ltd v Minister for Aboriginal Affairs [2024] WASCA 96 [58].
[11] In Souterine, the decisive factor appears to be that the doctor had undertaken not to perform certain procedures which meant that it could not be said it would jeopardise public safety if he was granted a stay: see [64].
[12] Western Australian Planning Commission and Coogee General Store Pty Ltd [2007] WASAT 182 [11].
[13] Owners of Strata Plan 58161 and Hanssen Pty Ltd [2022] WASAT 77 [11], [16], [17] and [18].
[18] Building Services (Complaint Resolution and Administration) Act 2011 (WA) (Building Services Act), s 5(1) and s 86(j).
[19] Section 91(1) of the Building Services Act enables the Building Commissioner to delegate the power under s 37.
[21] Hanssen Pty Ltd v Owners of Strata Plan 58161 [2024] WASCA 87.
[22] The owners of which house are not a party to any of the four matters before me.
[25] This being the category in the Western Australian Plumbing Failure Policy (2024) published in the Western Australian Government Gazette, No. 137, 12 November 2024, page 2661, into which the respondents in these proceedings and the other three proceedings fall.
[26] Western Australian Plumbing Failure Policy (2024) published in the Western Australian Government Gazette, No. 137, 12 November 2024, page 2661. See cl 12.9 and cl 12.12 in particular.
[28] SH v Chief Executive Officer of Department of Communities [2019] WASCA 31 [29] following Collector of Customs (NSW) v Brian Lawlor Automotive Pty Ltd (1979) 41 FLR 338, 342.
[29] Frugtniet v Australian Securities and Investments Commission (2019) 266 CLR 250; [2019] HCA 16 [15] and [51].
[31] Legal Profession Complaints Committee and Rayney [2016] WASAT 142 [18].
Dobson and Legal Practice Board of Western Australia [2022] WASAT 80
Forrest & Forrest Pty Ltd v Minister for Aboriginal Affairs [2024] WASCA 96
Frugtniet v Australian Securities and Investments Commission (2019) 266 CLR 250; [2019] HCA 16
Hanssen Pty Ltd v Owners of Strata Plan 58161 [2024] WASCA 87
Legal Profession Complaints Committee and Rayney [2016] WASAT 142
Nugawela and Medical Board of Australia [2023] WASAT 82
Owners of Strata Plan 58161 and Hanssen Pty Ltd [2022] WASAT 77
PAG (WA) Pty Ltd v Commissioner for Consumer Protection [2018] WASAT 57
SH v Chief Executive Officer of Department of Communities [2019] WASCA 31
Soutorine and The Medical Board of Australia [2020] WASAT 5
Western Australian Planning Commission and Coogee General Store Pty Ltd [2007] WASAT 182
(2019) 266 CLR 250
(1979) 41 FLR 338
(1979) 24 ALR 307