[2025] WASC 205
General information, not legal advice.
Supreme Court of WA
2025-05-26
Solomon J
Original judgment source is linked above.
The major highways include the Brand and Great Northern Highways, with future highway - Perth-Darwin Highway to be constructed to replace Great Northern Highway, as the primary heavy haulage route from the Perth Metropolitan Area and the north west of the State.
...
A future main connecting road to link the existing Great Northern Highway and Perth-Darwin Highway, should the proposed new urban settlement proceed.
To pursue the early construction of the Perth-Darwin Highway to alleviate the heavy haulage traffic on Great Northern Highway and divert through traffic away from Bindoon;
To press for urgent improvements to Great Northern Highway to reduce traffic problems and accidents.
The modifications to the plan had various consequences. These included the necessity to build a longer sealed road for internal traffic, in contrast with a shorter unsealed road under the initial application. In addition, vehicles entering and exiting the proposed facility on the Property would have longer to travel to and from Great Northern Highway than if there had been direct access. A map/diagram of the modified plan appears below.[22]
(a) removal expenses; or
(b) disruption and reinstatement of a business; or
(c) the halting of building works in progress at the date when the interest is taken and the consequential termination of building contracts; or
(d) architect's fees or quantity surveyor's fees actually incurred by the claimant in respect of proposed buildings or improvements which cannot be commenced or continued in consequence of the taking of the interest; or
(e) any other facts which the acquiring authority, the court, or the State Administrative Tribunal considers it just to take into account in the circumstances of the case.
(1) $288,667 for loss arising from the additional costs;
(2) cost of a 410m slip road/driveway at a cost of $197,780;
(3) signage at a cost of $10,000;
(4) additional maintenance costs for the longer driveway at a cost of $21,333; and
(5) replacement of dam at a cost of $59,600.
(1) the cost of the sealed 583 m road which, as noted, Mr Garmony calculated from the evidence from Mr Hancock established as $697,958.81; or
(2) that cost of $697,958.81, less the cost of the unsealed road that would have been required under the initial application, in respect of which Instant Products relied on evidence that it would have cost $179,000, reducing the claim to $518,958.81; or
(3) the difference between a sealed road of 583m and a sealed road of 411 m (on the basis that even under the initial application, a sealed road was likely to have been required). Using the linear rate extracted from Mr Hancock's evidence, that difference would be $205,915.
Further to recent instructions ... please note the following key findings from the general town planning investigation undertaken by this office in respect of the abovementioned property.
...
...
Discretionary ('A') Uses (subject to public advertising)
...
Transport Depot - IMPORTANT NOTE: We know from recent dealings with the City of Swan there is currently strong demand for transport depots in Bullsbrook and surrounding areas given the proximity and good accessibility to both Great Northern and Brand Highways. This land use type is a good potential option for [a] portion of the land if you are looking to derive a passive income.
...
(a) the objectives of the land's current 'Agricultural Resource zoning and 'Basic Raw Materials' Special Control Area classifications in the Shire of Chittering's current Town Planning Scheme No 6;
(b) the need to obtain approval from Main Roads WA for direct access to Great Northern Highway along the land's western boundary.
(1) the WAPC's Development Control Policy 5.1 Regional Roads (Vehicular Access) (Control Policy); and
(2) the MRWA policy statement on Driveways (Driveways Policy).[64]
1.1 This policy sets out the principles to be applied when considering proposals for vehicle access to or from developments abutting regional roads. It is intended to inform government agencies, local government and prospective developers of these principles and to act as guidelines for the exercise of development control powers in this regard.
...
3.1.4 In summary, the capacity of regional roads to carry traffic, safety of that traffic, and the free flow of traffic are all related to access - the fewer the number of driveways and junctions, the smoother the traffic flow and safer the road.
...
3.2.1 The functional classification of roads and streets is an essential first stage in the establishment of a network which can satisfy the requirements of both traffic movement and development. There is no universally recognised standard defining different types of roads. The Commission has, therefore, adopted the road classification system outlined in Policy No. DC 1.4, 'Functional Road Classification for Planning', namely primary distributors, district distributors, local distributors and access roads.
3.2.2 The access control requirements of this policy apply to Primary and District Distributors, which includes all categories of regional roads designated in the Metropolitan Region Scheme and in areas subject to other regional planning schemes. However, many District Distributors are not classified in a scheme and control of development on these roads according to this policy is the responsibility of local governments.
3.3.1 In considering applications for access on regional roads, the effects of the proposals on traffic flow and road safety will be the primary consideration. The more important the regional road, the greater the importance attached to these factors. In general, the Commission will seek to minimise the creation of new driveways on regional roads and rationalise existing access arrangements.
3.3.2 Where regional roads are constructed or planned to freeway standards, no access to frontage development is permitted. On regional roads not constructed or planned to freeway standards, there is a general presumption on traffic and safety grounds against the creation of new driveways or increased use of existing accesses to these roads. Where alternative access is or could be made available from side or rear streets or from rights of way, no access shall be permitted to the regional road unless special circumstances apply.
3.3.3 An arrangement whereby adjoining owners enter into cross-easement agreements to provide reciprocal rights of access across adjacent lots may be required as a means of rationalising access to the regional road.
3.3.4 The types of development that would be allowed access to a regional road include large traffic generators such as major shopping, recreation or community centres. These would justify either a local distributor or access road, leading from a junction with the regional road to car parks servicing the centre.
3.3.5 In determining applications for development involving the formation, laying out or alteration of a means of access to regional roads, the following must be considered:
3.3.6 Where access is permitted, conditions may be imposed prescribing the location and width of the junction or driveway to ensure adequate visibility and to provide for the safe and convenient movement of vehicles both entering and leaving the traffic stream. In determining design requirements for junctions and driveways, the Commission has regard to standards recommended by both the National Association of State Road Authorities and Main Roads Western Australia.
SOLOMON J: I have a question as to whether your view as a planner is - whether there are other parts of the land that might be suitable for other sorts of development. Or is it your view that outside the envelope of the application, it is only suitable for rural?
MR DOUGLAS: I would suggest that everything outside the envelope was only really suitable for rural. We had a massive hill in the northern part of the land that had significant slope. So, we knew that that was constrained. It was really only suitable for grazing of animals. We knew that the rear section behind the - where the proposed development was going to go was flatter ground. We knew that - that again, was only really going to be suitable for rural use. And we also were mindful of there is an extractive industry immediately south that imposes a significant buffer. This land is affected by buffers. It is affected by special control areas. So, there are significant limitations on higher order uses if you know what I mean. So, we have always expected that the balance portions really were only suited for rural use or extractive industry, as reflected in the agricultural resource zoning.
SOLOMON J: So, the fact that there might have been other land outside the building envelope that was not hilly, because the really hilly bit is in the northeast did that flatter land not to the northeast not have development potential beyond rural?
MR DOUGLAS: No. It didn't because it was constrained by buffers. And it was constrained by vegetation to an extent.
SOLOMON J: What do you mean by constrained by vegetation? Any rural land is constrained by vegetation?
MR DOUGLAS: Yes. Well, it was banksia country. So, yes, we couldn't go in there and clear. But it was really ideally suited for rural uses. That is the way we - I see it.
cover the proposed and existing traffic volumes of the Great Northern Highway; but also take into account the suitability of the proposed access, types of vehicles, movement patterns etc. The referral process [MRWA] would identify if the current proposed access and traffic impact statement is acceptable or not.
We request that the Shire withdraw the requirement for the preparation of a traffic impact study as the costs associated with preparing such a report is high and at this state there is no guarantee our client will receive approval for the development. As you are aware, the application only proposed the construction of one (1) crossover to Great Northern Highway and that Main Roads WA are intending to upgrade this section of the Highway. We understand and appreciate that Main Roads WA may require a deceleration lane for the proposed crossover.
In light of the above, we request that the Shire refer the proposal to Main Roads first for comment.
I have been asked to give my opinion, to the extent it is within my professional expertise in relation to the following:
(a) At the date of taking (30 November 2016) were there any crossovers from Lot 195 to Great Northern Highway?
(b) If there was a crossover or crossovers, state whether they were approved by Main Roads and whether they would be suitable permitted to be used for a transport depot and warehouse;
(c) At the date of taking (30 November 2016) would Main Roads have permitted an access to Great Northern Highway for development of the type and scale:
(i) proposed by Instant Products in its application dated 30 June 2015; or
(ii) consistent with the alternative assumptions contained in paragraphs 70 to 74 of the report of Mr Garmony (To be clear, we do not seek your advice regarding the costs assumed by Mr Garmony).
(d) If Main Roads would not have permitted access, why not? If you would have recommended that an access be permitted what intersection treatments, if any, would it have required? Your assessment should ignore the road widening as part of the Public Work. In other words you are to assume that there was no road widening Public Work being undertaken when assessing whether the Main Roads would have permitted an access to Great Northern Highway as proposed by the application for development approval dated 30 June 2015; and
(e) Were you present at the meeting held at the Shire's office on 14 August 2015? If so, please state who else was present, what was discussed and whether any agreement was reached between Instant Products and Main Roads in respect of access to Great Northern Highway.
Great Northern Highway is classified as a Primary Distributor Road by MRWA. It forms part of the major arterial Perth-Darwin National Highway and provides the main connection for freight, commuter and tourist traffic between Perth and the north of the state. This section of Great Northern Highway has a speed zone of 110km/hr and carried 3965 vehicles per day (2015/16 figures). The percentage of heavy vehicles is 23.0%. Great Northern Highway forms part of the RAV 7 restricted access vehicles route, permitting vehicles up to 36.5m long and a maximum mass of 107.5T. The Great Northern Highway also forms part of the 'Over Size Over Mass' route, that caters for loads up to 8.0m wide. The combination of the above means that Great Northern Highway is unique for the area and has been designed and dedicated to the efficient and safe movement of freight as a freight corridor. The traffic on Great Northern Highway expects to travel at high speed with minimised interruptions in free flow and limited congestion. Given the high speed, heavy vehicles are not able to stop, accelerate or decelerate as quickly as passenger cars and limiting the number of conflict points increases the safety for all users. Conflict point include crossovers and intersections.
I have serious doubts as to whether it is open to the defendant to advance this alternative case, given that it purports to rely upon the 'unaffected' scenario but then imports a variation of the very same public work that is excluded in the unaffected scenario.
The immediate contrast is that in the before scenario, there was a pathway by which approval may have been granted for direct access. In the consequence of the public work there is no pathway and no direct access was even contemplated or could, as a matter of law, be granted. Now, that sets up what we say is the argument that gives rise to what we say is the consequential loss ...[128]
Our loss, and it is a loss, occurs on the day on which our land was taken because that's the day on which we go from the prospect of approval of access under regulation 14 to not having any right of access by reason of Section 28.[129]
...
What we say is that we have suffered that loss because from the moment at which the land was taken, we no longer could obtain direct access no matter how good a case we might mount because, legally, it was simply impermissible.[130]
The question that arises is whether, as a matter of construction, a loss of a future business opportunity is loss or damage which is 'sustained' - or suffered - by an individual, or whether sustained has a more limited meaning. Damages for a loss of a chance or an opportunity to obtain a commercial benefit can be awarded in the context of breach of contract claims, in tort and for misleading and deceptive conduct. In such cases, the question of causation is required to be established by the plaintiff on the civil standard of the balance of probabilities. For a breach of contract, the opportunity will usually be established by proving the contract itself. In the context of a tort or misleading and deceptive conduct, the plaintiff must prove on the balance of probabilities that they have suffered some loss. The question of the value of that lost opportunity is then ascertained by reference to the court's assessment of the prospects of success of that opportunity had it been pursued. That is, by reference to the degree of probabilities or possibilities.
The appellants submit that there is no rational basis for adopting a different approach in the context s 241(6) of the LAA. As a matter of statutory construction, we agree that there is no reason in the text of s 241(6)(b) of the LAA, when considered in its statutory context, that would exclude loss or damage for the loss of a commercial opportunity from being loss or damage which is 'sustained' - that is 'suffered'. There is also nothing inherent in the nature of a claim for compensation following the compulsory acquisition of the land which would suggest that a loss which is sustained in the context of a breach of contract, in tort or as a result of misleading and deceptive conduct, would not also be a loss which is 'sustained' in the context of s 241(6)(b) of the LAA.
Accordingly, the trial judge erred in holding that the loss of an opportunity to win additional storage contracts was not loss or damage 'sustained' for the purposes of s 241(6)(b) of the LAA.
(1) for the Taken Land under s 241(2) is $375,000;
(2) under s 241(6) is limited only to the cost of the dam.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[1] See Exhibit A-4.86. The consideration recorded on the transfer was $1,430,000. That figure was inclusive of GST. The valuation evidence proceeded on the basis that the purchase price exclusive of GST was the relevant figure. The defendant's valuer, Mr Srhoy, adopted the figure of $1,300,000. There was no challenge to that figure.
[3] Amended Outline of Plaintiff's Opening Submissions for Trial 1 February 2024, 3.
[5] See explanation from Main Roads Western Australia (MRWA) in its letter to Instant Products dated 4 November 2014, Exhibit A-8.96.
[6] Exhibit E, Further Witness Statement of Scott Cameron Rawson 22 January 2024, 3 [21].
[11] Exhibit H, Briggs J, Cormann M and Price M, 'Building WA Transport Infrastructure for the 21st Century', 6 February 2014.
[16] Exhibit G, Witness Statement of Joseph Carl Douglas 13 July 2022 [8] (Exhibit G).
[32] The prayer for relief at [2] of the Amended Statement of Claim referred to the compensation as claimed 'pursuant to s 241(6) and (7)'. However, at trial the claim for compensation was advanced unambiguously under s 241(6) and any claim under s 241(7) was disavowed.
[33] Amended Outline of Plaintiff's Opening Submissions for Trial, 1 February 2024, 6; The prayer for relief at [2] of the Amended Statement of Claim referred also to 'Professional fees; Quantified separately'. This item was not pursued and was not the subject of evidence.
[37] Exhibit I, Witness Statement of Matthew John Garmony 22 January 2024, 1 (Exhibit I).
[39] Amended Outline of Plaintiff's Opening Submissions for Trial 1 February 2024, 6.
[40] DBW Reynolds as trustee for the DBW Reynolds Family Trust v Public Transport Authority [2025] WASCA 43 (DBW) [15] ‑ [21] and see [152] of these reasons for the effect of the Court of Appeal decision on this matter.
[41] McKay v Commissioner of Main Roads [No 7] [2011] WASC 223 (McKay) [135] - [143].
[47] Exhibit F, Witness Statement of Louie Hancock 19 January 2024 (Exhibit F).
[49] As explained by Instant Products' counsel in opening submissions; ts 87 - 88.
[64] The version provided in evidence as part of the witness statement of Ms Hartley-West was Revision 4B and is marked 'Date amended: 29-Jun-2015'. There was no suggestion that the document was materially different at the time that Instant Products purchased the Property.
[72] Mr Douglas repeated that proposition in cross-examination; ts 189.
[76] Exhibit H 'Building WA Transport Infrastructure for the 21st Century', 6 February 2014 and see [13] of these reasons.
[89] Witness Statement of Janet Hartley-West 24 March 2022 [2] (Hartley-West Witness Statement).
[90] Hartley-West Witness Statement [11].
[92] Hartley-West Witness Statement [12].
[93] Hartley-West Witness Statement [17].
[94] Hartley-West Witness Statement [21].
[95] Hartley-West Witness Statement [18].
[96] Hartley-West Witness Statement [2]; Supplementary Witness Statement of Janet Hartley-West 26 August 2022 [5], [6].
[97] Hartley-West Witness Statement [40] - [41]; Supplementary Witness Statement of Janet Hartley-West 26 August 2022 [7].
[105] Kelliher v Commissioner for Main Roads [No 2] [2015] WASC 478 (Kelliher) [723].
[107] This is a reference to the test laid down in Spencer v The Commonwealth (1907) 5 CLR 418. See also McKay [1503], [2213].
[108] Maurici v State Revenue [2003] HCA 8; (2003) 212 CLR 111 [16].
[111] Garmony Report 2 November 2021, Exhibit A-52(iii).426, Exhibit A-52(iii).430; Exhibit A-53.445.
[113] Mr Garmony adopted without objection use of the standard measure in Australia for the height of land known as the Australian Height Datum.
[118] See Exhibit A-54(i).476 which applied an 'optimistic' rate of $12,500 to whole of the Taken Land based on the purchase of the Property by Instant Products in 2014.
[125] See McKay [377] in particular [377(8)].
[127]Amended Statement of Claim 9 November 2021 [24].
[132] That submission was reiterated in the supplementary submissions filed by Instant Products in May 2025.
[136] Defendant's Supplementary Submissions 29 April 2025 [7].
[137] Defendant's Supplementary Submissions 29 April 2025 [9].
(1907) 5 CLR 418
(2003) 212 CLR 111