Infratel Networks Pty Ltd v Gundry's Telco & Rigging Pty Ltd
[2012] NSWCA 365
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2012-10-24
Before
Hoeben JA, Ward J, Black J, Young JA
Catchwords
- 61 ACSR 321 Hopetoun Kembla Investments Pty Ltd v JPR Legal Pty Ltd [2011] NSWSC 1343
- 21 ACLC 533 Re Seduce Group Australia Pty Ltd [2011] NSWSC 290 Saferack Pty Ltd v Marketing Heads Australia Pty Ltd [2007] NSWSC 1143
- 25 ACLC 1392 Trecomax Pty Ltd v Prentice [2004] FCA 1057
Source
Original judgment source is linked above.
Catchwords
Judgment (9 paragraphs)
Judgment 1HOEBEN JA: I agree with Young AJA. 2YOUNG JA: This is a concurrent hearing of an application for leave to appeal from a decision of Black J in the Equity Division of this Court together with the hearing of the appeal if leave be given. 3Black J dismissed an application brought by the appellant under s 459G of the Corporations Act 2001 (Cth) to set aside a Statutory Demand served on it by the Respondent. However, he later extended the time for complying with the Demand until after this Court had considered the matter. 4The Appellant, both here and below contended that the demand should be set aside for any one of a number of reasons which can be summarised as (a) there was a genuine dispute over the alleged debt claimed (vide s 459H(1)(a)), (b) the appellant had an offsetting claim (s 459H(1)(b)) and (c) the Demand should be set aside as unconscionable (s 459J(1)). 5The Respondent's case was to deny that any of those grounds was applicable. It further alleged that because of what is commonly called the Graywinter principle the application needed to be dismissed. 6Black J found most (but not all) of the contentious matters in favour of the Respondent. 7I need to note some background to the matter. The Appellant had a number of contracts with communication companies such as Telstra and Optus to erect communication towers. The Appellant did not consider that it had the expertise to deal with certain aspects of the rigging of those towers and subcontracted with the Respondent to do that work. 8Unfortunately, neither the head contracts nor the subcontract are in evidence. Indeed even the "Purchase Orders" and "Statements of Work" referred to in the subcontract, if they ever existed, were not in evidence. 9The telecommunication companies complained that there were defects in the work done on the towers: they have declined to pay the Appellant. As will be considered in more detail later in these reasons, after the Appellant had informed the Respondent that its claims would be paid when the Appellant itself was paid, it subsequently took the view that as it appeared that its dispute with the telecommunication companies was a result of defective work and it considered that the defective work was that of the Respondent, it was not going to pay the respondent. 10Indeed, the Appellant itself at least partly performed rectification work. It claims (this is the offsetting claim) $230,963.96, but this includes $125,000.00 described as "Loss of revenue to Infratel personnel rectifying sites". 11The basal document is described as "Instrument of Agreement". The copy in evidence is undated. Both parties accept that its terms bind them. In the Instrument, the Appellant is described as "the Company" and the Respondent as "the Contractor". 12Recital B states: The Company wishes to engage the Contractor to perform agreed Services during the Term of the Contract as requested by the Company. 13The Instrument shows that it was intended that the Appellant would give the Respondent Purchase Orders and Statements of Work. None are in evidence. It is clear that not all the work, which the Appellant was to perform on the communication towers, was subcontracted to the Respondent. The Respondent was to perform rigging work; however, how much and where did not appear in the evidence. 14Special Condition 1 of the instrument is as follows: I) Unacceptable works All costs associated with revisits due to unacceptable works are to be bourne [sic] by the subcontractor. These unacceptable works must be fixed in a timeframe acceptable to Infratel Networks Pty Ltd, otherwise Infratel Pty Ltd will rectify the works, and back-charge the subcontractor. 15The only other provisions of the instrument that need be reproduced are cll 11.4, 13.1, 13.2, 13.9, 13.11, 14, 22.3, 28.1, 28.2, 28.3 which are as follows: 11.4 Subject to clause 11.5, neither party shall be liable to the other under the Contract for any indirect or consequential loss of any kind whatsoever in contract or tort (including negligence), including loss of revenue or profit, loss of opportunity or business interruption, arising out of or in connection with the Contract, 13.1 The value of the Services shall be: (a) an amount calculated by multiplying the relevant rates and/or prices in the Schedule of Rates and Prices by the relevant quantities of the Services provided; less (b) the reasonable costs incurred by the Company in remedying any default by the Contractor of its obligations under this Contract including any Purchase Order. 13.2 If the Company on reasonable grounds disputes the accuracy of any invoice, the Company shall give notice of that fact to the Contractor. Such notice shall state the basis of the dispute and give relevant supporting details. The Company shall pay the undisputed portion of the invoice and may withhold payment of the portion disputed. If the parties cannot resolve the dispute within 30 Business Days of the date of the notice, the Dispute shall be determined in accordance with clause 28. 13.9 Invoice not provided If a valid GST tax invoice for Services is not received by the Company within 90 days of the last day of the month in which the relevant Services were provided by the Contractor, the Contractor shall not invoice the Company for such Services and the Company shall have no obligation to pay for any such Services unless agreed otherwise by the Company. 13.11 Setoff Without prejudice to any other rights the Company may have under the Contract, the Company may deduct from any moneys which are otherwise payable to the Contractor any money which is payable by the Contractor to the Company under the Contract. Nothing in this clause 13.11 shall affect the right of the Company to recover from the Contractor the whole of the debt or any balance that remains owing after any such deduction. 14 Defects 14.1 Should all or any part of the work undertaken by the Contractor as part of the Services be found to be defective, the Contractor shall remedy such defect including any consequential effects of the defect at its own expense in accordance with this Clause 14. Defect includes omissions and faults. The remedying of defects shall be carried out at such times and in such circumstances as directed by Company so as to cause as little inconvenience to the Company, its customers and other contractors as possible. Should the Contractor fail to remedy a defect as described above, or where the defect is affecting a Customer service, or where urgent rectification is required to maintain the operation of the clients network, then the Company may arrange for the defect to be remedied by another party instead of the Contractor and the cost of doing so shall be a debt due to the Company recoverable under Clause 13.1. 22.3 The Company may remedy default: Without limiting any of the Company's other rights in relation to a default under this Contract by the Contractor, the Company may in its absolute discretion elect to remedy such default (including by contracting a third party to undertake any Service or Services terminated under clause 22.2) and whenever the Company so elects, all reasonable costs and expenses incurred by the Company in so doing may be deducted from the relevant Service Charges otherwise payable to the Contractor in respect of the Service or Services to be undertaken by a third party and/or at the discretion of the Company, invoiced to the Contractor for immediate payment, provided that the Company shall not require from the Contractor any amount in excess of the total costs and expenses incurred by the Company in remedying such default. Before the Company may exercise its rights under this clause, it must issue a Default Notice to the Contractor in accordance with clause 22.1 unless the Company determines, in its sole discretion, that the default requires more urgent rectification in which case the Company may immediately exercise its rights under this clause. 28 Disputes 28.1 If a dispute or difference arises in relation to any matter relevant to this Contract including any Purchase Order, the Party requiring the dispute or difference to be resolved must give prompt notice to the other Party of the dispute or difference along with sufficient particulars in order for the other Party to understand the facts and likely quantum of the dispute. 28.2 Following receipt of the notice under clause 28.1, the Company's Authorised Representative and the Contractor's Representative must enter into negotiations with a view to resolving the dispute. 28.3 The Parties may agree for the dispute to be referred or elevated to other representatives of the Parties, and also may agree upon an alternative dispute resolution procedure to resolve the dispute, such as mediation or expert determination, but no Party may commence litigation with respect to a dispute prior to 90 days following the issue of a notice under clause 28.1 in respect of the dispute. 16The Respondent's Statutory Demand covered its Invoices 4, 6, 7, 8 and 9 (for September, October and November 2011) totalling $201,136.67. 17There does not appear to be any challenge to the amount of these invoices. Any dispute relates to whether the amount due under them should be rebated because of the alleged defective work. The rebating would be through the operation of cl 13.11. Alternatively, the dispute is whether the Appellant has an offsetting claim of the same magnitude. 18I should state at this stage that the amount to be rebated, or the offsetting claim, could not exceed $105,963.96 as the remaining $125,000.00 of the claim, the claim for lost revenue, is precluded by cl 11.4 of the Instrument. I note that the primary judge rejected this part of the claim in [35] and [36] of his reasons on the merits. 19Thus, even if the Appellant succeeds in this appeal, the Statutory Demand would only be reduced to $95,172.71, not set aside entirely. 20The concurrent hearing took place on 24 October 2012, Mr M R Aldridge SC and Mr J Baird of counsel appearing for the Appellant and Mr J C Giles of counsel appearing for the Respondent. 21The issues on the appeal can be summarised as follows: (A) Whether there should be leave to appeal. (B) The Graywinter Principle. (C) Did the primary judge apply the proper test as to whether there existed a genuine dispute? (D) Did the primary judge err in his construction of the Instrument? (E) Did the primary judge err in determining that no genuine dispute existed? (F) Did the primary judge err in determining there was no offsetting claim? (G) Should the primary judge have set aside the Statutory Demand because it was unconscionable to allow it to stand? (H) What is the result of the appeal? I will deal with each of these matters in turn, though, as will be seen, some of the issues raise identical considerations.