[2003] VSCA 126
Court of Appeal (Vic)
2003-09-02
ORMISTON and PHILLIPS, JJ.A. and ASHLEY, A.J.A.
Original judgment source is linked above.
[ 2003] VSCA 126
INSURANCE - House contracts guarantee - Insolvency of builder - Building owner's claim for extra costs of completing unfinished work - Policy limitations affecting claims - Dictated by Ministerial Order - Proper construction of policy wording - Whether more than one construction reasonably open - Building Act 1993 s.135, Ministerial Order (G.G. 30/10/98) clause 5.5.6
might blow out without there necessarily being any active dishonesty or deliberate attempt to inflate those costs. The inconvenience to a building owner caused by non-completion is obvious, leading as it almost invariably does to the need to bring new equipment and new workers onto the site and to let a contract appropriate for the completion of works which may well be left in a disorganised state. There would be a temptation, not so much for the building owner perhaps, but more likely for the new builder to add a few "bells and whistles" to the cost of the finishing works, in order to make it a worthwhile contract. Perhaps the Minister saw para.(b) as a means of keeping builders' quotations under some restraint.
HIH Casualty and General Insurance Limited ("HIH") in respect of domestic building work, to the extent of the indemnity provided by that policy. The scheme is administered by the appellant.
"(b) The insurer shall bear no liability for claims arising from non-completion of domestic building work for any reason listed in Item(2) of the definition of Prescribed Cause to the extent that the cost of completing the domestic building work (excluding the cost of rectifying any defective building work) exceeds the contract price specified in the Schedule for the Major Domestic Building Contract by more than 20%."
The issue determined by the Tribunal, and subsequently in the Trial Division, was the meaning and effect of this limitation. The reasons "listed in Item (2) of the definition of Prescribed Cause" included the death, the disappearance and the insolvency of the builder, the third being the relevant one in this instance.
"made under the indemnity for non-completion of domestic building work required by clause 5.1.3 to the extent that the cost of completing the domestic building work (excluding the cost of rectifying any defective building work) exceeds the contract price under the relevant major domestic building contract by more than 20%."
Subject (inter alia) to clause 5.5, the policy was not otherwise to "contain any exclusion or other provision which excludes limits avoids or modifies the requirements of" clause 5 (see clause 5.6) and this was reinforced by clause 8.1 which read:
"The policy is issued in compliance with this Order and if any term of the policy conflicts or is inconsistent with this Order then the policy shall be read and be enforceable as if it complies with this Order."
judgment of Walsh, J. in H. & E. Van Der Sterren v. Cibernetics (Holdings) Pty. Ltd. (1970) 44 A.L.J.R. 157 at 158:
"The terms of exception clauses must sometimes be read down if they cannot be applied literally without creating an absurdity or defeating the main object of the contract ... . But such a modification by implication of the language which the parties have used in an exception clause is not to be made unless it is necessary to give effect to what the parties must be understood to have intended."
It matters not whether the reference to the intention of "the parties" be understood as referring in the instant case to the intention of the parties to the insurance contract or to the intention the Minister when making his Ministerial Order: either way, I am quite satisfied that the intention may fairly be culled from the context and that it favours the construction placed upon the limitation provision by the Tribunal.
"the cost of completing the domestic building work[5]" (`the first factor')
"the contract price specified in the Schedule for the Major Domestic Building Contract by more than 20%" (`the second factor').
"The Owner must pay the Builder the Contract Price set out in Item 2 of Schedule 1."
"The Insurer shall provide a Certificate of Insurance in the form or to the effect of the form contained in Schedule 2 of the Current Order... evidencing a policy issued in compliance with the Current Order in respect of the policy: (a) to the insured immediately upon issue of the policy;"
"to the extent that the costs of completing the domestic building work... exceeds the contract price under the relevant major domestic building contract by more than 20%."
"Subject to clauses 5.5 and 7, the policy shall not otherwise contain any exclusion which excludes, limits, avoids or modifies the requirements of this clause 5."
"The policy is issued in compliance with this Order and if any term of the policy conflicts or is inconsistent with this Order then the policy shall be read and be enforceable as if it complies with this Order."
There was a provision to that general effect in the policy: GP (3.).
[1] The relevant Order has now been amended.
[2] The certificate, headed Schedule 2, reflected Schedule 2 to the Ministerial Order which is mentioned below.
[3] It is called "major" because the value of the work to be done exceeded $50,000.
[5] Excluding the cost of rectification work.
[6] I say "would arise" because so far the litigation has proceeded upon the construction issue alone.
[7] I shall, for sake of convenience, describe it as "the policy".
[8] As to which see the definition of "schedule" in the policy.
[9] And clause 8.9.1 of the Ministerial Order.
[11] [1985] HCA 7; (1985) 156 CLR 274 at 294 per Brennan J
[12] See Johnson v American Home Assurance Company (1998) 182 CLR 266 at 274 per Kirby J, who dissented in the result.
[14] (1987) 11 NSWLR 404 at 421-424, per McHugh JA, dissenting in the result.
[15] [1996] VICSC 11; [1996] 2 VR 613 at 625, per Phillips JA.
[16] [1998] HCA 28; (1998) 194 CLR 355 at 384 per McHugh, Gummow, Kirby and Hayne JJ.
[17] (2003) 198 ALR 1 at footnote 94 per Heydon J.
[18] [1986] HCA 82; (1986) 161 CLR 500 at 510.
[20] The purpose of the relevant provisions of the Building Act 1993, bearing in turn on the Ministerial Orders and the policy, was described by Eames JA, in whose Reasons Callaway and Vincent JJA agreed, in HIA Insurance Services Ltd v Davy [2003] VSCA at [36]-[38].
[21] I say "were specified" because the 1998 Orders were revoked and a new Order was gazetted on 20 May 2002. By cl. 17 of the new Order a policy may limit claims for non-completion "to an amount that is not more than 20% of the contract price under the insurable domestic building contract". That clause, expressed in simple language, may have the effect which the appellant attributed to sub-cl. (b). Even if that be so, it does not give an answer to the meaning of sub-cl. (b).
Housing Guarantee Fund Ltd
Dore [2003] VSCA 126