"We refer to the Architects Instructions dated 29th May 1974 (this
date should be 31 May) enumerating the outstanding items to be
completed or made good by W. Curl & Sons in their subcontract with
you for the Mechanical Services at the Adelaide Festival Theatre.
Some of the items have been completed, but we hereby give notice
in accordance with Clause 1(c) of the Conditions of Contract that
unless you, within 7 days, comply with our instructions to commence
the work of making good the remainder of the items and diligently
proceed with this work, the Proprietor will employ and pay others to
execute any work whatsoever which may be necessary to give effect to
our instructions and all costs properly incurred in connection
therewith shall be recoverable from you by the Proprietor."
Further correspondence ensued between the architect and the
builder culminating in a letter of 12 September 1974 from the
architect noting the builder's failure to comply with the
instruction of 3 September and adding:
"We will therefore arrange, on behalf of the Proprietor, to employ
and pay workmen of the Adelaide Festival Centre Trust and others to
execute any work whatsoever which may be necessary to give effect to
those instructions.
Accurate records of the work performed will be kept and all costs
properly incurred in connection therewith will be recoverable from
you by the Proprietor."