[2025] VCC 1115
General information, not legal advice.
County Court of Victoria
2025-08-08
Original judgment source is linked above.
BUILDING CONTRACT - SHOW CAUSE NOTICE - whether Show Cause Notice valid -
hybrid nature of Show Cause Notice - required works to be completed as well as showing
cause in writing - contract did not provide for Show Cause Notice to require work to be completed - whether cause was shown - Hometeam Constructions Pty Ltd v McCauley [2005] NSWCA 303 - Brenmar Building Co Pty Ltd v The University of Newcastle (1999) 15 BCL 467 - Re Stewardson Stubbs v Collet Pty Ltd & Bankstown Municipal Council [1965] NSWR 1671.
BUILDING CONTRACT - whether variations established - turns on own facts.
(a) Show Cause Notice Issues (regarding the validity and effect of the Show Cause Notice); and
(b) Danpalon Costs Issues (regarding the amount payable under the Subcontract after Danpalon supply and installation was removed from the scope of the Subcontract.)
(a) Subcontract Reference Table;
(b) Subcontract Conditions;
(c) Schedule 1 - Document Register of Drawings, Plans and Specifications;
(d) Schedule 2 - Subcontract Scope of Work;
(e) Schedule 4 - Construction Program; and
(f) the drawings referenced in Schedule 1, including the architectural drawings prepared by Kosloff Architecture dated 25 August 2020.
1.1 The Subcontractor must carry out the Works described in the Subcontract for the Subcontract Price to a high standard of skill and care and to H. Troon's reasonable satisfaction in accordance with:
(a) the Subcontract Scope of Works, Specifications and Drawings attached or otherwise referred to in this agreement;
(c) H. Troon's Construction Program attached in Schedule 4;
(d) all reasonable directions and requirements of H. Troon and, if applicable, those of the Superintendent under the Head Contract; ...
The Subcontractor must ensure that it supplies sufficient labour and materials to achieve and maintain progress of the Works in a timely and efficient manner strictly in compliance with the Construction Program attached in Schedule 4 (as amended and issued from time to time to meet target dates) ...
24.1 If the Subcontractor commits a substantial breach of this Subcontract H. Troon may give the Subcontractor a written notice to show cause. This show cause notice shall:
(a) state that it is a notice under clause 24 of the Subcontract Conditions;
(b) specify the alleged substantial breach;
(c) require the Subcontractor to show cause in writing why H. Troon should not exercise a right referred to in clause 24.2;
(d) specify the time and date by which the Subcontractor must show cause (which time shall not be less than 5 clear days after the notice is given to the Subcontractor); and
(e) specify the place at which cause must be shown.
24.2 If by the time specified in a notice under clause 24.1 the Subcontractor fails to show reasonable cause why H. Troon should not exercise a right referred to in this clause H. Troon may by notice in writing to the Subcontractor:
(a) take out of the hands of the Subcontractor the whole or part of the Work remaining to be completed; or
(b) terminate the Subcontract.
24.5 For the purpose of this clause 24, a substantial breach includes but is not limited to where the Subcontractor:
(a) ...
(b) fails to proceed with the Works regularly and diligently and in a competent manner including in accordance with the Construction Program;
(c) fails to comply with a direction from H. Troon;
(d) commits any substantial or material breach of this Subcontract; or
(e) ...
Complete Construction of the Roofing Package including supply labour, materials, plant and equipment. All in accordance with the Standards, Drawings, Specifications, Reports and Subcontract Post Tender Review minutes. The works for this package includes, but is not limited to the following: -
5. Supply & Installation of polycarbonate roofing as per plans
24. All works to be watertight and free from leaks
(a) did not complete the Works as adjusted by the 2020 Variations and the Danpalon Installation Variation (the Varied Works) on or before 19 January 2021, or at all; > > (b) failed to proceed with the Varied Works regularly and diligently and in a competent manner including in accordance with the Construction Program; > > (c) failed ensure that it supplied sufficient labour and materials to achieve and maintain progress of the Varied Works in a timely and efficient manner strictly in compliance with the Construction Program.
By 23 March 2021 Obsidian had failed to complete or make any substantial progress completing the following aspects of the Varied Work:
(IV(i)) completion of flashings to the low-level amenities roof;
Through the period December 2020 to 23 March 2021, Obsidian failed to provide sufficient labour onsite to maintain progress of the Varied Works including as recorded in the following emails:
11A. The breaches referred to in paragraph 11 hereof were 'Substantial Breaches' within the meaning of that term in clause 24.5 of the Subcontract.
As at 30 March 2021 Obsidian had failed to complete or make any substantial progress completing:
(IV(i)) completion of flashings to the low-level amenities roof;
The breaches in the Show Cause Notice were the subject of correspondence between H.Troon and Obsidian as follows:
(i) In an email from Tony Shao (Obsidian) dated 23 March 2021 at 4:08pm, Obsidian responded to the Show Cause Notice.
(iii) In an email from Tim O'Callaghan (H.Troon), to "Cary" (Obsidian) dated 26 March 2021 at 7:50am attached images of missing handrails.
(iv) In an email from Tony Shao to Tim O'Callaghan, cc: Riley Pascoe (H.Troon) and James Troon (H.Troon)) dated 28 March 2021 at 8:13pm.
(v) In an email from Riley Pascoe to Tony Shao dated 29 March 2021 at 4:17pm.
(vi) In an email from Tony Shao to Riley Pascoe, 'Cary' and Tim O'Callaghan dated 30 March 2021 at 1:17am.
10. It denies the allegations in paragraph 8 on the basis that on or about 15 December it was agreed between the Plaintiff and Defendant that due to the structural and design faults (as particularised in paragraph 13), the Completion Date pursuant to the Subcontract would be varied to a future date, where that future date would be the day on which the Plaintiff completed and rectified all Structural and Design Faults plus the period of thirty five (35) working days ("Amended Completion Date Agreement") as provided for in the Construction Program.
(a) The Structural and Design faults included amongst other things inherent design flaws, structural defects and incomplete structural works with the Plaintiff's roofing and cladding works which was caused by the Plaintiff and which the Plaintiff failed to rectify or complete in a timely manner.
(b) These structural, installation defects and design issues included but were not limited to:
(i) The flashing detail at the bottom of the Aramax cladding was not completed to the required standard set by the architect Mr Lance van Maanen. The detail was fully functional, but its appearance was not to the required standard set by the architect.
(iii) The pergola roof to the East side of the building was not completed till on or around the 6th of April 2021, after the Take Out Notice was issued.
(iv) The flashings to the West Elevation Aramax could not be completed due to the lack of Fibre Cement sheeting that was required as a substrate to support the flashing.
(v) The East and North Elevation Aramax was not completed by the 30th of March, but the Defence maintains it is within time of its contractual obligations to complete the works.
(vii) The North Elevation required access was well, as it sits above the low-level amenities roof. Emails were exchanged to find a solution, but Htroon never approved a method for this to go ahead before the Take Out Notice was issued. Obsidian proposed the use of aluminium scaffolding built on top of plywood sheeting in order to protect the low-level amenities roof from any damages, but was not yet approved.
This is a notice under clause 24 of the Subcontract Conditions. Obsidian Roofing Pty Ltd are in substantial breach of the subcontract as they have failed to proceed with Works regularly and diligently and in a competent manner including in accordance with the Construction Program.
H. Troon has no choice but to protect the interests of the head contract by taking out of the hands of the Subcontractor the Works remaining to be completed should the following not be completed by 5pm on the 30th of March 2021.
Completion of Aramax wall cladding installation to the East, West and North elevations including associated flashings.
Gutter installation to Low level amenity roof and High-level gymnasium roof and front entry roof, including downpipes connected to stormwater points.
Completion of all flashing to the high-level gymnasium roof.
Completion of flashings to the low-level amenities roof.
Rectify all current water leaks from roof penetrations to gymnasium roof and amenities roof.
H. Troon requires you to show cause in writing via email to James Troon james@htroon.com.au. Show cause must be provided by 5.00pm, 30th of March 2021.
A. Did the 'Show Cause Notice' specify the alleged substantial breach?
(a) a practical approach is to be taken to the construction of default notices and that they must be interpreted with business common sense;
(b) the question of whether the notice is valid is to be determined objectively by reference to the understanding of a reasonable recipient;
(c) in considering this question, the notice must be construed considering the relevant objective "contextual scene."
...both authority and common sense...fully support the view that to inform the builder that he has not been proceeding with the general task which he has been given - not with a particular item - in a competent manner or with reasonable diligence is a sufficient specification.
The question still remains, however, whether the notice "specifies the default". It has been argued it is not sufficient merely to refer to the failure to proceed with reasonable diligence. A default can be specified in two ways; one is by directing attention to the provision in the contract in respect of which default is made. The other is by giving particulars of the manner in which a breach has occurred. In order to specify the default, I think at least the former must be pointed out. But each case will depend on its own circumstances as to whether in order to specify the default there must be added some particulars such as will identify the particular breach alleged. Thus, a default under sub-clause (3) may well require some further specification so that the builder is put in the position to discontinue the default which is complained of. Somewhat different considerations apply with regard to sub-clauses (1) and (2) where the mere reference to the clause said to be in breach may be sufficient to specify the default. For example, to state that the works had been wholly suspended surely would specify the default. The question of what precisely constitutes a failure to proceed with reasonable diligence is a matter of some difficulty. However, it is an allegation of a general failure to proceed with that degree of promptness and efficiency that one would expect of a reasonable builder who has undertaken a building project in accordance with the terms of the contract in question.
(a) clauses 1.1(c) and 1.10 of the Subcontract that required Obsidian to carry out the Subcontract Works in accordance with the Construction Program in Schedule 4 of the Subcontract (which called for commencement of the Subcontract Works by 21 November 2020 and for their completion by 19 January 2021) and required Obsidian to resource the those works with sufficient labour to achieve that;
(b) the fact that Obsidian had commenced its works under the Subcontract on 13 November 2020;
(c) the provisions of clause 24 of the Subcontract including clause 24.5;
(d) the repeated complaints by H. Troon in writing about the progress of the Varied Works and its resourcing of those works;
(e) the specific complaints by H. Troon in writing about Obsidian's failure to comply with the Construction Program;
(f) the absence of any meaningful response from Obsidian explaining its failure to meet the Construction Program or to resource the carrying out of the Varied Works to achieve compliance with the Construction Program;
(g) H. Troon's repeated requests for a revised program from Obsidian explaining when Obsidian considered it would be able to complete its works and how it proposed to achieve this;
(h) the absence of any meaningful response from Obsidian in response to those requests;
(i) the incomplete state of the Varied Works as at 23 March 2021.
Obsidian wholly rejects the allegations that HTroon have put forward alleging breaches of contract by Obsidian Roofing.
If there exists such breaches, HTroon are required to prove them with evidence, otherwise this shall deemed to be unsubstantiated. HTroon have 5 business days to provide Obsidian with any evidence for breaches of contract.
Obsidian have worked diligently on this project since the beginning despite multiple failures from Htroon to deliver compliant steel structures as per architectural drawings and engineering drawings. Some of these images of the roof have already been demonstrated to Htroon, to which Htroon have not provided any feedback to why they have delivered non-compliant work as per Australian Standards or per architectural and engineering drawings.
It is relevant, however, to note that while Mr Goulding's response to service of the Notice of Default was to raise what, to my mind, were technical quibbles with its wording, it is clear from the balance of his 24 July letter that he understood the assertion in the Notice of Default. He sought both to challenge the proposition there had been any relevant delay as well as to assert what work had been done between 12 - 20 July and what work was to be undertaken shortly, by way of an assertion that "the alleged breach has been remedied".
where the Subcontractor...fails to proceed with the Works regularly and diligently and in a competent manner including in accordance with the Construction Program;
B. Was Obsidian in substantial breach of the Subcontract for the reasons specified in the Notice when the Notice was sent on 23 March 2021?
To proceed continuously, industriously and efficiently with appropriate physical resources so as to progress the works steadily towards completion substantially in accordance with the contractual requirement as to time.
...a sensible commercial construction...is that the actual extent of work completed is of some significance. "Diligence" in this contract means, it seem to me, not only the personal industriousness of the defendant himself, but his efficiency and that of all those who worked for him.
I am entitled to accept, as evidence, that reasonable diligence had not been displayed by the defendant, evidence that the work was, at the material time, seriously incomplete, together with evidence that there were no circumstances preventing the defendant from overcoming the situation.
(a) the work the appellant was required to carry out under the Contract; as events transpired this included the original contract works and the rectification work;
(b) what, in addition to the contract period, was a reasonable time within which the appellant ought to have executed the original contract works and the rectification work;
(c) that the appellant had failed to execute the work within that reasonable time;
(d) that, to the extent the appellant proffered explanations of why the work had not been executed within that reasonable time, those explanations were unacceptable.
Secondly, in my view, the respondent was also entitled to seek to prove lack of due diligence by establishing a case of delay in progress during construction. This appears from both Stubbs and Hooker. On this basis she could have established a failure to carry out a reasonable amount of work by a given time; that that period of time be measured by reference to all the work to be performed under the Contract or, in absolute terms, by reference to a lack of activity on site over a significant period that could not be satisfactorily explained. The onus of proving lack of due diligence was on the respondent. If the facts established by the respondent are capable of giving rise to an inference of lack of due diligence, the appellant may discharge any evidentiary onus that may pass to it, by explaining why the work progressed at that rate: see Hobbs. That evidence should be "sufficient ... to turn the scale": Brady v Group Lotus Car Cos plc [1987] 3 All ER 1050 at 1059 (CA) per Mustill LJ.
Obsidian has not established that the slow progress of the Varied Work and the seriously incomplete state of those works at the 23 March 2021 was a consequence of factors for which it was not responsible.
Obsidian claims it delayed in completing some aspects the Varied Work by structural defects and incomplete structural works that, it says, H. Troon was responsible for. Obsidian relies on two such alleged structural defects or incomplete structural works:
(a) a flashing detail at the bottom of the Aramax cladding that is said not to have been to the "required standard set by the architect" in appearance;
(b) the lack of a fibre cement substrate said to have prevented completion of flashing to the west elevation Aramax wall.
Obsidian also appears to claim it was delayed in carrying out the north wall Aramax cladding by H. Troon's failure to approve Obsidian's proposed methodology for the installation of that cladding.
The evidence produced by Obsidian at trial does not support its these claims.
The evidence produced by Obsidian in support of each of them is dealt with below.
No evidence was led by Obsidian that the Aramax flashing detail was not to the "required standard set by the architect" in appearance or in any other respect.
Vague evidence was given by Mr DeWit that he had made suggestions to the architect to improve an unspecified Aramax flashing detail and that this suggestion was agreed to by the architect.
When asked by Her Honour how much the process of changing the flashing detail had delayed the project, Mr DeWit initially responded that he could not be certain. After prompting by Dr Shao and being taken to several emails, Mr DeWit revised his answer to say that the process of changing the flashing detail delayed the project by "at least a week" and then he further revised his answer to say that it may have been "several weeks".
Taken at its highest then, the evidence relied on by Obsidian establishes only that it was delayed "several weeks" because of a design change to the Aramax flashing that it initiated.
It called no admissible expert evidence that would tend to establish that the design change was required because of deficiencies in the work of H. Troon or its agents.
The FC sheet that Obsidian complained had not been installed by H. Troon is highlighted in the following snapshot from "Detail 4 West Wall Junction Detail" in architectural drawing A4-101 at CB 225:

While H. Troon acknowledges that it was its responsibility to install the FC sheet, the evidence shows Obsidian's work to the west wall Aramax was never sufficiently advanced to permit that to be done.
Mr De Wits evidence under cross examination was that a necessary precondition for the placement of the FC Sheet by H. Troon was Obsidian first cutting the rake of the West wall Aramax and that Obsidian never completed cutting the rake of the West wall during its time onsite.
This evidence thus shows that it was the slow progress the installation of the west wall Aramax by Obsidian that delayed H. Troon's installation of the FC sheet not, as pleaded by Obsidian, the failure by H. Troon to install the FC Sheet that delayed the west wall Aramax fashing.
The evidence is that by email on 9 March 2021 Obsidian proposed a new method for placement of the north wall Aramax involving the construction of scaffolding and that H. Troon's project manager Mr Pascoe responded by email on 11 March 2021 saying that he was happy with the scaffold option and requesting details on how Obsidian was going to fix the scaffolding to the existing framing and how they were going to protect the existing roof as well as offering H. Troon's crane to assist with the installation of the north wall Aramax.
There is no evidence to the effect that H. Troon withheld its approval for the proposed new methodology or that Obsidian was delayed in installing the north wall Aramax by such approval being withheld.
C. Should the Subcontract be construed such that Obsidian had 35 working days to complete the Varied Work, dating from after the last structural component that Troon was responsible for had been completed?
(a) Even if the plaintiff has removed the Pergola roof from Paragraph 11 of the Statement of Claim, it does not change the requirement under the Construction Program, in that, Obsidian has 35 working days from which the last structural component is completed to fulfill its contractual obligations.
(b) 35 working days past the 6th of April 2021 is the 25th of May 2021. Obsidian under the Contract was entitled to at least the 25th of May 2021 to complete the works, assuming the last part of any structural requirements from Htroon was completed on the 6th of April 2021.
(c) The fibre cement sheeting substrate under the cappings was the responsibility of Htroon and this work was not completed even at the time of the Take Out Notice was issued. Assuming this was also completed on or around the 6th of April, then Obsidian would be entitled to complete the works by the 25th of May 2021.
D. Was there an oral agreement to extend the time that Obsidian had to complete its work?
This confirmation took place on or about the 21 January 2021 in a meeting on Site between Obsidian's General Manager, Mr Cary De Wit, and H. Troon's Project Manager, Riley Pascoe, and it was orally agreed that even though H. Troon had closed the Site for an extended period of time being an extra 14 days over the Christmas period in 2020, the terms of the Subcontract did not need to be amended because the terms of the Amended Completion Date Agreement provided Obsidian with sufficient time to complete the Works.
F. Debt claim for work done by third party instead of Obsidian
24.4 If the cost incurred by H. Troon is greater than the amount which would have been paid to the Subcontractor if the work had been completed by the Subcontractor, the difference shall be a debt due from the Subcontractor to H. Troon.
Obsidian admits that all of the work set out in the daily task list at CB 2977 - 2982 prepared by Tony Hughes of C & L Roofing was completion of work that was within Obsidians scope of works under its Subcontract save for the following items at the top of CB 2981 said to have been carried out on the 6th and 7th of May 2021:
Thurs 6th Toby 7-4, Barry 7-4, Logan 7-4 : DANPAL ROOF
The parties agree that these entries relate to the roofing of the pergola on the east side of the gym. Obsidians position is that the DANPAL was different type of polycarbonate roofing for the pergola and that the cost (or time?) taken to install the DANPAL was different to that which would have been taken installing the roof that Obsidian says was specified in the Subcontract.
H. Troon may at any time direct the Subcontractor to carry out a variation to the Works ("Variation Notice").
Where this agreement provides for a valuation under this clause, H. Troon (and if required in consultation with the Superintendent under the Head Contract) will value the relevant work by reference to:
a) prior agreement in writing;
b) any applicable rates or prices prescribed in this agreement;
c) rates or prices in any priced BOQ or schedule of rates, or prices applying to the Head Contract to the extent that it is reasonable to use them; or
d) reasonable rates or prices as otherwise determined by H. Troon in consultation with the Superintendent under the Head Contract.
H. Troon may, at any time in its absolute discretion by notice in writing terminate this agreement in whole or in part, and H. Troon will be liable to the Subcontractor for:
a) the value of any Works performed by the Subcontractor in accordance with this agreement as at the date of termination;
b) the cost of goods and materials properly ordered as at the date of termination for which the Subcontractor has paid or which it will be bound to pay provided that:
i) the value of the goods or materials is not included in the amount payable under clause 24.6(a) above; and
ii) title in the goods and materials will vest in H. Troon upon payment.
We are happy to pay for the Danpalon/ Aramax orders but we want to be able to make margin on the orders. Can you please work out the required qtys for both aramax and Danpalon and forward over the quotes and we will make payment.
Once you send over quotes we will work out your revised contract value and go from there.
Can you please send over quotes today and we will start getting the orders underway.
Please see attached contract summary for Delacombe Primary factoring in credits and variations.
We will be making payment of Aramax cladding tomorrow for delivery by the end of the week.
Most of those have worked out really well and I appreciate the help.
Just with the Danpalon, that's like way above my original estimate, of $93,090 exc GST, which included labour as well. It's nobody's fault really, this is the problem of pricing Danpalon. So during tender Shane asked me to price this and we only had like 2 days to submit a tender option. Danpal wouldn't even be able to properly price it in that short period, so I used previous projects to estimate. But I also knew that Danpal potentially has a lot of variance between their products depending on the situation. I've seen anywhere between $100 to $400 per sq metre just for material. On this one, this even exceeds that at around $500 per sq metre. In this case, I took on the design risk and it hasn't worked out well.
As it stands, the amount for labour to install Danpal and Aramax is around $29k:

So as a package, it's not a complete disaster. I'm not sure how much margin you guys have in the Danpalon, but comparing it to the other parts, I can't imagine it's a lot. But for now, I'm ok with just keeping all of this as it is. It's not a disaster yet and it's just bad luck with the Danpalon. But I can't lose any more margin with the wall packages.
The East elevation cannot begin until the lower roof on that is done. I've got a question regarding that, is that being done in polycarbonate or Danpal? Tim has said it's in Danpal, however in my contract, it's still written as polycarbonate, so if it is Danpal, then we'll have to do a variation. Did the Danpal you've already ordered for around $133k include that roof?
But essentially, we're happy to break off the Danpalon labour component for $10,000.
Following the failure to comply with H Troon's instruction to commence works associated with the Danpalon cladding, the Danpalon wall cladding works is no longer included in the Obsidian Roofings contract.
The current resource allocation that you have provided on this project has not been adequate since day 1, Obsidian have committed on a number of occasions to increasing resources to ensure the roofing and wall cladding works are being completed simultaneously, this has not been the case. H Troon have provided Obsidian ample opportunity to show they are capable of completing these works within the reasonable timeframe set at contract time, given the current pressure that has been placed on the program as a result, we cannot proceed under the current arrangement. You commenced on site in early November and we still do not have a completed roof.
Obsidian have not failed to commence as per H Troon's instruction. We have lawfully issued a variation that is reasonable and fair in line with the changes that have occurred on this project with regards to the Danpalon. You are not permitted to issue instructions that goes against the contract or the original drawings. It is not a lawful instruction.
If you wish to remove Danpalon from our scope, you are welcome to put forward an offer to Obsidian for our how much that is worth. If we choose to accept, then you may proceed with that element removed from our contract. If you choose to proceed without approval from Obsidian, then you need to pay us for the completed works anyway, as it is part of our contract. Essentially, you will be double paying. If you refuse at the time of completion to pay this obligation, then we'll just take this to court. This is a black and white situation, I'm advising you on what will happen legally on the various paths you want to take.
There does not need to be an offer, the amount you have already confirmed as your allowance and rate for danpalon install will be removed from your contract figure, along with the supply costs already removed as you could not provide the material through the required supplier.
Please be advised in accordance with Clause 24.6 of the subcontract, H.Troon has terminated from the subcontract the installation of Danpalon Wall Cladding to the Southern Elevation of gymnasium.
As no works have commenced in relation to this scope, H.Troon will not be liable for any costs associated with this part of scope.
As no material has been provided for this scope of works by Obsedian, H.Troon will not be liable for any material costs associated.
It has come to our attention that the defendant has been wound-up in insolvency and a liquidator appointed.
We wish to bring this to the court's attention as this event may trigger a stay by way of section 471B of the Corporations Act 2001 (Cth), unless leave is obtained. Should this be the case, neither party objects to leave being granted and judgement proceeding.
471B Stay of proceedings and suspension of enforcement process
While a company is being wound up in insolvency or by the Court, or a provisional liquidator of a company is acting, a person cannot begin or proceed with:
(a) a proceeding in a court against the company or in relation to property of the company; or
(b) enforcement process in relation to such property;
except with the leave of the Court and in accordance with such terms (if any) as the Court imposes.
... it is her Honour's preliminary view that an application for leave for judgement to be delivered does not need to be made under s471B of the Corporations Act, as the Court is not a 'person' under s471B, and in delivering judgment, it is carrying out a function of the Court, not taking a step in a proceeding as a person: Unilever Australia Ltd v Rosella Foods Pty Ltd [2012] NSWDC 221 at [80]- [81]; Sovereign MF Ltd v Compliance and Risk Services Pty Ltd [2013] VSC 213 at [9].
There are arguments to the contrary (that leave is required in these circumstances).
If either the plaintiff or liquidator considers that leave is required, before judgment can be delivered, please advise of this.
The section prevents a step in litigation concerning a company in administration at the instance of the company, if the litigation is in relation to the property of the company, or at the instance of the other party if the company is the defendant- it does not prevent the delivery of judgment in respect of an application already heard, which is a step taken by the Court, not by a party. The solicitors for the plaintiff advise that they have been instructed by the solicitors for the administrator not to take any further step, including attending to receive judgment. On that basis I have indicated I will excuse their attendance, and that of the defendants if they wish.
(a) Judgment for the plaintiff against the defendant.
(b) The defendant pay the plaintiff $178,228.15 plus interest.