[2025] NSWCATAD 214
General information, not legal advice.
NCAT Administrative and Equal Opportunity
2025-08-25
Original judgment source is linked above.
The publication or broadcast of the name or address of the Applicant is prohibited pursuant to section 64(1)(a) of the Civil and Administrative Tribunal Act 2013.
A search of Council records has revealed that no Tree Clearing Permits or Development Consent have been issued for works on the property.
Therefore, the works that are currently being undertaken may be considered as illegal and it is now appropriate that a Stop Work Notice be issued to you as described below, to cease work immediately.
Reason: So that you can provide Council with the necessary information for Council to assess works completed to date and to determine if approval is required for tree clearing, earthworks, building works or any other associated works.
In relation to works that have already been undertaken without approval, Council requires a written response as to why a penalty infringement notice ($3000.00) should not be issued to you as the property owner for undertaking prohibited development. You have the opportunity to respond within 28 days.
2.1.23 I arrived at my block of land to do my usual maintenance, and check of the property. [Two named Council officers] discussed my private information with neighbours, and they placed letters addressed to me on my bin and my front fence for the whole of Tweed Heads to see. This was deliberately done.
I am mortified. I am going to be living there in the future, and all the neighbours are calling the council, and watching my every movement. Every time I attend my property, they call the council and tell them that I am breaking the stop work notice, when I just regular property maintenance, that I was doing every 2 weeks until this council displayed my personal business ...
I want them to stop leaving my private information for the world to see. They need to apologize to me, and they need to compensate me for damages to my reputation.
"Breach of my personal information to members of the public and left personal information on my front fence and bin for 2 weeks for the whole of the world to see and record."
If you do not receive a response by 14 March 2023, you may lodge an external review with the NSW Civil and Administrative Tribunal (NCAT). You have 28 days (from 14 March, 2023) to apply to NCAT for an external review of the conduct or decision complained about (refer to Rule 24 of the Civil and Administrative Tribunal Rules 2014). In other words, your application to NCAT must be made within 88 days after you lodged your internal application with the agency.
We note that an exception under the PPIP Act applies in relation to compliance action, namely:
s23(5) A public sector agency (whether or not a law enforcement agency) is not required to comply with section 18 if the disclosure of the information concerned -
(a) is made in connection with proceedings for an offence or for law enforcement purposes (including the exercising of functions under or in connection with the Confiscation of Proceeds of Crime Act 1989 or the Criminal Assets Recovery Act 1990), or
(b) is to a law enforcement agency (or such other person or organisation as may be prescribed by the regulations) for the purposes of ascertaining the whereabouts of an individual who has been reported to a police officer as a missing person, or
(c) is authorised or required by subpoena or by search warrant or other statutory instrument, or
(ii) in order to investigate an offence where there are reasonable grounds to believe that an offence may have been committed.
We note that the stop work notice was issued following an onsite investigation of illegal tree cleaning (council reference ...). Council had received notice of land clearing on your property and was required to investigate this.
The investigation ultimately resulted in an infringement notice being issued under the Environmental Planning & Assessment Act 1979 No. 203 Clause 4.3(a). The legislative considerations were:
● Chapter 2 of State Environmental Planning Policy (Biodiversity and Conservation) 2021 contains planning rules and controls for the clearing of vegetation in non-rural areas. This chapter applies to the R3 Medium Density Residential zone, in which the clearing of trees at your property has occurred.
● At the site inspection undertaken by Council's Environmental Planning Officer and Compliance Officer, the officers observed and made record of several trees that had been cleared that qualify as prescribed vegetation under Council's DCP A16 - Preservation of tree or Vegetation, and a permit from Council was required prior to removal.
● Under section 4.3 of the Environmental Planning and Assessment Act 1979 No 203, if an environmental planning instrument provides that - a) specified development is prohibited on land to which the provision applies, or b) development cannot be carried out on land with or without development consent, a person must not carry out the development on the land.
The stop work notice was issued under Schedule 5, Part 1 (General Order) Order No. 2 of the Environment Planning and Assessment Act 1979. Under this order, the notice is to be given to the owner of the property. Therefore, Council addressed the stop work notice to the property owner to ensure the notice was valid.
Under the Government Information Public Access Regulation 2018, Schedule 1(4)(e), information contained in records of orders given under the authority of any other Act, is prescribed as open access information. In Part 2, Division 1(6) of the Government Information (Public Access) Act 2019, open access information can be made publicly available in any other way that the agency considers appropriate.
We note that there is a public interest in upholding our compliance policy and the legislation referred to above. We believe that the risk of public access to the information was low in that a person would need to be passing by the property and make an effort to get closer to the letter to enable them to read the addressee details. As the Christmas closure period was approaching, and we were unable to contact you by telephone or email, despite numerous attempts, it was necessary for the stop work notice to be clearly displayed on the property as notice to yourself, workers and/or contractors so that further breaches of the relevant legislation did not occur.
Despite our protections under the exception noted above, Council has taken this opportunity to improve our practices. In the future, the owners postal address (if different to the property address) and email address will be not viewable on stop work notices that are attached to the subject site.
If you are unhappy with this decision, you may lodge a review with the NSW Civil and Administrative Tribunal (NCAT) in accordance with section 53(8)(c) of the PPIP Act. You have 28 days to apply to NCAT for a review of the conduct or decision complained about (refer to Rule 24 of the Civil and Administrative Tribunal Rules 2014).
I refer to your letter on 13.3.23 where you justify the appalling deliberate and malicious privacy breach, and the bullying and harassment performed by [a named office], who's motto is, "WE DO WHAT WE WANT". ...
I am writing to formally advise that I never received the letter referenced in your correspondence. ...
(1) If a person who has made an application for internal review under section 53 is not satisfied with -
(b) the action taken by the public sector agency in relation to the application,
the person may apply to the Civil and Administrative Tribunal for an administrative review under the Administrative Decisions Review Act 1997 of the conduct that was the subject of the application under section 53.
(d) accompanied by the applicable fee (if any) for the application.
(2) An administrative review application need not specify the Division of the Tribunal to which the function of determining the application is allocated by the Act. However, if the appropriate Division is not specified or an incorrect Division is specified, a registrar may complete or alter the application form accordingly.
(3) Unless the Tribunal grants an extension under section 41 of the Act, an application must be made -
(a) in the case where enabling legislation specifies the period within which the application is to be made - within the period specified, or
(b) in any other case - by the end of the default application period.
(4) The default application period for the purposes of subrule (3)(b) is -
(a) in the case where the applicant has duly applied for an internal review of the administratively reviewable decision under the Administrative Decisions Review Act 1997 - the period of 28 days after the day on which the internal review is taken to have been finalised under section 53(9) of that Act, or
(a1) in the case of an administrative review application under section 55 of the Privacy and Personal Information Protection Act 1998 - the period of 28 days after -
(i) if an internal review under section 53 of that Act is completed within 60 days from the day on which the application for the internal review was received by the public sector agency concerned - the day on which the applicant was notified of the result of the internal review, or
(ii) if an internal review under section 53 of that Act is not completed within that 60-day period - the day on which the 60-day period expires or the day on which the applicant was notified of the result of the internal review (whichever is the later), or
(b) in any other case - the period of 28 days after -
(i) if the applicant has requested reasons under section 49 of the Administrative Decisions Review Act 1997 for the administratively reviewable decision - the day on which the applicant was either provided with a statement of reasons under section 49 of that Act or notified under section 50 of that Act of a refusal to provide reasons, or
(ii) if the applicant has not requested reasons under section 49 of that Act - the day on which the applicant was notified of the making of the administratively reviewable decision.
(1) The Tribunal may, of its own motion or on application by any person, extend the period of time for the doing of anything under any legislation in respect of which the Tribunal has jurisdiction despite anything to the contrary under that legislation.
(2) Such an application may be made even though the relevant period of time has expired.
My right to privacy was breached by Council through the misapplication of legislative authority. Council staff justified this breach by incorrectly alleging that I had acted unlawfully, without conducting proper due diligence into the planning history of my property. The entirety of my block is designated as an Asset Protection Zone (APZ) in 2007, and under the Rural Fire Service Act 1997 (NSW) and applicable Bush Fire Environmental Planning and Assessment Codes, I am legally permitted to undertake necessary vegetation management and tree clearing to maintain fire safety for my property and the adjacent townhouses.
On 24 February 2005, planning consultant BP Surveys asked Council to confirm that no further permits were required to clear the necessary 30m APZ. Council confirmed on 1 March 2005 that the clearing required by the consent did not need any further consent.
On 27 November 2007, BushfireSafe Services confirmed that they had carried out a site inspection and the developer had implemented a 20m Inner Protection Zone with a 10m Outer Protection Zone which complied with the Rural Fire Services General Terms of Approval ...
An APZ is a fuel reduced area established to protect a building or an asset. The APZ is to be managed and maintained in accordance with the relevant standards for the life of the development. As such, the clearing at the site is determined to be lawful clearing for the purpose of maintaining the APZ which was required and established ...
Considering the information available ... and Council's outcome in relation to vegetation clearing at the site Council is revoking penalty notice ... issued to you on 20 January 2023, and any monies paid will be refunded to you. Further, Council is revoking any compensatory planting required under condition 2 of the Preservation of Trees or Vegetation Partial Permit issued to you 13 April 2023. Please note however, that clearing outside of the APZ or on a neighbouring property requires consent prior to doing so.
Thank you for your patience and understanding while Council reviewed the site history and the previous investigations undertaken in relation to vegetation clearing the site. ...
The considerations that will generally be relevant to the Appeal Panel's consideration of whether to grant an extension of time in which to lodge a Notice of Appeal include:
(1) The discretion can only be exercised in favour of an applicant upon proof that strict compliance with the rules will work an injustice upon the appellant - Gallo v Dawson [1990] HCA 30, 93 ALR 479 at [2], Nanschild v Pratt [2011] NSWCA 85 at [38];
(2) The discretion is to be exercised in the light of the fact that the respondent (to the appeal) has already obtained a decision in its favour and, once the period for appeal has expired, can be thought of as having a "vested right" to retain the benefit of that decision - Jackamarra v Krakouer (1998) 195 CLR 516 at [4], Nanschild v Pratt [2011] NSWCA 85 at [39] and, in particular, where the right of appeal has gone (because of the expiration of the appeal period) the time for appealing should not be extended unless the proposed appeal has some prospects of success - Jackamarra at [7];
(3) Generally, in an application for an extension of time to appeal the Appeal Panel will be required to consider:
(c) The appellant's prospects of success, that is usually whether the applicant has a fairly arguable case; and
(d) The extent of any prejudice suffered by the respondent (to the appeal),
- Tomko v Palasty (No 2) [2007] NSWCA 369; (2007) 71 NSWLR 61at [55] (per Basten JA) but note also [14], Nanschild v Pratt [2011] NSWCA 85 at [39] to [42]; and
(4) It may be appropriate to go further into the merits of an appeal if the explanation for the delay is less than satisfactory or if the opponent has a substantial case of prejudice and, in such a case, it may be relevant whether the appellant seeking an extension of time can show that his or her case has more substantial merit than merely being fairly arguable - Tomko v Palasty (No 2) [2007] NSWCA 369; (2007) 71 NSWLR 61 at [14] (per Hodgson JA, Ipp JA agreeing at [17]) and Molyneux v Chief Commissioner of State Revenue [2012] NSWADTAP 53 at [58] - [59].The considerations that will generally be relevant to the Appeal Panel's consideration of whether to grant an extension of time in which to lodge a Notice of Appeal include
94 Whilst the discretion to extend time is seemingly unconstrained, its purpose is to ensure that the time limits do not themselves become an instrument of injustice: Gallo v Dawson (1990) 64 ALJR 458 at 459; [1990] HCA 30. Self-evidently, in a case concerning an extension of time to file proceedings, the higher the merits of the underlying proceedings, the higher the risk of injustice, if an extension is not granted. Where the merits of a case are particularly strong, this may override some inadequacy in the explanation for the delay or may, in some cases, trump any prejudice to a respondent, which may, in any event be accommodated or ameliorated with procedural rulings or an award of costs. Accordingly, even if not a relevant consideration (in the requisite sense discussed in Peko-Wallsend) we accept that the merits of the underlying application is material to the ultimate exercise of the discretion to extend time. Accordingly, an error in relation to determination of the merits is capable of providing the warrant for the granting of leave to appeal.
95 Ultimately, the exercise of the discretion requires a balancing exercise; once all of the material factors are known. Accordingly, if an analysis of merits has gone awry, that may be something that could undermine the decision-making; even where other factors do not favour the grant of an extension of time. This is particularly the case where the prejudice to the Appellant is to be shut out of administrative review entirely.
96 The Tribunal was required to exercise the jurisdiction which required determining whether or not an extension of time should be granted. An aspect of that was to form a view about the merits of the underlying application. This, in turn, required the Tribunal to grapple with the competing evidence and submissions, at least at a high level for the purposes of the application for an extension of time. We note that the material was said be voluminous. We are not here suggesting that a full merits review was necessary; that would be the subject of the substantive application. Nonetheless, some assessment of merits must be undertaken.
34. In Jackamarra v Krakouer [1998] HCA 27, Brennan CJ and McHugh J at [7] referred to the necessity for an appellant seeking an extension of time in which to appeal to demonstrate that the "proposed appeal has some prospects of success." ...
35. It is also necessary to refer to a decision of the Supreme Court of Victoria Appeal Division in Dix and Another v Crimes Compensation Tribunal [1993] VicRp 21. Brooking J, with whom Fullagar and Tadgell JJ agreed said:
... the principles laid down by Wilcox J in Hunter Valley Developments Pty Ltd v Minister for Home Affairs and Environment [1984] FCA 176; (1984) 58 ALR 305 concerning the exercise of the power to grant an extension of time under s11 of the Commonwealth Administrative Decisions (Judicial Review) Act 1977. ...
"(a) Although the section does not, in terms, place any onus of proof upon an applicant for extension, an application has to be made. Special circumstances need not be shown, but the court will not grant the application unless positively satisfied that it is proper so to do. The 'prescribed period' of 28 days is not to be ignored ... Indeed it is the prima facie rule that proceedings commenced outside that period will not be entertained ... It is a pre-condition to the exercise of discretion in his favour that the applicant for extension show an 'acceptable explanation of the delay' and that it is 'fair and equitable in the circumstances' to extend time ...
My claim has some prospect of success for the following reasons:
Council will not be prejudiced by the delay because:
(a) the Respondent inspection confirmed that tree clearing had been undertaken on the Property;
(b) Respondent was of the view that the tree clearing required approval; and
(c) a search of Respondent's records indicated that no approvals had been issued for the clearing works.
(c) failed attempts to contact the Applicant by telephone and email.
(c) any relevant prejudice that would be suffered by the Respondent as a result of time being extended; and
(a) The Applicant asserts that there is "new evidence" which was "not known or reasonably knowable to me at the time of the original review and therefore constitutes new evidence".
(b) The new evidence is said to be contained in a letter from Council to the Applicant dated 22 July 2024 (2024 Letter). This letter advised of the outcome of an investigation by Council into alleged unauthorised clearing on the Property on 18 May 2024.
(c) In summary, the investigation found that the clearing undertaken in May 2024 was determined to be lawful. This was because Council had established that the maintenance of an asset protection zone was required under a development consent granted in respect of the Property on 10 February 2005, and the clearing was for that purpose.
(d) Based on that finding, the 2024 Letter also advised the Applicant that Council revoked its previous enforcement action/steps in respect of clearing on the Property which, at that earlier point in time, it had understood to be unauthorised.
(e) According to the Applicant, because of the matters communicated to her in the 2024 Letter about the permissibility of clearing on the Property, the Internal Review Decision "relied on inaccurate and incorrect legislative grounds, rendering it materially flawed".
(1) the correctness of the decision to issue the Order in 2022, having regard to "new evidence" she received in 2024; and
(2) the correctness of the Internal Review Decision in respect of alleged privacy breaches.
Repeated Attempts to Raise the Matter with Relevant Authorities (Reason 2)
(a) In the Extension Request, the Applicant refers to various communications she sent to Council and other bodies regarding the content of the 2024 Letter.
(b) For the reasons set out above, the information in the 2024 Letter is irrelevant for present purposes. In any case, the communications referred to by the Applicant did not prevent her from making an Application, and do not excuse the lengthy delay in doing so.
Instructions from Privacy Commissioner to Lodge New Complaint (Reason 3)
(a) The basis upon which the Applicant seeks to justify the delay, in paragraph 3 of the Extension Request, is not entirely clear.
(b) The Applicant states that she requested Council to conduct a "fresh review" based on "new evidence" (the 2024 Letter), but Council did not do so. Instead, the Applicant submits that Council responded to that request for a fresh review on 13 April 2025 by "re-issuing the same internal review outcome from 13 March 2023, thereby ignoring the new evidence."
Procedural Fairness and Interests of Justice (Reason 4)
(i) "The serious privacy breach involved public display of personal data" ...
(ii) "The subsequent identity theft, defamation, harassment, intimidation and bullying and by both Tweed Shire Council Employees and neighbours and financial losses exceeding $525,000, which does not include the PTSD suffered as a result".
The Applicant has provided no evidence to establish any of the above matters.
(iii) "The new evidence proves that Council staff applied the wrong legislative framework in the original decision".
Again, this statement appears to be an impermissible attempt to agitate matters in the 2024 Letter. ...
(iv) "I have made consistent, diligent efforts to resolve the matter without judicial intervention"
Any relevant prejudice that would be suffered by the Respondent as a result of time being extended
Section 41 of the NCAT Act confers discretion on the Tribunal to extend the time in which an application may be made. That discretion is unfettered but must be exercised judicially having regard to established principle. In short summary, time limits are to be strictly enforced unless to do so would work an injustice to an applicant. The relevant considerations are the length of the delay, the applicant's explanation for the delay, any relevant prejudice that would be suffered by the respondent as a result of time being extended, and the merits of the applicant's claim. In this last respect, if the delay is relatively short, it is necessary for the applicant to show that their claim is fairly arguable. If the delay is lengthy, the applicant must show that their claim has substantial merit: Jackson v NSW Land and Housing Corporation [2014] NSWCATAP 22.
(1) The Applicant's claim is misconceived. It is clear from the material relied upon by the Applicant that she is seeking to air complaints about the Respondent which are irrelevant and/or beyond the jurisdiction of the Tribunal in these review proceedings.
(2) The Applicant's claim cannot overcome the findings of the Internal Review Decision itself, including:
(a) exemptions which apply to Council under section 25 of the PPIP Act when exercising functions as an enforcement authority; and
(b) public interest considerations which were required to be weighed up by the Council, including the context in which the Order was issued.
(3) In deciding whether or not section 25 is applicable the Tribunal is not required to go so far as to make a "microscopic comparison" of an alternative law to which an agency refers in justification: As acknowledged in PN v Department of Education and Training (GD) [2010] NSWADTAP 59 at paragraph [54].
(4) It is sufficient for present purposes to note that Council is a regulatory authority with powers to investigate matters which are alleged to amount to a breach of the EPA Act, and that its investigative powers extend to formal action which includes the issue of Stop Work Orders.
(5) In the present case, public considerations included Council's role in enforcing compliance with the EPA Act with some urgency, to ensure no further clearing was undertaken on the Property, with potentially irreparable harm caused to the environment.
(1) The application for an extension of time in which to make the application is refused.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
GZY
Tweed Shire Council [2025] NSWCATAD 214;