[2025] VCAT 944
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-10-23
Mr J
Original judgment source is linked above.
(a) carried out in a proper and workmanlike manner and in accordance with the plans and specifications set out in the building contract;
(b) that all material to be supplied for use in the Works will be good and suitable for the purpose for which they are used and that, unless otherwise stated in the contract, those materials will be new;
(c) carried out in accordance with, and will comply with, all laws and legal requirements;
(d) carried out with reasonable care and skill; and
(e) the Works would result in a home that was suitable for occupation at the time the Works were completed ('Warranties').
In considering whether it would be unreasonable to award the cost of rectification, the Tribunal should consider all the circumstances of the case before it. The nature and significance of the breach should be looked at in terms of the bargain the parties had and the relative importance of the breach within the context of the contract as a whole. The decision in Ruxley[4] suggests that account can be taken of the following matters at least:
(i) Whether and to what extent the work, although not in conformity with the contract, is nonetheless serviceable;
(ii) Whether and to what extent the defect has affected the value of the work or the building as a whole;
(iii) The cost of rectification, the proportion that the breach bears to the cost of rectification and whether the cost of rectification would be wholly disproportionate to the real damage suffered by reason of it;
(iv) The likelihood that, if rectification cost is awarded, the sum so ordered will actually be spent on rectification. Obviously, a successful plaintiff can spend his damages as he sees fit but this may be a useful indicator of whether the amount sought is greater than the real loss suffered.
Quite obviously, this list is by no means exhaustive ...
As stated in Bellgrove, the question of reasonableness is one of fact. Mr Sedal submitted, correctly I think, that the Builder bears the onus of proof that it would be unreasonable to award the full rectification cost. That was the view taken by Rares J of the Federal Court in Tabcorp and I respectfully agree.[5]
(a) omitted bored pier(s) by the Builder;
(b) bored piers being 400 mm diameter not 450 mm diameter as designed;
(c) bored piers not founded 900 mm into natural silty clay or 300 mm into rock as designed;
(d) the bottoms of the bored pier holes not being cleaned out and so they contained a relevantly large volume of soft material that compressed following full loading;
(e) edge beams inadequate in some locations around the slab;
(f) 2 m deep edge beam omitted by the Builder on downhill side of the house;
(g) insufficiently wide internal footing beams;
(h) missing internal footing beams; and
(i) internal footing beam cut short.
(a) omitted bored pier(s);
(b) bored piers being 400 mm diameter, not 450 mm diameter as designed;
(c) bored piers not founded 900 mm into natural silty clay or 300 mm into rock as designed; and
(d) the bottoms of the bored pier holes not cleaned out and so they contained a relevantly large volume of soft material that compressed following full loading.
(a) No bored pier inspection was conducted by the relevant building surveyor or his building inspector:
(b) Bored pier photos of bottoms of bored piers[8] show no clay, hence confirming piers are not founded 900 mm into natural soil being a clay base;
(c) The concretor and Builder refused to clean out the bottom of the bored pier holes;
(d) Builder offered a $13,000 discount at the end of the building work due to the fact he had not installed the footings as per plans;
(e) He raised the footings defects with the Builder who refused to return to the site to fix the defects.[9]
(a) 35 to 40 cubic metres of soil was extracted from bored pier holes and spread around the slab area creating extra fill;
(b) he phoned the Builder and concretor about loose fill in bored piers but got no response;
(c) after the bored pier holes were drilled out, there was no clay anywhere on top of the site so no clay was extracted from the bored pier holes;
(d) bored pier auger was only 1.8 m long, being way too short;
(e) he did not get extra fill imported onto site after soil test or contract signed with the Builder on site;
(f) the relevant building surveyor or his building inspector did not come on site to inspect the bored pier holes;
(g) the garage floor has subsided considerably.
(a) the hire invoice provided by the Builder shows a 450 mm diameter auger was hired for the building work; and
(b) during his December 2024 site inspection, he measured the diameter of the piers that were exposed and confirmed they were over 450 mm wide.
(a) edge beams inadequate in some locations around the slab; and
(b) 2 m deep edge beam omitted on downhill side of the house.
(a) insufficiently wide internal footing beams;
(b) missing internal footing beams;
(c) internal footing beam cut short.
To reduce the pod spacing over a length of beam would require the systematic and intentional modification or removal of the pod spacers in the construction prior to concrete placement - this would create more work and not provide any benefit to the workers or reduction in material (the concrete volume is still the same over the slab, as the adjacent beam is required to be wider to compensate over the grid), which in my experience has been typical rationale for a 'shortcut' in construction works.
Finding - the movement does not constitute a building defect
(b) there is evidence that most of the consolidation of newly placed fill material will have already been realised because:
(i) 80-90% of consolidation of newly placed material will have been realised at around 7 years;
(ii) the remaining 10-20% of consolidation will occur in the long term;
(c) given that the building work was completed in June 2019 and the building is now over 6 years old, only a small amount of movement will be seen in the future;
(d) this is supported by the observation that there has been very little further movement since the first reading taken by Mr O'Brien on 10 December 2022;
(e) the remaining 10-20% of consolidation and any resulting movement is expected to remain within the required tolerances; and
(f) any future movement may also be influenced by poor site drainage and the poorly executed excavation and backfilling of the piers to inspect them post construction, which is separate to the issues raised in this proceeding regarding construction of the footings.
QUESTION 2 - RECIFICATION WORK AND COST OF RECTIFICATION WORK
(a) an assessment of the slab with the roof truss loadings to the rib with the various worst case load combinations, found that the deflection experienced was within the allowable limits;
(b) if the ribs were deflecting excessively or were structurally inadequate to resist the loads, there would be greater deflection;
(c) the dwelling is over 6 years old and there is no deflection being experienced by the load bearing wall not being built on bored piers; and
(d) the dwelling has experienced the impact of an internal wall (with no bored piers under the wall) supporting roof trusses and is performing.
QUESTION 4 - RECIFICATION WORK AND COST OF RECTIFICATION WORK
[3] (Domestic Building) [2010] VCAT 1202, [165](d).
[4] Ruxley Electronics and Construction Ltd v Forsyth [1994] 1 WLR 650.
[5] [2010] VCAT 1202, at [159].
[6] Standards Australia, AS 2870-2011 Residential slabs and footings, 2011.
[7] Victorian Building Authority, Guide to Standards and Tolerances, 30 March 2015. I note that the Guide to Standards and Tolerances is currently under review.
[9] Grech witness statement dated 16 October 2024, TB173 - 177 inclusive
Grech
Dakota Homes Pty Ltd
(2009) 236 CLR 272
(1954) 90 CLR 613