[2019] NSWCA 234
Court of Appeal (NSW)
2019-08-15
Meagher JA, Gleeson JA, McCallum JA, Pain J
Original judgment source is linked above.
licant) Roads and Maritime Services (Respondent) Representation: Counsel: P Tomasetti SC / J Johnson (Applicants) R Lancaster SC / M Astill (Respondent)
Solicitors: Ristevski & Associates (Applicants) Norton Rose Fulbright (Respondent) File Number(s): 2019/79194 Publication restriction: N/A Decision under appeal Court or tribunal: Land and Environment Court of New South Wales Jurisdiction: Class 3 Citation: [2019] NSWLEC 12 Date of Decision: 14 February 2019 Before: Pain J File Number(s): 2018/207357; 2018/207345; 2018/207366
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
headnote [This headnote is not to be read as part of the decision] On 9 February 2018, Roads and Maritime Services (RMS) compulsorily acquired properties of each of the applicants for the WestConnex Stage 3 M4/M5 Link project. At that time, each property was the subject of a contract for sale exchanged on 28 June 2016 which provided for settlement on 28 June 2018. The consideration payable under those contracts was $56.5 million. The Valuer General determined the market value of the three properties at the date of acquisition to be $33.1 million. The applicants objected to that amount, maintaining that the market value of their land on that date was not relevant to the determination of compensation to which each was entitled under Land Acquisition (Just Terms Compensation) Act 1991 (NSW) (Just Terms Act), s 54. Instead, the applicants' claims for compensation were directed to the unpaid purchase price due under the contracts for sale, framed as a "loss attributable to disturbance" within s 59(1)(f). The applicants successfully applied to have the question whether each was entitled to compensation determined in that manner decided separately. The questions formulated in the Land and Environment Court were:
Judgment
The claim for compensation and separate questions
The relevant statutory provisions
The decision of the primary judge and the application for leave to appeal
Question 1
Question 2
Conclusion
Amendments 22 May 2020 - Minor typographical amendments to paras [1], [2], [3], [8], [9], [10], [11], [12], [13], [16], [20], [29], [30]. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 22 May 2020
G Capital Corporation Pty Ltd
Roads and Maritime Services
(2008) 160 LGERA 375
(2012) 191 LGERA 267
(2014) 199 LGERA 198
(1940) 64 CLR 37
(2014) 88 NSWLR 752
(2016) 212 LGERA 307
(2019) 236 LGERA 389
(2010) 79 NSWLR 155
(2019) 99 NSWLR 279
(1957) 96 CLR 493
(1959) 100 CLR 1