[2016] VCAT 662
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2016-05-10
Original judgment source is linked above.
8 Pasco Street, Williamstown (part of 255 Nelson Place, Williamstown to which the permit, as a whole, relates)
Eastwood v Hobsons Bay CC [2016] VCAT 662
The decision of the Responsible Authority to refuse to grant the proposed amendment to Planning Permit PA0818569 issued by the Responsible Authority on 23 June 2009 is affirmed.
Ms Robyn Gray, Town Planner, appeared for the applicant. She presented written and oral submissions.
Ms Kylie Sullivan, Town Planner and Officer of the City of Hobsons Bay appeared for the Responsible Authority. She presented written and oral submissions.
Various plans, photographs and other documents were tendered in evidence. The evidence and submissions in documentary form have been retained on the file on the Tribunal.
Application under s 77 of the Planning and Environment Act 1987 for a review of a decision of the Responsible Authority to refuse to grant an amendment to Planning Permit PA0815869 issued by the Responsible Authority on 23 June 2009 allowing the construction of 11 double storey dwellings, a new parish centre, associated demolition, buildings and works (including new and upgraded car parking) and the subdivision of the land into 12 lots.
Melbourne Anglican Trust Corporation Williamstown v Hobsons Bay CC [2009] VCAT 667 and [2009] VCAT 1182
Nelson v Hobsons Bay CC [2015] VCAT 1153
Lee v Hobsons Bay CC [2000] VCAT 1520
Vincent v City of Hobsons Bay, Victorian Administrative Appeals Tribunal decision in Application No. 99/08003
Franceshini v MMBW (1980) 1 PABR 276; (1980) 57 LGRA 284
Dervency Nominees Pty Ltd v City of Brighton (1994) 14 AATR 104
Poci Brothers Pty Ltd v Bayside CC (2003) VCAT 1884
Cope v Hobsons Bay CC (2004) VCAT 2487
Hill-Murray v Hobsons Bay CC [2007] VCAT 1764
Cosgrave v Hobsons Bay CC [2011] VCAT 519
Neil Fletcher Design Pty Ltd v Kingston CC [2011] VCAT 1184
Stein v Hobsons Bay CC [2013] VCAT 1828
To identify areas which are affected by specific requirements relating to the design and built form of new developments.
A schedule to this overlay must contain a statement of the design objectives to be achieved for the area affected by the schedule.
Buildings and works must be constructed in accordance with any requirements in a schedule to this overlay. A schedule may include requirements relating to:
A permit may be granted to construct a building or construct or carry out works which are not in accordance with any requirement in the schedule to this overlay, unless the schedule specifies otherwise.
To protect and enhance the environment of the Hobsons Bay foreshore as an environmental, conservation and recreational asset of State, metropolitan and local significance.
To ensure that the height, scale, bulk, setback and appearance of new development is compatible with the prevailing character of the area.
To achieve development that is a high quality architectural and urban design standard.
To preserve solar access to the foreshore, including associated roadways, bicycle and pedestrian paths.
To protect the foreshore reserve and significant public open spaces from inappropriate development.
A permit must not be granted to construct a building or to construct or carry out works exceeding a height of two storeys.
The height of a building or works is the height of its highest point above the permanent footpath at the centre of the site frontage. If there is no footpath, the natural surface level at the centre of the site frontage is the base level.
That part of a building between floor levels. If there is no floor above, it is the part between the floor level and the ceiling. It may include an attic, basement, built over car parking area, and mezzanine.
Mezzanine ...n. a low storey between two other storeys of greater height, esp. when the low storey and the one beneath it formed part of one composition; entresol.[8]
A storey below ground level, or that projects not more than 1.2 metres above ground level.
The vertical distance from natural ground level to the roof or parapet at any point.
In my view these proposed units do exceed the height of two storeys as those expressions are used in the Planning Scheme. It may be conceded that in so far as the basement's protrusion above ground does not exceed 1.2m it is not a "within a storey"; however the prohibition is not upon buildings exceeding a particular number of storeys, rather it is against buildings exceeding the height of two storeys. These proposed buildings are two storeys high plus 1.2m. In the circumstances therefore they would if built, clearly exceed the height of two storeys.
The internal rearrangement of a building ... provided the gross floor area of the building ... is not increased and the number of dwellings is not increased.
Hence the requirement of the Design and Development Overlay that a permit is required to construct a building extends to the construction of part of a building or an extension to a building. Similarly the limitation on the power to grant a permit expressed in clause 2.0 of schedule 4 is relevant in considering an application for a permit to construct an extension to a building. But, in such a case, how is the limitation that a permit may not be granted to construct a building exceeding a height of two storeys to be applied? We think that the provision means that a permit may not be granted to construct a building, or an extension to a building, so that the building becomes a building of more than two storeys (that is three storeys) by reason of the construction.
The fact that a building may appear as a two storey building from some locations does not make it a two storey building.[18] Further, the fact that an existing roofline is to be extended does not mean that a building is of the same number of storeys as the existing building. In the present case the construction of the extension will create the appearance of a three storey building when the building is viewed from positions 100 metres distance from the site in either direction among the Esplanade or toward the foreshore. This is not a case like Poci where an additional level has been created within the building in a way which made no discernible difference to the external appearance of the building.
The new building would have two level over an under-croft parking area. It is conceded that internally the new building will have three levels. However, it will be the same height as the existing two level building and in terms of its external appearance, will present as a two level building.
In my view, it is evident that in choosing an express height control in DDO[20] 4 in terms of storeys rather than metres, there is a clear intention that it is the appearance of the new development that is paramount, not the actual height in metres. I consider that the term "storeys" is used in a non-technical sense and is intended to describe the external appearance of the building in terms of number of apparent levels.
...I am of the opinion the proposal is in excess of the two storeys and the inclusion of the roof terrace is therefore contrary to DDO4.
The aim of the DDO4 is to limit development to two storeys, and, having regard to the approaches adopted in Misquitta and Cosgrave, the intent or purpose of the Overlay is to ensure that the development has the visual appearance of, or can be categorised, as being two storeys. These decisions were decided on the facts of each case where the Tribunal formed the view that the proposed roof decks would appear as a third level and would for this reason be contrary to DDO4.
...I do not consider the mandatory requirement of DDO4 would be met.
[4] Victorian Administrative Appeals Tribunal decision in Application No. 99/08003.
[8] The word "entresol" is defined in the same dictionary as "a low storey between two other storeys of greater height, USU. One immediately above the chief or ground floor; a mezzanine".
[11] While I agree with this passage generally I would not go so far as to say that clause 2 is so free of doubt and ambiguity that there is but one clearly correct interpretation.
[16] See paragraph 9 of the Cope reasons.
[20] Abbreviation for Design and Development Overlay.
[24] [2012] 1775 a similar situation arose in relation to this clause 2.
Eastwood
Hobsons Bay CC [2016] VCAT 662