[2025] VCC 972
General information, not legal advice.
County Court of Victoria
2025-06-30
Original judgment source is linked above.
Supagas Pty Ltd v R [2025] VSCA 106; Farrugia v The Queen [2011] VSCA 24.
Sentence: Magistrates' Court Orders-Det aside - Fined $25,000 - Costs $9223 - Section 6AAA Declaration-$25,000.
(a) Must set aside the sentence of the Magistrates' Court;
(b) May impose any sentence which the court considers appropriate and which the Magistrates' Court imposed or could have imposed; and
(c) Must not take into account the element of double jeopardy involved in the respondent being sentenced again, in order to impose a less severe sentence than the court otherwise would consider appropriate.[3]
(a) What is the applicable maximum penalty?
(b) What is the appropriate penalty?
(c) Should that penalty imposed by the court be with or without conviction?
(a) Developed a Blast Management Plan dated 16 January 2023 ('the BMP');
(b) Prepared a Safe Work Method Statement for 'Blasting' work at the workplace dated 16 January 2023 ('the SWMS'); and
(c) Obtained a Blasting Permit from the City of Whittlesea provided by way of letter dated 9 January 2023. In accordance with the Blasting Permit, Van Dyck were required to use explosives 'only in circumstances where it is safe to do so' and to keep certain records of the blast.
(a) Up to 400 blastholes were to be pre-drilled, 89mm wide, 'up to 4 metres deep' and placed 1.6 metres apart in a staggered drill pattern;
(b) Each blasthole was to be filled with up to 10kgs of an 'ES Emulsion' explosive and a net quantity of up to 5000 kgs of ES Emulsion explosive was to be used;
(c) Nearby residences were 180 metres away and an exclusion zone of 150 metres was to be established. The shotfirer was to be 200 metres or more from the blast site and the nearest public access was 150 metres away; and
(d) The height of 'stemming' material was to be 2.5 metres.
(a) To undertake the blasting works, 348 holes were drilled to an approximate depth of 4 metres;
(b) It was calculated that 10.5kg of ES Emulsion would be needed for each hole, with a total of 3.7 tonnes of ES Emulsion needed to complete the blast successfully;
(c) The depth allowed for a calculated 2.2m for stemming;
(d) Orica have depth indicators on the hoses to allow personnel to fill the blast holes to the required depth;
(e) Prior to the blast taking place a 150m exclusion zone was set up;
(f) It was estimated that material was identified on the streets of a neighbouring housing estate more than 200 metres from the blast site; and
(g) After the blast it was identified that 5 tonnes of ES Emulsion was pumped into the blast holes by Orica.
(a) 'Shot firer is to cross check with the operator several times during the loading of the holes on how much explosive is been [sic] used and if the holes are been [sic] loaded to his instructions'; and
(b) '[o]nly the shotfirer can sign the delivery docket'.
(a) Checking blastholes to ensure they have been drilled to correct specification;
(b) The shotfirer will provide a written load sheet to the person supplying the explosive;
(c) If the net explosive quantity is different from the blast management plan, the site will need to be re-examined and altered as required to prevent any uncontrolled blast;
(d) If there is too much explosive in the hole or over-charging, the usual process would be to check the level to ensure correct stemming is applied and then top up or extract the product as required; and
(e) burden might need to be added on top of the stemming or blast mats used with soil beneath them.
(a) Assess drilling results and deliver a safe charge design;
(b) Comply with the documented blast management plan concerning blast parameters;
(c) Provide adequate direction to the explosives supplier about charge loading requirements for short holes; and
(d) Assess charge height prior to stemming holes.
(a) The blast design should have covered the expected range of hole depths, and the hole depths should have been confirmed prior to loading with explosives. This was a safety critical step and was omitted;
(b) Where gassed explosives are used, as was the situation here, they expand vertically in the blasthole. Checking the charge height is a 'basic industry wide standard practice' which requires only a tape measure to implement and was omitted; and
(c) The net quantity of explosives used was not checked and was excessive for a sensitive blast, which would lead to increased risk of flyrock.
(a) Inspect the workplace prior to the blast process proceeding and identify and assess variations to the blast management plan (5.1);
(b) Prior to loading each blasthole with explosive, check each blasthole for its location, depth, diameter, angle and presence of water and where variances from the blast management plan are discovered, assessing the effects and mitigating any unacceptable risks (6.1.7);
(c) Provide a clear method of communication for loading requirements, especially for blastholes requiring special treatment such as those that have partially or fully collapsed (6.1.7(d)); and
(d) Implement controls to ensure overfilling of the blasthole does not occur (7.4.5(d)).
(a) The degree of carelessness or negligence involved; and
(b) The extent to which life, the safety of property, or both was endangered.
(a) The use of explosive substances is inherently dangerous;
(b) The risks associated with fly rock are well known and are able to be eliminated if control measures are properly implemented;
(c) The respondent failed to manage the use of explosives safely in a residential area; and
(d) The offending resulted in actual injury to Mrs Talevska and the potential consequences were far more serious.[7]
Careful attention to maximum penalties will almost always be required first because the legislature has legislated for them; secondly, because they invite comparison between the worst possible case and the case before the court at the time; and thirdly, because in that regard they do provide, taken and balanced with all of the other relevant factors, a yardstick.[11]
Additional penalties for offences involving explosives
(2) Notwithstanding the provisions of section 45 and of any provision of this Act which prescribes a specific penalty for an offence, a person who is guilty of an offence under this Act in relation to any explosives is liable, in addition to or in lieu of any other penalty to which the person is liable under this Act, to a penalty not exceeding 1 penalty unit for every kilogram or part of a kilogram of the explosives and the penalty imposed under this section shall be no less than 5 penalty units.
(a) in the case of a body corporate - to a penalty of not more than 500 penalty units and to a further penalty of not more than 50 penalty units for each day on which the offence continues after conviction; or
(b) in any other case - to a penalty of not more than 100 penalty units and to a further penalty of not more than 10 penalty units for each day on which the offence continues after conviction.
(a) Under the BMP, there were to be 'up to 400 blastholes' which were up to 4 metres deep; and
(b) Each blasthole was to be filled with 'up to 10 kgs' of explosives and a net quantity of 'up to 5000 kgs ... was to be used'.[13]
The principle of parity does not extend so far as to permit the imposition of a sentence which is inadequate and outside the range because a co-offender has been sentenced to an inappropriately low sentence.[20]
... where one co-offender has been given a manifestly inadequate sentence, that sentence cannot be ignored for the purpose of sentencing the other co-offender, but it should only be given such weight as is appropriate in the circumstances.[22]
In exercising its discretion whether or not to record a conviction, a court must have regard to all the circumstances of the case including -
(b) the character and past history of the offender; and
(c) the impact of the recording of a conviction on the offender's
economic or social well‑being or on his or her employment prospect
(a) Set aside the sentence imposed by the Magistrates' Court pursuant to section 259(2)(a) of the Criminal Procedure Act;
(b) In its place, on the charge under section 37 of the DGA, the respondent is convicted and fined $18,000;
(c) The respondent is to pay costs of $9223.
[1] Criminal Procedure Act 2009 (Vic) s 257(1) ('CPA').
[4] Standards Australia, Australian Standard - Explosives - Storage and Use (AS 2187.2 - 2006, 2 February 2006).
[5] Mr Duniam holds a Bachelor of Engineering (Mining) and has 39 years' experience in the mining industry and in drill and blast mining.
[6] Morgan Brown, 'Submissions for the Appellant', Submissions in Director of Public Prosecutions v Van Dyck Pty Ltd, AP-25-0224, 02 June 2025, [13].
[8] David Carolan, 'Respondent's Outline of Submissions on Sentence Appeal', Submissions in Director of Public Prosecutions v Van Dyck Pty Ltd, AP-25-0224, 02 June 2025, 7 [27]-[28] ('Respondent's Submissions').
[10] It is a matter of significance that the maximum penalty is the first of the mandatory considerations listed in s 5(2) Sentencing Act, see DPP v Aydin and Kirsch [2005] VSCA 86, 7 [10].
[12] R v Beary [2004] VSCA 229, 11 [21].
[13] Statement of Material Facts, 19-20 [9].
[17] On the relationship between the two enactments, see generally DPP v Bradbury Industrial Services Pty Ltd (in liquidation) [2023] VCC 1029, 19 [83].
[18] DPP v Amcor Packaging Australia Pty Ltd [2005] VSCA 219; (2005) 11 VR 557, 12-3 [35].
[19] Respondent's Submissions (n 8) 6 [26].
[20] [2011] VSCA 145, 13 [37].
[21] Supagas Pty Ltd v R [2025] VSCA 106, 24 [85].
[22] [2011] VSCA 24, 11-2 [31].
[23] DPP (Cth) v Gregory [2011] VSCA 145, 13 [37]
[24] See Sentencing Act 1991 (Vic) s 52.
DPP
Van Dyck Pty Ltd [2025] VCC 972
(2005) 228 CLR 357
(2005) 11 VR 557