[2018] TASFC 13
General information, not legal advice.
Supreme Court of Tasmania (Full Court)
2018-12-03
Geason J, Martin AJ, Marshall AJ
Original judgment source is linked above.
"[83] The development and sale of lots in Stage 1 of the Mount Pleasant subdivision, which was adjacent to Ernest Street, was not delayed by the defendant's breach of contract. No lots were sold in any other stages until the 2011 financial year. But in that year the plaintiff received sales revenue exceeding $2.3 million from the sale of lots in stages other than Stage 1. Positive cashflows from the sale of lots outside Stage 1 commenced during that financial year, have continued ever since, and are likely to continue for years to come.
[84] The plaintiff contends that, but for the defendant's breach of contract in failing to complete the construction of the Connector Park roadway, those positive cashflows would have commenced 3½ years earlier than they did. On the basis of data relating to those cashflows, Mr Rands has expressed an opinion as to the extent of the loss suffered by the plaintiff as a result of delayed cashflows as at September 2014."
"7 Ground 6 of the appellant's notice of appeal, as originally drafted, impugned the exclusion by the Honourable trial judge of the evidence of an accounting expert called by the appellant/defendant at trial, Mr Wallace, to the effect that expenses should have been taken into account by the respondents' expert Mr Rands.
"[6.1] Attached as Appendix 1 is a printout of the spreadsheet prepared by employees of RV Pty Ltd I have been instructed to adopt as reflecting the actual and projected cashflows of the project both as they have and are projected to occur and also how they would have occurred if the roadway was completed three years earlier."
"2 (a) KPMG Appendix 3 is a document from Shaun McElwaine + Associates to Mr Rands. In this document in the section titled 'The Plaintiffs' Financial Accounts and Dealings', Mr Rands is requested to meet with staff of RV Pty Ltd to ask questions relating to the report. Mr Rands seems to have been relying on management data without verification or scrutiny for reasonableness.
(b) The document has missing expenses, formula errors, overstated income forecasts and amounts that are not equalling the RV Pty Ltd column in the consolidated spreadsheets at KPMG Appendix 6.
(c) Errors noted in the following KPMG points numbers 3 to 6."
"5 (a) The spreadsheet mentioned in Mr Rands' section 6.1 has formula errors at cells F141 & F143. Effectively the initial cash outlaid for the commencement of the subdivision is missing.
(b) The row heading 'Net Cash Flow (excl State 1)' as mentioned in Mr Rands' section 6.4 first shows the total cash spent on the subdivision in 2006 at $194,957. In 2006 the WIP balance is $1,757,759. How is it possible for the total expenses spent to date to be reported as only $194,957 if the WIP balance is much greater.
(c) It is suggested that $1,562,802.57 is excluded from the cash position of the company in 2004 and 2005 due to the formula errors."
"It's an expression of expert - well, 5(a) is an expression of expert opinion that the cash outlaid for the commencement of the subdivision should have been brought into account but it was not. There is no reasoning in support of that opinion. 5(a) is therefore inadmissible.
5(b) amounts to an expression of opinion that two figures in Exhibit P22 are inconsistent. No reasoning is given as to what makes them inconsistent. 5(b) is therefore inadmissible. 5(c) is a conclusion based on 5(b). It must also be inadmissible."
"9 a) I refer to Mr Rands' report section 7.9 (refer to appendix 4 page 9 for the correct section 7.9 as Mr Rands' report contains 2 section 7.9s). In this section, he states that his calculations are showing the 'net cash generated by the sales of allotments less the amounts expended on allotment construction'.
"Point 9 has to do with expenditure prior to the first positive cash flow in the 2012 tax year. The - it begins with the statement or the recitation of some factual premises. Paragraphs (a) to (c) basically say that Mr Rands' calculations ignored the expenditure that was incurred before the first year of positive cash flow. 9(d) sets out figures which can be found in the spreadsheet, exhibit P22 as to the amount of such expenditure. Then we have the opinion in 9(e) to the effect that it - that one, it should be inferred that RV would have reduced loan debts once there was a positive cash flow, and two, that the amounts paid to - or the assumed amounts paid to reduce such loan debts, should have been brought into account. Well those are the opinions, no reasons are given for them.
(f) and (g), go on to set out further opinions as to the consequences of bringing into account the amounts assumed to have been paid to reduce loan debts but there aren't any calculations provided to substantiate the assertion of a nil balance in (f) and the figures in (g). So, all of paragraph 9 becomes in - must be inadmissible because the opinions expressed in it aren't explained by way of - no reasons are given for the reasons expressed in the paragraph - in the point. Item 10 - in item 10, the central opinion is in paragraph (c). It's an opinion that the initial subdivision costs totalling 2.844 million, that's - that comes from 9(d) that, that amount would have been repaid to the bank and therefore not available for investment as per Mr Rands' report. No reasoning is given for that opinion, therefore point 10 is inadmissible."
(1) Evidence of an opinion is not admissible to prove the existence of a fact about the existence of which the opinion was expressed.
(2) Subsection (1) does not apply to evidence of an opinion contained in a certificate or other document given or made under regulations made under an Act other than this Act to the extent to which the regulations provide that the certificate or other document has evidentiary effect.
77 Exception: evidence relevant otherwise than as opinion evidence
The opinion rule does not apply to evidence of an opinion that is admitted because it is relevant for a purpose other than proof of the existence of a fact about the existence of which the opinion was expressed.
The opinion rule does not apply to evidence of an opinion expressed by a person if -
(a) the opinion is based on what the person saw, heard or otherwise perceived about a matter or event; and
(b) evidence of the opinion is necessary to obtain an adequate account or understanding of the person's perception of the matter or event.
78A Exception: Aboriginal and Torres Strait Islander traditional laws and customs
The opinion rule does not apply to evidence of an opinion expressed by a member of an Aboriginal or Torres Strait Islander group about the existence or non-existence, or the content, of the traditional laws and customs of the group.
79 Exception: opinion based on specialised knowledge
(1) If a person has specialised knowledge based on the person's training, study or experience, the opinion rule does not apply to evidence of an opinion of that person that is wholly or substantially based on that knowledge."
To the extent to which Dr Basden expressed an opinion about the numerical or quantitative level ... of respirable silica dust to which [the employee] was exposed in the course of working for [the employer], his evidence was not 'wholly or substantially based on' 'specialised knowledge based on [his] training, study or experience'."
"[32] To be admissible under s 79(1) the evidence that is tendered must satisfy two criteria. The first is that the witness who gives the evidence 'has specialised knowledge based on the person's training, study or experience'; the second is that the opinion expressed in evidence by the witness 'is wholly or substantially based on that knowledge'."
"[36] In this case, demonstration of those matters could come only from evidence given by Dr Basden. That is why, in HG v The Queen, Gleeson CJ pointed out that, '[b]y directing attention to whether an opinion is wholly or substantially based on specialised knowledge based on training, study or experience, [s 79] requires that the opinion is presented in a form which makes it possible to answer that question'.
[37] It should be unnecessary, but it is nonetheless important, to emphasise that what was said by Gleeson CJ in HG (and later by Heydon JA in the Court of Appeal in Makita (Australia) Pty Ltd v Sprowles) is to be read with one basic proposition at the forefront of consideration. The admissibility of opinion evidence is to be determined by application of the requirements of the Evidence Act rather than by any attempt to parse and analyse particular statements in decided cases divorced from the context in which those statements were made. Accepting that to be so, it remains useful to record that it is ordinarily the case, as Heydon JA said in Makita, that 'the expert's evidence must explain how the field of "specialised knowledge" in which the witness is expert by reason of "training, study or experience", and on which the opinion is "wholly or substantially based", applies to the facts assumed or observed so as to produce the opinion propounded'. The way in which s 79(1) is drafted necessarily makes the description of these requirements very long. But that is not to say that the requirements cannot be met in many, perhaps most, cases very quickly and easily. That a specialist medical practitioner expressing a diagnostic opinion in his or her relevant field of specialisation is applying 'specialised knowledge' based on his or her 'training, study or experience', being an opinion 'wholly or substantially based' on that 'specialised knowledge', will require little explicit articulation or amplification once the witness has described his or her qualifications and experience, and has identified the subject matter about which the opinion is proffered.
[38] But that was not this case." [Footnotes omitted.] [My emphasis.]
"A reasonable summary of the effect of this evidence is that, consistent with the methodology described above, the battery was identified at an early stage in the investigation as a potential ignition source. After the consultation with Toyota, Mr Catterall conducted a number of further investigations and made observations himself. On the basis of all of this information, he excluded the battery as a cause of the fire. It is a reasonable assessment of this evidence that the only role played by the information obtained from Toyota was the identification of the battery as the correct battery for the vehicle. This was a piece of factual information which was not otherwise within the knowledge of Mr Catterall. It clearly played some role in the formation of his opinion, although the extent of that role was not clear."
"The ground asserts that Mr Catterall's ultimate opinion as to the source of the fire is inadmissible because it relies, in part, on opinion and facts within the knowledge of others which has not been proved by calling those persons to give evidence. This is an appeal to what at common law may have been called the 'basis rule' or 'proof of assumption rule'. The decision of the High Court in Ramsay v Watson [1961] HCA 65; (1961) 108 CLR 642 was often cited as authority for the proposition that proof of assumed facts was a necessary precondition of admissibility of expert opinion at common law. Whether such a rule was actually identified by that case was a matter of some controversy."
"However, as was noted by the New South Wales Court of Criminal Appeal in Taub v The Queen [2017] NSWCCA 198, the plurality also considered that these requirements implied a further condition of admissibility. Their Honours reasoned that the need for the evidence to demonstrate that the opinion is wholly or substantially based on the specialised knowledge of the witness requires an explanation of this relationship in the context of the factual assumptions upon which the opinion is based."
"[37] The plurality made it clear that this 'third' condition of admissibility did not introduce or re-establish a general rule that necessarily required proof of the underlying factual assumptions of an opinion:
'[41] Contrary to submissions on behalf of Mr Hawchar, this analysis does not seek to introduce what has been called "the basis rule": a rule by which opinion evidence is to be excluded unless the factual bases upon which the opinion is proffered are established by other evidence. Whether that rule formed part of the common law of evidence need not be examined. It may be accepted that the Law Reform Commission's interim report on evidence Australia, The Law Reform Commission, Evidence, Report No 26, (1985) vol 1 at 417 [750]. denied the existence of such a common law rule and expressed the intention to refrain from including a basis rule in the legislation the Commission proposed and which was later enacted as the Evidence Act 1995 (Cth) and the Evidence Act 1995 (NSW). What has been called the basis rule is a rule directed to the facts of the particular case about which an expert is asked to proffer an opinion and the facts upon which the expert relies to form the opinion expressed. The point which is now made is a point about connecting the opinion expressed by a witness with the witness's specialised knowledge based on training, study or experience.
[42] A failure to demonstrate that an opinion expressed by a witness is based on the witness's specialised knowledge based on training, study or experience is a matter that goes to the admissibility of the evidence, not its weight.'
[38] The effect of the plurality's reasoning is that evidence of an opinion is admissible if the requirements of the section are satisfied and the connection between the witness's opinion and his specialised knowledge, as it applies to the assumed facts is demonstrated on the evidence. The factual assumptions must therefore be stated and their relationship to the opinion explained, but they need not necessarily be independently proved. The failure to prove facts upon which the expert has relied to form the opinion will therefore not affect the application of s 79 to the evidence, and hence unless the evidence is excluded for another reason, it will be admissible."
"[46] The partial reliance by an expert on information, factual or otherwise, provided by others, will not impact on the admissibility of the opinion, provided that the opinion is based wholly or substantially upon the expert's specialised knowledge. Whether the opinion is substantially based on such knowledge is a question of degree, and requires an evaluative assessment by the court when determining admissibility. It is inevitable that experts will often rely partially on such information when formulating an opinion. In his submissions, the Director of Public Prosecutions referred to comments of Hall J in R v Jung [2006] NSWSC 658 at [57]:
'[57] It is not uncommon for professional persons or experts in various fields to utilise materials produced by third party specialists for the purpose of assisting them apply their specialised knowledge. That does not mean that the opinion of the former is not based wholly or substantially upon his or her specialised knowledge (the making or production of such materials being proved independently or admitted in legal proceedings). An example is the radiologist who produces an MRI scan which, in due course, is utilised by a medical specialist for the purposes of forming an opinion concerning causation, diagnosis and/or treatment. The specialist utilises such materials (and equipment) for the purposes of exercising his specialised knowledge in order to arrive at an opinion for the purposes of treatment or otherwise. It is apparent from the evidence that Dr Sutisno has, from her experience, an appreciation that photographic images can be affected by issues such as distance between subject and lens, angle, perspective and other issues. Whether or not the ATM photographs and forensic procedures are affected by circumstances that impact upon their quality or utility are matters that go to the soundness or value or integrity of the factual material utilised by her as an expert'."
"In doing so, please also comment upon the correctness or otherwise of any assumptions within your field of expertise that he applies, and set out the type of factual material that would be required in order to found those assumptions."
"[87] Mr Blackwood's calculations as to the actual cashflows up to 30 June 2013 were based on figures extracted from the JAC group's financial records as to the following:
[88] Mr Blackwood's predictions in relation to 2014 and subsequent years were based on the following:
"The evidence of the plaintiff's accountant Mr Blackwood is not challenged on this appeal. Mr Blackwood calculated the plaintiff's cashflows for each of the relevant years, and gave evidence that the plaintiff's 'Cash received from the sale of lots in that year' for the financial year (FY) 2012 was $1,974,379. That figure was the first year the plaintiff's cash receipts exceeded development expenditure."
"So this is relevant to the third point that we make and that is that the spreadsheet prepared by Mr Blackwood failed to properly record some $1.5 million of non-stage 1 expenditure in the financial year 05 resulting in an addition $1.562,802 of negative cashflow which should've been taken into account when assessing when a net positive cashflow for the development was actually achieved."
"[101] Mr Blackwood was thorough and meticulous in his calculations, and conservative in his assumptions. I accept that his methodology was appropriate. It is true that he made no allowance for real estate prices increasing with inflation, but sale prices are only one component in a very complex calculation. Construction costs might also increase with inflation, but Mr Blackwood made no assumption that they would. Rather than looking at trends in relation to real estate prices or construction costs in isolation, it would be more appropriate to consider what trends there were as to the margins between sale prices and expenses, but I have not been presented with any evidence as to such margins, and will therefore have to assess damages as best I can."
"Let's go to his .8 which I think - no, we've dealt with .8, .9, and I direct your attention to sub-paragraph (e) because this seems to be the pith and substance of what's being said. The contention that it's unreasonable to assume in your calculations that initial costs are never repaid from 2012 to 2029. Having heard the evidence of Mr Blackwood and read this report of Mr Wallace, is there any qualification - ?.....No.
You see necessary, why not?.....No because the - those initial costs were before the positive cash flow started in the project and so they're not relevant to an analysis of the bringing forward of positive cash flows.
Right, so they would have happened in any event?.....Yes.
The next point - well 10(c), did you make any adjustment for the Commonwealth - initial subdivision costs of 2.844 million dollars and the contention that they would have been repaid to the bank, or do you understand what's meant by this?.....I - I don't know on what basis it can be said that any amounts would have been repaid to the bank. I certainly wasn't advised of that when speaking to Mr Blackwood.
But, again, does it make any difference, because you might choose to repay a loan at 6 or seven percent?.....No, no, no. Repaying the loan is perhaps one of the uses of funds along with investing it and I don't know why we would want to repay initial costs. I mean, they're costs, they're not anything that gets repaid. They're - they've been outlaid."
"The question would be - we'll phrase it another way, your Honour. (Resuming) Would you accept that, that would be the debt that would've been built up, if you had've started with a cash position of zero, that would've been the debt built up for a standalone situation for Mt Pleasant subdivision stage 2?.....Yes.
Yes. Now, I'd ask you to turn to Mr Wallace's report because I suggest to you that at .9, he shows the expenses of the Mt Pleasant subdivision for those years, 2005 to 2011. Point 9?.....Yes, I'm just tracking those back to the-
Thank you?.....In part that is correct but there's also a 1.562802 for 2004/5 which has been added in there as well.
It's otherwise-?.....Then the balance of it, yes. Yes, indeed.
In a standalone situation, stage 2 onwards, would you agree that the RV Pty Ltd cash flow values would show an overdrawn balance of approximately 2.8 million at the end of financial year 2011?.....Well, no, because if we're going to exclude the 1.5 which is at the top of that column, the amount which would be the stage 2 overdraft balance, on your assumption, would be approximately 1.3.
I see. And if the 1.5 was added in, then it would be the 2.8?.....The 2.8, yes because he's put the 1.5 there.
Okay. If funds received in 2012 were the 1,974,379, if they were applied off the opening balance, cash flow would still be negative?.....Well, if we're going to say the opening balance was 1.3, as we established a moment ago, no, it wouldn't.
No, but if it were 2.8?.....If it were 2.8, yes, 2.8 is larger than 1.9.
I see. If we're showing the net present value of the funds RV had in the bank, why wasn't the opening negative cash position for 2012, included in your calculations?.....Because we were not doing the value of the company, we weren't doing the net present value of the total project, we were modelling the difference between the positive cash flows starting when they did start and starting three and a half years earlier. And so, those earlier costs are not relevant to that analysis.
On the basis that you're constricted to that model?.....No, not at all. They are different things which would've been modelled. I was not asked to calculate the net present value of the project and if you include the earlier cash flows, that's the net present value of the whole project. If what you're trying to do is understand the economic impact of bringing the positive cash flows forward, then you disregard the earlier negative cash flows.
And you'd agree with me that the results are very different if based on those two streams?.....Well, they're two different questions and so they would have two different answers."
"You said yesterday, that 'I don't know on what basis it can be said that any amounts would've been repaid to the bank. I certainly wasn't biased of that when speaking to Mr Blackwood'?.....Yes.
Wouldn't it have been an obvious enquiry for you to make?.....No.
I suggest that you didn't ask that question because, effectively, you were only working towards the assumptions that you'd been directed?.....No. No, the allocation or the repayment of loans is a separate consideration to the timing and quantum of the cash flows at their present value and then bringing them forward three and a half years and finding out that present value. The bank funding or repayment of bank debt or the recoupment of stage 1, is irrelevant to that consideration, to that process.
I suggest to you that the repayment of bank debt would have affected things such as taxation. I mean, interest is deductible, it's-?.....Yes.
So, clearly it would've affected your projections, wouldn't it?.....No, because what we've done is we have disregarded overheads, we've disregarded financing and we've just looked at the cash flow coming out of the project itself and then applied - I could have said 'notional', I believe the word I've used is 'implicit.' A tax, only applicable, to those cash flows."
"Would you agree that you made an assumption when calculating the available cash for reinvestment, that initial funds of 2.8 million outlaid in years 2004 to 2011 for the commencement of the subdivision, including stage 1, are never repaid, correct?.....Um, my model - the spreadsheet doesn't deal - Mr Blackwood's spreadsheet doesn't deal with the repayment of debt. My analysis doesn't deal with the repayment of debt. We established it was 1.3, not 2.8. Um, I - it - they are outlays on the cost if - on the project before the cash flows - positive cash flows commences, I just don't see how any of that is helpful to my analysis.
When you say helpful, you mean helpful to the assumptions that you were given?.....No. It was helpful in trying to understand it or criticise it.
I suggest to you that the model that you were given was designed to calculate a loss?.....I can only take it as it was given to me.
I suggest to you that if the 2.8 million was repaid into your model then that would change the positive cash available in the model?.....If we were not going to look just at operating costs our operating cash flows, which is what my analysis is, and we were to take into account debt repayments, yes, that's right.
Would you agree with Mr Wallace that by not adopting the $2.8 million as repaid this overstates the positive cash available by between 1.03 million and $849,000?.....I can't understand where he would get his money from and I can't accept that criticism."
"In relation to expenses on the allotments, in terms of the net cash generated by the sales of allotments, less the amounts expended on allotment construction, which is in your report of the 2nd, 7.9, would you agree that there is no reference there in the report to initial construction costs in - sorry, to construction costs from 2004 to 2011?.....That is correct.
Would you agree that it's unreasonable to assume, in your calculations, that these initial costs are never repaid from 2012 to 2029?.....That's not relevant to the process that I went through to establish the net present values of the breach and no-breach cash flows.
Would you agree with me that in terms of giving the most accurate assessment of events, that it would've been reasonable to assume that those costs were repaid from 2012 to 2029?.....It's really not relevant to the calculations.
Would you agree that if they were repaid, that would've affected the net cash flow from the project, according to your model.
MR McELWAINE SC: Well, he said, it's not relevant, and so the next question follow.
MR WILLIAMS: (Resuming) I'll withdraw that question, your Honour. Would you agree with Mr Wallace's contention that the initial subdivision costs, totalling approximately $2.8 million , would have been repaid to the bank as cash was made available and would therefore not be available for reinvestment, according to your report?.....When we discussed this earlier, we established that it was actually 1.3 because 1.5 of the 2.8 relates to stage 1 of the subdivision and I maintain that it is not relevant, they're not considerations.
I suggest to you that it is relevant that stage 1 and stage 2 be considered together for the actual project, therefore, it is relevant. What do you have to say to that?.....I disagree that it is relevant."
"So, it would be a calculation of economic loss and it would be based on the facts of the particular case and standing back and trying to make an assessment of what the real loss actually is and net present value of future cash flows is certainly one methodology. An alternative methodology could be what is the cost for the breach which maybe the net present value of future cash flows, but it may also be, in this example, not receiving a return on funds invested in the subdivision for the three and a half years whilst it was delayed. So you could do an economic loss calculation based on 2.8 million or 1.5 was invested up to '05, but it seems to be common that work in progress was 2.8 before sales happened, so there's a - there's a cost, an opportunity cost of those funds, in a sense, sitting idle. So that would be an alternative methodology which isn't a net present value that has you dealing with known figures, as opposed to some known and then forecast. So that would be an alternative methodology that you could use to assess this economic loss."
"Now, the method of calculation submitted, or put forward by the plaintiff, is flawed in a number of respects. There's no doubt that Mr Blackwood is a faithful employee of the JAC Group, but he did what he was directed. He developed a spreadsheet that he himself agreed was too conservative and, as directed by Mr Cocker, a fundamental defect in this spreadsheet is that it took out the initial costs - 2.8 million. It didn't include the $400,000 that was paid. There's nothing in that spreadsheet that deals with the $400,000 that was paid and there's nothing in it that deals with $400,000 that would later be paid.
In very simple terms, your Honour, by taking out that initial cost, it exaggerates the later profit. That's the effect of it. By taking out that initial cost of 2.8 million, it distorts the future profit.
So we have a calculation which fundamentally is unreliable."
"Now, your Honour, one could feel sympathy for Mr Rands. I asked him, at page 402 of the transcript:
If you'd been asked to come up with the most accurate figure, then you would have taken into account the costs of development, too, wouldn't you?
If I was going to do the exercise Mr Blackwood did, do you mean?
Yes.....I would have called, absolutely, I would have called for expert input as to both the sales, timing and quantum, and also the expenditure and quantum and timing, absolutely.
Do you accept that your opinion evidence is an opinion based on the spreadsheet prepared by Mr Blackwood?.....Well, I've accepted certain assumptions and as if they were facts, those projections, I've accepted those. My opinion is the conversation of those cash flows and taxable incomes into an economic loss, that's my opinion.
Would you accept, in this case, that your acceptance of the rigid assumptions and the calculations by others, that the outcome that you have predicted is different to an outcome if you hadn't been guided by those assumptions and you made your own inquiries?.....Who knows what I would have been provided had I not been provided the spreadsheet and I was engaged to compile that spreadsheet myself."
"It is also plainly the case that if cross-examining counsel had challenged the critical evidence of Mr Rands, that his modelling permissibly ignored the cash outflows, that he could have given a more detailed explanation and, most likely, would have explained the range of different methodologies which might have been employed and why he chose only the NPV calculation as applied to the difference between the receipt of identical income streams, but at different points in time. The possibility that this evidence might have been given, requires that the application to amend be refused."
"Given there are bank loans in both R V Pty Ltd and also the consolidated group as detailed in KPMG point 10, it is suggested that this loan plus the unfunded costs would be repaid in the 2012 and 2013 years' cash."
"(f) Therefore, in 2012 there is Net cashflow from the project and at 2013 is reduced by the remaining balance.
(g) The net present value variance is between $1.03M and $849K."
"(c) It is concluded that the initial subdivision costs totalling $2,844,134 would have been repaid to the bank and therefore not available for reinvestment as per Mr Rands' report."
"An experienced chartered accountant named Matthew Wallace gave evidence for the defendant. He criticised some aspects of the calculations undertaken by the plaintiff's witnesses. However he agreed that discounted cashflow was a common methodology employed to calculate the present value of a future cashflow. He accepted that cash received at an earlier point in time is more valuable than cash received at a later point in time; that such calculations had to take account of risk associated with the cashflow stream; that that risk was reflected in the discount rate used to convert future cashflows into a present value; and that the use of such a methodology was widespread in relation to projects with a finite life, such as subdivisions. He accepted that one has to make a projection in undertaking a discounted cashflow analysis for a subdivision, and that that projection was a matter of professional judgment."
"(a) determine the anticipated hypothetical 'no breach' positive cash flows in each year by bringing forward the actual and forecast positive cash flows by 3.5 years;
(b) subtract the actual and forecast positive cash flows in each year from the hypothetical 'no breach' positive cash flows in each year to calculate the difference between the two positive cash flows in each year;
(c) discount the difference in those two positive cash flows in each year back to 2005 dollars;
(d) add the discounted differences in cash flow to arrive at the Net Present Value (NPV) of the loss caused by the 3.5 year delay in 2005 dollars;
(e) apply a range of interest rates to the calculated loss in 2005 dollars until September 2014 (the date of the report of Mr Rands) and, thereafter, until the date of judgment;
(f) the interest free loans from JAC Group Holdings Pty Ltd to the respondent, between 2004 and 2011, mean that the discount rate is 0% in those years and therefore there is no discounting of any of the negative cash flows; and
(g) accordingly, there is no difference between the sum of actual negative cash flows and the sum of a hypothetical 'no breach' negative cash flow with the consequence that the NPV caused by any difference in the timing of negative cash flows between 2004 and 2011 is zero, consistent with a discount rate of 0%."
"[Mr Wallace] agreed that the purpose of the modelling of Mr Rands is to reasonably calculate the economic loss caused to the respondent by reason of delayed performance in the construction of the road. Importantly, he accepted that the modelling of Mr Rands proceeds in accordance with 'correct principles', is correct in its treatment of 'like for like' and was undertaken in order to determine 'the economic consequence of having cash flows at an earlier point in time'." [Footnotes omitted.]
"19 This analysis demonstrates that, firstly, Mr Wallace did not give evidence contrary to the factual finding that his Honour made at [105]; secondly, the methodology upon which his findings is based intentionally, and permissibly, excluded any consideration of expenditure between 2004 and 2011 as irrelevant; thirdly, expenditure in earlier years may have been relevant to other methodologies which may have calculated a different range of damages but Mr Wallace did not have the time to undertake that exercise; and fourthly, even if Blow CJ did not rule as inadmissible the critique and tentative conclusion of Mr Wallace, there is no proper basis for this Court to conclude that the appellant has discharged the onus which requires it to demonstrate that acceptance of this evidence could have affected the outcome of the trial.
"[86] He provided Mr Rands with data as to the actual net cashflows relating to the Mount Pleasant subdivision, excluding Stage 1, up to 30 June 2013, as well as his predictions as to such net cashflows from 1 July 2013 until the sale of the last lots in the subdivision. He predicted that the last lots would be sold in the 2028 financial year.
[87] Mr Blackwood's calculations as to the actual cashflows up to 30 June 2013 were based on figures extracted from the JAC group's financial records as to the following:
"The Honourable trial judge described the evidence of Mr Blackwood as being the provision to Mr Rands 'actual net cashflows' based upon material including, 'as to the actual cashflows up to 30 June 2013', 'the amount of accumulated expenditure for each stage at the start of each financial year', and the 'proportion of the cost of land' and the 'proportion of development costs' attributed to lots sold in each stage in each financial year.
The apparent finding by the Honourable trial judge at paragraph [87] - that the 'actual cashflows up to 30 June 2013' were based upon that list of inclusions- is wrong, if His Honour was intending to say that the respondent's cashflows allowed for (were 'based on') its past expenditure as, it is submitted, His Honour seems to have intended. The cashflows were not 'based on' all of the respondent's expenditure, but only on selective 'post-breach' expenditure. Those purported 'actual cashflows' were then embraced by His Honour in adopting Mr Rands' evidence from paragraph [90] and onwards of his reasons.
In the appellant's submission, this quarantining of 'pre-breach' expenditure is the issue which was identified by Mr Wallace, most conveniently at point 9 of his report (as was excluded by the Honourable trial judge). Mr Wallace's opinion highlights the error of Mr Rands as being Mr Rands saying that the respondent's loss is calculated upon 'net cash generated' only by reference to amounts which exclude 'pre-breach' expenditure. 'Net cash', in the appellant's submission, means available cash after allowing for all expenditure (not selective expenditure) - but this is not what Mr Rands deployed.
The appellant submits that had Mr Wallace's evidence been received, the Honourable trial judge would have identified the disconnect between the claimed 'net cash flow' and a truly positive cash flow including 'pre-breach' expenditure: an issue which in the appellant's submission is not identified or addressed in His Honour's reasons.
The admission of Mr Wallace's evidence would, it is submitted, have necessarily led the Honourable trial judge to consider whether or not the 'actual' cashflows excluded, and ought properly exclude, 'pre-breach' expenditure. Had that evidence been received, it was capable of influencing the Honourable trial judge's findings in particular at paragraphs [87] and [90], engaging s. 50(1)(a) of the Supreme Court Civil Procedure Act 1932 (Tas) in that the rejection of Mr Wallace's evidence:
(a) improperly limited the evidentiary materials by which it is not an unreasonable hypothesis to suppose the judgment of the judge might have been affected; and/or
(b) wrongly exposed the appellant to a hazard, that is appreciable and not illusory, of a verdict against it that otherwise might not have been found; and/or
(c) is not unreasonable to be regarded as capable of contributing to the result.
Further or alternatively, the appellant submits that the absence of proper explanation from Mr Rands, for Mr Rands incorporating only 'post-breach' expenditure to influence his calculations concerning the impact of delayed cashflows, is a matter which required findings by the Honourable trial judge regardless of His Honour otherwise adopting Mr Rands' evidence.
The notion of allowing only 'post-breach' expenditure in, and excluding 'pre-breach' expenditure from, cashflow calculations is something which finds no footing in the Honourable trial judge's reasons for decision, and is seemingly inconsistent with His Honour's description of Mr Blackwood's evidence at paragraph [87] as then inputted at paragraph [90].
It is central to the appellant's ground 6 (in both unamended and to sought-to-be-amended form) that only Mr Wallace's excluded evidence, as then buttressed by submissions in closing by the appellant's trial Counsel, properly queried the excision of the respondent's $2,844,134 in 'pre-breach' expenditure - with there being nothing of substance before the Court from Mr Rands, or falling from trial Counsel or the Honourable trial judge, to explain how that excision was immaterial and should not be the subject of explicit findings." [Footnotes omitted.]
"[91] The proposition that the plaintiff would have invested positive cashflows rather than repay debt is inconsistent with:
(a) it claiming as a compensable loss the interest paid to CBA;
(b) evidence of Mr Blackwood that net cash flow in the 2009 financial year was used to repay JAC Group Holdings Pty Ltd's inter-company loan;
(c) the plaintiff's trial balances produced at trial recorded the loan from JAC Group Holdings Pty Ltd as a liability, which was reduced (the only explanation available on the evidence is that it was repaid) in every financial year between FY07 and FY12;
(d) the evidence of Mr Blackwood that some funds from the plaintiff's CBA loan were used to pay money back to JAC Group Holdings." [Footnotes omitted.]
"• Substantial and profitable development and investment since 2003;
"Mr Blackwood gave evidence of group loans by reference to exhibit P19. Interest was never charged to the respondent upon group advances. In some years, net cash inflow was, in part, used by the respondent to make capital repayments on group loans as set out below.
JAC Group Holdings Pty Ltd funded the initial subdivision costs until 201.
Whilst it is true that the loan advance from JAC Group Holdings Pty Ltd fluctuated between 2004 and 2013, the conclusion that the appellant seeks to draw at [91](c) overlooks the returns that the respondent achieved in consequence of its business activities and the retained cash that it used for investment. Exhibit P23 included the consolidated group accounts for the years 2005-2013. Relevantly the respondent generated revenue, made profit, invested money and held cash as follows:
These figures differ from those in exhibit P22 as it is confined to revenue and expenses of the respondent for the Mount Pleasant subdivision: it ignores the entirety of its business activities in the relevant years.
The appellant submits at [91](c) that the respondent reduced its debt to JAC Group Holdings Pty Ltd in every financial year between 2007 and 2012. But it ignores what happened in other years. The evidence in exhibits P18 and P19 discloses that:
The appellant also, at least on this point, overlooks the evidence that the respondent obtained a business line of credit from the Commonwealth Bank of Australia on 29 June 2010 with a facility limit of $2,010,000.00. The respondent utilised that facility, as demonstrated in exhibit P19 as follows:
Thus, whilst it is correct that the respondent reduced its debt to JAC Group Holdings Ltd between 2011 and 2012, the debt increased in 2013 and correspondingly, the respondent's debt to the Commonwealth Bank substantially increased from 2010 until 2013.
Moreover, the relevant question is not how much the respondent paid, by way of loan capital repayments, to other group companies but what return it made upon its business activities as a whole? The appellant errs in that it makes no reference to all of the profitable activities of the respondent that, concurrently, included the subdivision and sale of land at Shearwater. Exhibit P23 discloses the profit made in each year from the entirety of the respondent's business. In summary:
In each year it is self-evident that the net profit margins substantially exceed the very conservative rates of return adopted in the analysis of Mr Rands. If one focuses only upon the returns from the Mount Pleasant subdivision, as exhibit P22 demonstrates (and excluding stage 1), total sales revenue is $26.7M, total expenditure is $12.4M and therefore net cash flow is $14.2M. On these figures expenses as a percentage of gross revenue may be calculated as: 12.4÷26.2 x 100 = 47% and correspondingly, net cash flow as a percentage of sales is 53%.
What this analysis demonstrates is that although the respondent did not receive a positive cash flow from the Mount Pleasant subdivision until 2012, it did manage to make loan repayments to JAC Group Holdings Pty Ltd between 2007 and 2012 which was funded by a combination of the Commonwealth Bank loan facility from June 2010 and the profitable conduct of its other business activities. It is artificial and wrong for the appellant to speculate that if the respondent had received positive cash flows three and one half years earlier than it did (the 2008-2009 financial year) that it would have used all of that cash flow to repay internal debt in 2012 and 2013. As Mr Blackwood explained, there were other options: the repayment of the Commonwealth Bank Debt, investment in other activities or the development of new subdivisions. Mr Blackwood was not cross-examined as to any aspect of the terms of the loan from JAC Group Holdings Ltd, the obligation of the respondent to make capital repayments nor the reasons why the respondent made repayments, and drew down further funds, between 206 and 2013.
It is clear that the respondent conducted very profitable business activities, and received significant economic returns, between 2004 and 2013, despite its indebtedness to JAC Group Holdings Pty Ltd. It is plain that if it had received even greater positive cash flow, from the Mount Pleasant subdivision, that it was open to it to employ this cash flow to its economic advantage. On the damages assessment question, did not have to prove how it would have utilised that cash, on the balance of probabilities." [Footnotes omitted.]
"[14] In saying that admission of the evidence of Mr Wallace ought to have led the Honourable trial judge to an enquiry about the exclusion of the plaintiff's accumulated losses from its 'available cash', the [defendant] also says that the same enquiry exposes the absence of any factual finding about what 'available cash' the plaintiff had or, alternatively, exposes and error in any finding discernible about that point.
[15] These asserted failings are the matter intended to be encompassed by the proposed amendment to ground 6. The asserted failings are also raised by ground 7."
"Such a consequence is, it is submitted, outside the natural and ordinary consequence of the plaintiff being delayed in its subdivision endeavours. Such a purported loss was not, and is not, foreseeable so as to properly form part of the plaintiff's compensable loss.
No such finding was made by the Honourable trial judge, but in any event the question of whether the plaintiff's claimed damages is foreseeable is a question properly capable of answer by this Court."
"• 'This ground asserts that Blow CJ committed three errors, in four respects. The appellant makes no attempt in the framing of its submissions to identify which submission is relevant to one or more of the asserted errors. In large measure the appellant departs from the errors that it asserts in the drafting of this proposed ground and seeks to raise a number of issues that do not form any ground of appeal. Not only is this fundamentally unfair but it is contrary to the appellant's basal obligation to identify error in the notice of appeal, to comply with rule 657(4)(b) and to comply with the requirements of Practice Direction 3/2017. Given the very unsatisfactory procedural history in the conduct of this appeal by the appellant, it is submitted that no further indulgence should be afforded to it and that it must now be confined, if at all, to the amendments which it has identified in the drafting of ground 6, of which notice was given on 17 April 2018.'
(a) foreseeability of loss: [75], [81] and [94-100];
(c) a failure to prove consequential loss: [77], [79], [80] and [87-91]; and
(d) a Hadley -v- Baxendale submission that loss did not reasonably and naturally flow from the breach and/or was not a kind of loss within the knowledge of the appellant.'
'If the appellant seeks further leave to amend this ground, then leave ought to be refused, not only by reference to the principles in Aon-v- ANU but also for the following specific reasons'."
"In the realm of contract law, the loss of a chance to win a prize in a competition resulting from breach of a contract to provide the chance is compensable, notwithstanding that, on the balance of probabilities, it is more likely than not that the plaintiff would not win the competition . As the contract contained a promise to provide the chance, the breach of the contract resulted in the loss of the chance and that loss was for relevant purposes an actual loss, in the sense in which Dixon and McTiernan JJ used that expression in Fink v Fink . And, where there has been an actual loss of some sort, the common law does not permit difficulties of estimating the loss in money to defeat an award of damages. The damages will then be ascertained by reference to the degree of probabilities, or possibilities, inherent in the plaintiff's succeeding had the plaintiff been given the chance which the contract promised.
This approach is not confined to contracts relating to games of chance, sporting contests or other competitions. Fink v Fink concerned a contract to provide an opportunity for a reconciliation, breach of which was held to entitle the wife to damages. And there can be no doubt that a contract to provide a commercial advantage or opportunity, if breached, enables the innocent party to bring an action for damages for the loss of that advantage or opportunity. So, in The Commonwealth v Amann Aviation Pty Ltd, Mason CJ and Dawson J, Brennan J and Deane J concluded that a lost commercial advantage or opportunity was a compensable loss, even though there was a less than 50 per cent likelihood that the commercial advantage would be realized. Damages for breach of contract were assessed by reference to the probabilities or possibilities of what would have happened.
Damages in tort have also been assessed by reference to the probabilities or possibilities of what will happen or what would have happened. That approach has been frequently adopted in the assessment of damages for personal injuries where a court has been called upon to assess future possibilities and past hypothetical situations. In Malec v J C Hutton Pty Ltd, this Court drew a distinction between, on the one hand, proof of historical facts - what has happened - and, on the other hand, proof of future possibilities and past hypothetical situations. The civil standard of proof applies to the first category but not to the second, particularly when it is necessary to determine future possibilities and past hypothetical situations for the purpose of assessing damages.
In Malec, Deane, Gaudron and McHugh JJ explained the way in which the matter is to be approached in these terms:
'If the law is to take account of future or hypothetical events in assessing damages, it can only do so in terms of the degree of probability of those events occurring. ... But unless the chance is so low as to be regarded as speculative - say less than 1 per cent - or so high as to be practically certain - say over 99 per cent - the court will take that chance into account in assessing the damages. Where proof is necessarily unattainable, it would be unfair to treat as certain a prediction which has a 51 per cent probability of occurring, but to ignore altogether a prediction which has a 49 per cent probability of occurring. Thus, the court assesses the degree of probability that an event would have occurred, or might occur, and adjusts its award of damages to reflect the degree of probability.'
Neither in logic nor in the nature of things is there any reason for confining the approach taken in Malec concerning the proof of future possibilities and past hypothetical situations to the assessment of damages for personal injuries. The reasons which commended the adoption of that approach in assessments of that kind apply with equal force to the assessment of damages for loss of a commercial opportunity, as the judgments in Amann acknowledge." [Footnotes omitted.]
"Notwithstanding the observations of this Court in Norwest, we consider that acceptance of the principle enunciated in Malec requires that damages for deprivation of a commercial opportunity, whether the deprivation occurred by reason of breach of contract, tort or contravention of s 52(1), should be ascertained by reference to the court's assessment of the prospects of success of that opportunity had it been pursued. The principle recognized in Malec was based on a consideration of the peculiar difficulties associated with the proof and evaluation of future possibilities and past hypothetical fact situations, as contrasted with proof of historical facts. Once that is accepted, there is no secure foundation for confining the principle to cases of any particular kind.
On the other hand, the general standard of proof in civil actions will ordinarily govern the issue of causation and the issue whether the applicant has sustained loss or damage. Hence the applicant must prove on the balance of probabilities that he or she has sustained some loss or damage. However, in a case such as the present, the applicant shows some loss or damage was sustained by demonstrating that the contravening conduct caused the loss of a commercial opportunity which had some value (not being a negligible value), the value being ascertained by reference to the degree of probabilities or possibilities. It is no answer to that way of viewing an applicant's case to say that the commercial opportunity was valueless on the balance of probabilities because to say that is to value the commercial opportunity by reference to a standard of proof which is inapplicable.
The conclusion which we have reached on this question finds support in other considerations. The approach results in fair compensation whereas the all or nothing outcome produced by the civil standard of proof would result in the vast majority of cases in over-compensation or under-compensation to an applicant who has been deprived of a commercial opportunity. Furthermore, it is an approach which conforms to the long-standing practice of taking into account contingencies in the assessment of damages.
On the findings made by the trial judge, the Pagini contract would have been entered into but for the contraventions of s 52(1). Although, on the probabilities, it would not have been completed, there was a significant chance that it would be completed. It follows that the Full Court of the Federal Court were not in error in dismissing the appeals."
"As French J found that it was improbable that the Pagini contract would have proceeded to completion, the defendants argue that his Honour must have found that it was improbable that the plaintiffs would have obtained financial benefits under the contract. In the defendants' submissions, the loss of those benefits is the only loss in respect of which the plaintiffs could have recovered under s 82(1) and, as they failed to prove on the balance of probabilities that that loss was the result of the contravening conduct, the plaintiffs' action must fail.
The ultimate objective of the plaintiffs was to acquire the financial benefits that would have flowed to them if the Pagini contract had been entered into and completed. Before that objective could be attained, there were several contingencies which had to be satisfied: the continuation of negotiations with Pagini, their satisfactory conclusion, the obtaining of an underwriter for the proposed share issue, the execution of the contract with Pagini, the satisfaction of the seven conditions precedent which were to be contained in the contract and performance of the contract by Pagini. If the relevant loss be identified as the financial benefits which it was the ultimate objective of the plaintiffs to acquire, the plaintiffs must fail for they failed to prove all the links in the chain of causation. That, indeed, is the defendants' submission. But if the loss of an opportunity to continue the negotiations with Pagini be identified as a loss entitling the plaintiffs to recover under s 82(1), they succeed for they were induced to lose that opportunity. The amount of that loss can be assessed by evaluating the prospects or possibilities of satisfying all the contingencies that stood between the continuing of the negotiations and the ultimate acquisition of the financial benefits that would have flowed from the completion of the Pagini contract. And that, indeed, is the plaintiffs' submission."
"The cases where a plaintiff seeks damages only for breach of a contractual promise to afford the plaintiff an opportunity to acquire a benefit are in a different category from cases under s 82(1) and cases in tort where damage is the gist of the cause of action. In a case like Chaplin v Hicks , the relevant loss is identified by the contractual promise to afford the plaintiff an opportunity to acquire a benefit or to avoid a detriment. A breach of the promise to afford that opportunity necessarily establishes that the loss flows from the breach. In contract cases, a plaintiff may be entitled to nominal damages for loss of the opportunity promised even though the plaintiff fails to prove what, if any, value performance of the unfulfilled promise would have had. But in cases arising under s 82(1) of the Act, as in cases of tort where damage is the gist of the action, a lost opportunity may or may not constitute compensable loss or damage. In such cases, the existence and causation of a compensable loss cannot be proved by reference to an antecedent promise to afford an opportunity." [Footnotes omitted.]
"Where a loss is alleged to be a lost opportunity to acquire a benefit, a plaintiff who bears the onus of proving that a loss was caused by the conduct of the defendant discharges that onus by establishing a chain of causation that continues up to the point when there is a substantial prospect of acquiring the benefit sought by the plaintiff. Up to that point, the plaintiff must establish both the historical facts and any necessary hypothesis on the balance of probabilities. A constant standard of proof applies to the finding that a loss has been suffered and to the finding that that loss was caused by the defendant's conduct, whether those findings depend on evidence of historical facts or on evidence giving rise to competing hypotheses. In any event, the standard is proof on the balance of probabilities.
Although the issue of a loss caused by the defendant's conduct must be established on the balance of probabilities, hypotheses and possibilities the fulfilment of which cannot be proved must be evaluated to determine the amount or value of the loss suffered. Proof on the balance of probabilities has no part to play in the evaluation of such hypotheses or possibilities: evaluation is a matter of informed estimation."
"8.2 Under the heading 'After Tax Interest Paid' is the amount I am instructed was paid by RV Pty Ltd to external financiers in the 2011, 2012, 2013 and 2014 financial years, net of associated tax deductions, and I am instructed that these amounts would not have been paid had the roadway been completed as contracted, and proceeds from allotments been received 3½ years earlier."
"Well, I put it to you this way: the assumption is that everything is the same and but for the breach there would have been no bank loan then if it was going to return to - if you were going - three and a half years in the model should go back to there is no bank loan, ie, the debt has been repaid, shouldn't it? Wouldn't that give a fairer picture of this as a stand-alone model?.....The parts of the spreadsheet that I have used start with the positive cash flows. So what happened earlier has not been taken into account for the reason I gave that we're not looking at the net present value of the total project.
There's a conflict - do you accept that there's a conflict between claiming lost earnings on surplus funds but wanting to be reimbursed the interest cost of borrowing the money?.....No.
Well, as an example, if there was a hypothetical $100 invested by RV you're suggesting they should be $6.20 in lost investment income?.....Yes.
In the final calculation you're claiming a further $6.20 for interest they had to pay the Commonwealth Bank?.....I've used the actual amounts paid to the Commonwealth Bank.
Whatever it is, but there's a double dipping there, isn't there?.....No. I don't believe there is."
"You were asked the question about whether you had been double-dipping by reference to the interest claim - you remember that?.....Yes.
-and you were cut off. Why don't you believe there's double-dipping?.....Because I'm instructed that, but for the breach, there would have been no borrowings, therefore no interest. So, so, clearly, the payment of interest is part of the economic loss."
"7 His Honour erred in calculating and awarding damages to the plaintiff for loss of use of moneys without allowing for his finding that the Defendant was entitled to $440,000 by way of counterclaim.
The sum used to calculate the damages awarded to the Plaintiff for loss of use of moneys should have been reduced by $440,000 in accordance with the evidence accepted by His Honour as the basis of the allowed counterclaim."
"[4] There is a counterclaim. The contract required the plaintiff, subject to certain terms and conditions, to pay the defendant $800,000 plus GST in three instalments. The first instalment, amounting to $400,000 plus GST, was paid in 2005. The plaintiff has not paid the second and third instalments, each amounting to $200,000 plus GST. It contends that, on a proper construction of the contract, it was not required to do so because its liability to pay was conditional upon the defendant performing its obligations in relation to the roadway in a timely manner. The defendant contends otherwise, and has counterclaimed $440,000, comprising $400,000 plus 10% GST."
"[44] The [defendant] submits that in calculating the plaintiff's damages, the honourable trial judge should have, but did not, make allowance for the inevitable outflow of monies which ought to have occurred by payment of the monies which his Honour held were payable under cl 5.8 of the Connector Park Agreement. The issue was raised by the Court in closing submissions [AB 728] but is not addressed in his Honour's reasons.
[45] The appellant submits that it necessarily follows from the success of its counterclaim that the plaintiff's cashflows and profits and losses were necessarily required to be reduced, in consequence of the payments under cl 5.8 falling due."
"HIS HONOUR: What do you say to the proposition that in Mr Rands' calculations, or perhaps - no, sorry - Mr Blackwood's calculations, in the no breach scenario, should he have allowed for an outflow of funds of $400,000?
MR McELWAINE SC: The calculations being necessarily hypothetical, that is a prospect that your Honour may well take into account in assessing the various contingencies.
MR McELWAINE SC: If there had been no breach, then at some time after January 2005, there would have been imposed upon the plaintiff a lawful payment obligation, I'd have to accept that, yes, your Honour."
"He [the defendant's counsel] might be right about that depending on the cross-appeal so I can put that to one side but your Honour's will have seen from my submissions, once you apply an MPV calculation, it can't be $400,000, it has to be something else."
"73 As might be expected, Mr Rands made a number of assumptions (which were not effectively challenged in cross-examination) as to the types of investments, and the rates of return. In each of his calculations, set out at appendices 3-5, he adopted different earning rates and applied a discounted cash flow analysis. As is well understood by accountants, a discount rate is applied to determine the time value of money. A dollar held by a person today is worth more than a dollar held by that person in April 2019.
74 It is for this reason that additional expenditure by the respondent of either $200,000 or $400,000 in 2005, is not to be translated to a reduction in the quantum of damages awarded in either sum: by definition, it is a lesser sum. What it might be will ultimately need to be reassessed by Mr Rands, in the event that this ground succeeds.
75 There are several other points. Blow CJ increased the quantum of the counter claim by $40,000, to allow for GST. In proceeding in this way, his award was plainly excessive. If the correct analysis of His Honour's reasoning is that the appellant, as the supplier, is entitled to receive payment from the respondent, then the appellant is obliged to deliver a tax invoice which includes the GST amount. Upon payment of that amount, the appellant is obliged to account to the ATO for the GST component. The effect of His Honour's order is either that GST has been added twice, or if not the primary amount payable to the appellant has been impermissibly increased, before accounting for GST.
76 The alternative analysis is that no GST is payable upon the award made in favour of the appellant and accordingly His Honour erroneously included GST in the award.
77 Finally, it does not follow that a failure to make allowance for either sum demonstrates reviewable error. The respondent particularised, and Blow CJ correctly understood, the damages claim as one for lost opportunity. The respondent framed the claim within a range of $1,879,840 to $2,710,776, in accordance with the opinion of Mr Rands. Appendix 6 of his report sets out his summary of his various calculations, based on different assumptions about investment rates and discount rates.
78 As is well understood, an assessment of damages for lost opportunity is not required to be proved on the balance of probability. Blow CJ accepted the methodology of the respondent's delayed cash flow calculation and the opinion of Mr Rands. The appellant does not contend that he erred in either respect. He set out the range of figures at [91] and returned to them at [102]. His Honour found that the discount rate was arrived at by Mr Rands as 'the product of what I would call an intuitive synthesis' at [104]. He then found that each of the assumptions made by Mr Rands and Mr Blackwood 'were so conservative that the strict adoption of an earnings rate of 6.2% or 6.6% would not do justice to the plaintiff' at [105] and from this finding he undertook a familiar analysis by doing the best that he could to provide fair compensation to the respondent. He adopted an earnings rate nearer to 9% and a discount rate 'more or less halfway' between 22% and 30% to derive his figure of $2.2M calculated as at September 2014 which he found 'appropriate to compensate the plaintiff for its lost commercial opportunity'.
79 This analysis is an example of the familiar approach to the assessment of damages for a lost, and necessarily hypothetical, opportunity. It was for His Honour to evaluate the relative prospects and to do the best that he could based on the evidence. Accordingly, it does not follow from the fact that because additional expenses of either $200,000 or $400,000 were not taken into account in the evidence of Mr Rands, that the appellant must succeed on this point. The appellant fails to identify how it is said that a failure to take into account the payments would have resulted in a different award. Often it is said that an appellant faces the difficult task of demonstrating that the award is 'out of proportion' to the damage suffered. It is insufficient for the appellant to point to an expense which was not allowed for in the schedule prepared by Mr Blackwood as the award is not framed by reference to a precise mathematical calculation. His Honour reached a value judgment, assisted by the expert opinion evidence, as to an amount of appropriate compensation for the lost commercial opportunity. He was assisted by the evidence of Mr Rands, but ultimately adopted an intuitively reasoned figure which sits well within the possible upper and lower ranges arrived at by Mr Rands. The essential problem for the appellant is that the ground of appeal, and the submissions in support, fail to grapple with the obvious force of the fact that in a lost opportunity assessment, the quantum of damages is necessarily a broad brush assessment involving, a 'degree of speculation and guesswork'.
80 For these reasons, the failure to include an item of expense does not compel the conclusion that in calculating the damages amount his Honour misapprehended the facts or that the amount awarded is so inordinately high as to be a 'wholly erroneous estimate of the damage suffered'." [Footnotes omitted.]
[8] It is convenient to deal with the counterclaim before addressing the plaintiff's claim. The outcome of the counterclaim depends upon the interpretation of the introductory words of cl 5.8, namely, 'In consideration for Connector Park completing its obligations as set out in this clause 5 ...'.
[9] The defendant contends that, because it undertook all the work required by cl 5.6, it completed 'its obligations as set out in this clause 5', and is therefore entitled to the payment of the two sums totalling $400,000 plus GST. The plaintiff contends that, because the required construction work was not completed by 6 January 2005 as required by cl 5.6, and because the defendant did not do all things necessary to ensure that the roadway was taken over as a road maintainable by the council by 6 July 2005 as required by that clause, it cannot be said that the defendant completed 'its obligations as set out in this clause 5'. It contends that the defendant completed its obligations after the deadlines provided for in cl 5.6, and thus not 'as set out in' cl 5.
[10] The proper approach to the interpretation of the critical words in cl 5.8 is as stated by Gleeson CJ, Gummow, Hayne, Callinan and Heydon JJ in Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52, 219 CLR 165 at [40], where their Honours said:
'The meaning of the terms of a contractual document is to be determined by what a reasonable person would have understood them to mean. That, normally, requires consideration not only of the text, but also of the surrounding circumstances known to the parties, and the purpose and object of the transaction.'
[11] The purposes and objects of the parties' transaction are clear. The defendant agreed (a) to terminate its contract for the purchase of about 3.17 hectares of land near Ernest Street, enabling the plaintiff to acquire that land from Mr Holyman's executors; and (b) to construct the Connector Park roadway and arrange for it to be taken over as a public road maintainable by the council, so that there would be much better road access to the land that the plaintiff hoped to subdivide. The plaintiff proposed to make money from a large residential subdivision. The acquisition of the 3.17 hectares and the construction of the roadway would help it to achieve that objective. In return, the plaintiff promised to pay the defendant a total of $600,000 plus GST, or $800,000 plus GST if the rezoning of the rural land went through, as well as allowing the defendant a temporary right of way between its Connector Park land and Ernest Street. The amounts that the plaintiff promised to pay may well have been determined by reference not only to the value of the 3.17 hectares and the cost of constructing the roadway, but also by reference to the commercial advantages accruing to the plaintiff as a subdivision developer as a result of the availability of road access to the subdivision site from both Ernest Street and the Kings Meadows Connector. It is significant that the defendant had been proposing to construct the Connector Park roadway in accordance with its subdivision permit of 29 December 1998. The construction of that roadway resulted in advantages to both parties as subdividers of their respective lands.
[12] The plaintiff's contention as to cl 5.8 is that a reasonable person would have understood both parties to have intended that the defendant would become entitled to either $200,000 or $400,000, plus GST, if it fulfilled the various obligations imposed by cl 5.8 within the time limits specified in that clause, but that it would be entitled to none of that money if any such obligation was not performed on time, even though the defendant would have a continuing duty to fulfil every such obligation. That is to say, if the defendant completed the construction of the roadway, but did so later than the contract required, then its right to receive payment in respect of the work and materials involved, and in respect of the commercial advantage thereby conferred on the plaintiff, would be lost. The consequences for the defendant would be so extreme in such a situation that I do not think that any reasonable person would regard the parties as having intended cl 5.8 to have the meaning contended for by the plaintiff.
[13] An analysis of the text of the clause gives some support to the interpretation contended for by the defendant. There is no express reference to time limits in the introductory words of cl 5.8. If the parties had intended monies to be payable under that clause only if contractual obligations were fulfilled on time, they could very easily have used words that made such an intention clear. They could have referred to the defendant 'completing its obligations as and when required by this clause 5'. Further the use of the word 'consideration' suggests an intention that the defendant was to be paid for doing what it promised to do, rather than getting paid a bonus, or two bonuses, if its contractual obligations were fulfilled within a certain time.
[14] In my view a reasonable person would not have understood the introductory words of cl 5.8 as meaning that the defendant was to become entitled to payments under that clause only if it completed its relevant contractual obligations in accordance with such time limits as were specified in cl 5.
[15] The Connector Park roadway was taken over by the council. The area zoned rural was rezoned as residential under the Launceston Interim Planning Scheme 2012. Although cl 5.8(b) expressly provided for a payment of $200,000 plus GST only in respect of rezoning 'under Part 3 of the Launceston Planning Scheme 1996', the plaintiff accepts that the superseding of that planning scheme by the 2012 interim scheme makes no difference to its obligations. Once the roadway was taken over by the council, the plaintiff became liable to pay the defendant $200,000 plus GST pursuant to cl 5.8(a). Once the rezoning took effect, the plaintiff became liable to pay the defendant a further $200,000 plus GST pursuant to cl 5.8(b). Those amounts have not been paid.
[16] The defendant is therefore entitled to judgment for $440,000 on the counterclaim. It made no claim for interest."
"1 At [9-14], he [the trial judge] misconstrued the express provisions of the agreement in writing between the Appellant and the Respondent in that, properly construed, the consideration for the making of payments by the Respondent to the Appellant pursuant to clause 5.8 was conditionally expressed upon satisfaction by the Appellant of each, and every, obligation imposed upon it to construct and dedicate the Connector Park road, as a highway;
(i) if the appellant is the supplier pursuant to the Connector Park agreement, then it is entitled as a matter of law to charge and receive payment from the respondent for the GST component of the supply, upon delivery of a tax invoice which includes the GST amount. On this basis, the effect of His Honour's reasoning is to calculate the GST twice; or
(ii) in the alternative analysis, if no GST is payable upon the counterclaim as an award of damages, then His Honour ought not to have made allowance for it."
"... if the language is open to two constructions, that will be preferred which will avoid consequences which appear to be capricious, unreasonable, inconvenient or unjust ...".
Any consideration provided for in this document for a Supply is expressed to be exclusive of GST, and in the event of GST being payable on a Supply made pursuant to this document:
(a) the Recipient of the Supply will reimburse to the Supplier the amount payable by the Supplier as GST on the Supply; and
(b) the Supplier will give to the Recipient a Tax Invoice for the Supply in a form which complies with the GST Act."
Connector Park Pty Ltd
RV Pty Ltd [2018] TASFC 13
17 The plaintiff is claiming damages for lost opportunity. The basis for awarding damages for a lost opportunity was explained by French CJ, Kiefel J (as she then was) and Keane J in Badenach v Calvert [2016] HCA 18, 331 ALR 48 at [39]- [41] as follows:
His Honour ought to have applied the findings in Bland v Levi [2000] NSWSC 161 at [17]- [22] (cited by His Honour at [27]), and held that completion of all the roadworks that the defendant was required by the contract to complete, fell within the scope of the plaintiff's right of carriageway granted by cl 5.4 of the contract, which right was not limited by either the heading of cl 5.4 or by cl 5.3 of the contract.
(1972) 127 CLR 454
(1961) 108 CLR 642
(2009) 239 CLR 175
(1994) 179 CLR 332
(1976) 11 ALR 305