[2018] ACAT 58
ACT Civil and Administrative Tribunal
2018-05-25
Original judgment source is linked above.
P AND G BUILDERS PTY LIMITED V FLAHERTY (Civil Dispute) [2018] ACAT 58
Catchwords: CIVIL DISPUTE - unpaid final progress claim and variations claim arising from a residential building contract - termination of contract for non-payment of money owed - counterclaim for defective works - onus of proof in response to a debt application - builder not liable to rectify defects where contract validly terminated
Legislation cited: Building Act 2004 ss 42, 69
Cases cited: Chetty and Anor v Automotive Computer Diagnostic Centre (ACDC) Pty Ltd [2016] ACAT 38
Gordon v Macgregor [1909] HCA 26; (1909) 8 CLR 316
Leeper v The Primary Producers' Bank of Australia Ltd [1935] HCA 19; (1935) 53 CLR 250
Inglis v John Buttery & Co (1878) 3 App Cas 552
Onesteel Manufacturing Pty Ltd v United Kg Pty Ltd [2006] SASC 119
PCM Office Services Pty Ltd & Anor v Mi [2018] ACAT 36
York Air Conditioning and Refrigeration (Australasia) Pty Ltd v The Commonwealth [1949] HCA 23; (1949) 80 CLR 11
When the owner pays the final progress payment, the builder must hand any keys for the building works to the owner.
practical completion means that the building works have reached the stage where the builder certifies that they have been completed in accordance with the contract, except for minor omissions and, where applicable, has done all that the builder is required to do under the contract to enable a certificate of occupancy to be obtained.
Thanks for arranged the inspection yesterday (26th July 2017). As the assessor John told us yesterday, we are not reach the stage of practical completion. This is because the inspection did not passed, due to you have some works need to be fixed. Once he gives you the certificate for the inspection passed, you have to give a copy to us. Then we can reach to the stage of practical completion. (sic)
We found the following works need to be done by handover on 7th August 2017.
Laundry - Double Power Point x 2 in laundry (inclusion list) One upper and one under the bench. The wire was put into this area. Mark knows this and I have two photos to prove this.
Outside - Power Point outside for the water pump (This should be in the quote)
Kitchen- One of the Kitchen drawer has paint on it. We told Mark before he said will clean it or change it for us.
Alfresco - Sliding screen doors missing on one side and other side very lose and not fitting correctly.
We look forward to moving in on the 7th August and paying all money to you. (sic)
Thanks for your letter date on 24 July 2017 about the stage of the practical completion. Due to the inspection failed on 26 July 2017, we cannot reach to the stage of practical completion until we pass the inspection (information advised from Mr John Mihaljevic - Principal Building Surveyor from Certified Building Solutions Pty Ltd). Once the inspection passed and you received the notification or certificate from John. Then we can successful reach the stage of practical completion.
Thanks for your arrangement for the inspection. We look forward to reach the stage of practical completion and handover the keys. (sic)
We hereby acknowledge receipt of your defects list pursuant to clause 23.2 of the contract dated 22/12/2016. Emailed 27/7/2017.
We didn't send any defect list you on 27 July. We only send a incompleted works to you as per contract. You have to complete all works as the contract. If not, we cannot pay you the last payment.
You are a experienced builder, the owner didn't go to check the house and works how to prepare the defect lists to you? You are a licensed builder you should know what is the right things to do to the owner and yourself.
You need to do the power point under the bench in laundry and put other screen door. Once the inspection pass and signed by the certifier. Then we go to the practical completion and then we will pay. (sic)
An inspection of the building work has been carried out:
As a result of that inspection I hereby certify that the building work complies with section 42 of the Building Act 2004.
Work completed and the registrar would be justified in issuing a Certificate of Occupancy under section 69(2).
(2) If building work involving the erection or alteration of a building as completed is not strictly in accordance with the prescribed requirements for the building work but is substantially in accordance with the requirements, the construction occupations registrar may, on application made by the owner of the parcel of land where the building work has been carried out, issue a certificate that the building as erected or as altered is fit for occupation and use as a building of the class stated in the approved plans for that building work.
Pursuant to clause 24 of the contract dated 22/12/2016, we hereby notify you that you are in breach of the contract and that we, as of today's date suspend the building works. The details of the breach set out below.
The price or cost of the variation, as the case may be, is added to or deducted from the contract price. Payment for the variation must be made at the next progress payment stage (unless a different time is stated in the variation agreement). Any credit to the owner is to be made to the final progress claim.
7. Within 65 days after the date of practical completion, the owner must provide the builder with a written list of the claimed defects if any, in the building works. The builder must within 15 days after the expiry of the 65 day period rectify the defects resulting from work or materials not being in accordance with the contract.
Private property. Trespassers will be prosecuted to the full extent of the law[4]
The owner must not take possession of the building works without the builder's consent until all outstanding money owed to the builder is paid.
3. If the owner asks for a variation, the builder must reply in writing to the owner within 5 days of the request, or as soon as is reasonably practicable. The owner is, at the builder's election, to pay the administration fee stated in item 14 of Attachment A for any variation requested by the owner.
4. The builder has the right to refuse a variation.
5. The builder and the owner must both agree in writing to the variation, its details and how much it will cost or save prior to commencement of the variation work.
Onus of proof must be approached with caution, especially in Tribunal proceedings. However in my view, in a claim for unpaid fees, the person seeking payment must at least be able to demonstrate in a reasonably transparent manner the tasks done referenced to the time spent. Only with that information disclosed can the reasonableness of the time spent, and implicitly the fees charged, be considered. For example, in Onesteel, the builder itemised its costs by reference to different components and/or sequential tasks that it contended were necessary to construct the building. Having done so, the onus moved to the builder's client to show why, in relation to each costed component, the amount was "neither reasonable nor proper".[8]
Through the course of the negotiations to reach a final contract sum, Mr Flaherty and his wife present at the time, instructed me to remove that wall and door. I then did that and the amount was deducted from the previous contract amount. I didn't document that in the inclusions list or have the plans amended. Through the course of the work, Mr Flaherty spoke to both myself and Mark and requested us to reinstate those works. We reinstated those works and charged a variation accordingly.[11]
Now, I think it is quite fixed - and no more wholesome or salutary rule relative to written contracts can be devised -- that where parties agree to embody, and do actually embody, their contract in a formal written deed, then in determining what the contract really was and really meant, a court must look to the formal deed and to that deed alone. That is only carrying out the will of the parties.
Powder coat aluminium sliding windows and doors, double glazed, standard colour, all with fly screens and locks.
Mr Flaherty brought this to our attention as soon as it happened, as he did with every part of the works on the job through the process of building, as Mr Flaherty was living on the site.[19]
When the parties have shown by their conduct that they understand and can apply the terms of a contract without difficulty, a court should be very reluctant indeed to pay no attention to such conduct by holding that the terms of the contract are unintelligible by reason of uncertainty.
Alter the glass ensuite wall as directed and described in the amendments prepared by Ray and Ping Flaherty. An allowance of $1,200.00 has been included for the glass section of this wall.
Because in deleting a component like that, it doesn't reduce the time of the project, which - and the time that we're on the job relates to our overheads, and our profit isn't based on the amount of work that we do, our profit is based on the job in itself, so if there isn't a significant change to the actual scope of the works which would significantly impact on our profit, then our profit that we have deemed that we require to do this work stays as is[23]
There was an area of the existing building that was damaged by rain entry in the building which was caused by the works that we had exposed. That water damaged part of the ceiling through the existing residence. We had a discussion with Mr Flaherty, we being myself and Mark Gillett, in which we advised Mr Flaherty that at our cost we would repair those water damaged areas. Mr Flaherty advised us that he wanted the whole of the ceiling replaced and insulation. We advised him of an estimate of the cost, which I can't recall at the time the amount was, and we were given an instruction to go ahead and do that work. We went ahead and did that work, charged Mr Flaherty for those amounts that were extra over the costs for the water damage that we accepted to repair ourselves at our cost.
Do CPV4 and 5 represent any component of the damage done by the water?No.
But I can say for certain that none of those costs in either of those variations included any of the works that we agreed with Mr Flaherty that we would repair that were water damaged by that leak[26]
Remove existing sheet flooring, fix floor frame and resheet
Remove sheet, straighten walls, replaster and paint
Remove sheets, straighten walls, resheet and plaster and paint
Remove bench top, disconnect sink, remove cupboards, level existing base, replace cupboards and make good all defected area
Ceiling is 25mm out of level. To fix all trusses need to be removed and cut framing down to correct height which will cost over $14,000. It would be done on a cost plus builder's fee
This is unable to be fixed unless you remove the glass sliding door, top the whole floor with a levelling agent
Remove glass sliding door frame and pack level. Replace
This is because the new timber wall frame from the extension to the existing house was 30mm higher. You would have to remove the roof sheets, cut down the wall frames etc. This would effect the internal gyprock, cornice, external facia and gutter, eave sheets. Would cost over $25,000. Charged at cost plus builder's fee
Remove tank and concrete slab and pump. Replace concrete slab on proper gravel base with new concrete slab, refit tank and equipment
Pull out pantry cupboards, remove wall sheets, plumb up existing sliding cavity door frame, replaster and paint, make good all areas
Remove door frame and accommodate substructure floor
Sand back original timber architraves and skirtings in all existing bedrooms affected and repaint
Remove toilet by plumber, remove tiles. Refix toilet properly and refix tiles
[1] Transcript of proceedings, 19 February 2018, page 113, lines 1 - 19
[2] Transcript of proceedings, 19 February 2018, page 113, lines 23 - 44
[3] Transcript of proceedings, 19 February 2018, page 101, lines 35 - 43
[4] Transcript of proceedings, 19 February 2018, page 35, lines 40 - 41
[5] Transcript of proceedings, 19 February 2018, page 61, lines 42 - 45
[6] For these principles, see Chetty and Anor v Automotive Computer Diagnostic Centre (AC/DC) Pty Ltd [2016] ACAT 38 at [18] - [25]. Quantum meruit means, in substance, an obligation to pay a reasonable sum for a benefit obtained
[7] PCM Office Services Pty Ltd & Anor v Mi [2018] ACAT 36]
[8] PCM Office Services Pty Ltd & Anor v Mi [2018] ACAT 36 at [45]
[9] Transcript of proceedings, 20 February 2018, page 253 line 45 - page 254, line 1
[10] Transcript of proceedings, 20 February 2018, page 255 lines 5 - 9
[11] Transcript of proceedings, 20 February 2018, page 250, lines 8 - 15
[12] Transcript of proceedings, 20 February 2018, page 250, lines 20 - 22
[13] Transcript of proceedings, 20 February 2018, page 252, line 14
[14] Inglis v John Buttery & Co (1878) 3 App Cas 552 at 577
[15] Gordon v Macgregor [1909] HCA 26; (1909) 8 CLR 316 at 323
[16] Transcript of proceedings, 20 February 2018, page 276 lines 15 - 21
[17] Transcript of proceedings, 20 February 2018, page 262, lines 39 - 40
[18] Transcript of proceedings, 20 February 2018, page 272, lines 4 - 30
[19] Transcript of proceedings, 20 February 2018, page 233, lines 22 - 24
[20] Transcript of proceedings, 20 February 2018, page 195, lines 10 - 34
[21] Transcript of proceedings, 20 February 2018, page 195, line 33
[22] York Air Conditioning and Refrigeration (Australasia) Pty Ltd v The Commonwealth [1949] HCA 23; (1949) 80 CLR 11 at 53
[23] Transcript of proceedings, 20 February 2018, page 200, lines 30 - 35
[24] Transcript of proceedings, 20 February 2018, page 217, lines 20 - 21
[25] Transcript of proceedings, 20 February 2018, page 290, lines 10 - 15
[26] Transcript of proceedings, 20 February 2018, page 248, line 39 page 249, line 44
[27] Transcript of proceedings, 20 February 2018, page 247, lines 40 - 43 and page 255, lines 5 - 8
[28] Transcript of proceedings, 20 February 2018, page 249, line 44
[29] Transcript of proceedings, 19 February 2018, page 129, lines 21 - 26
[30] Transcript of proceedings, 20 February 2018, page 143, line 11 - page 144, line 15.
[31] Transcript of proceedings, 19 February 2018, page 177, lines 10 - 21
Cases cited: Chetty and Anor
Automotive Computer Diagnostic Centre
(1909) 8 CLR 316
(1935) 53 CLR 250
(1949) 80 CLR 11