Carthew-Wakefield v Sorell Council (No 4) [2025] TASCAT 130
1. The appellant's application for costs is refused.
2. Each party is to bear their own costs of the appeal.
Environment and planning - Planning appeal - Application for costs
Launceston City Council v Tasmanian Water and Sewerage Corporation Pty Ltd (No.2) [2015] TASSC 29;
J ID Constructions Pty Ltd v Northern Midlands Council (No.2) [2024] TASCAT 126;
Calderbank v Calderbank [1975] 3 WLR 586;
A and J DeCesare v Clarence City Council [2010] TASRMPAT 178;
Leichhardt Municipal Council v Green [2004] NSWCA 34;
Softmed Manufacturing Pty Ltd v Secretary, Department of Health and Aged Care (Costs) [2024] FCA 857;
Acton View Tas Pty Ltd and Ors v Clarence City Council and Ors [2021] TASRMPAT 09;
BDR21 v Australian Broadcasting Corporation (No.2) [2021] FCA 1347;
Loughhead and Ors v Hobart City Council and Anor [2015] TASRMPAT 64B
(1) Subject to this clause, each party to proceedings in relation to an appeal or application is to pay its own costs.
(2) The Tribunal may, under this clause, order a party to proceedings in relation to an appeal or application to pay all or part of the costs of another party to the proceedings if the Tribunal is satisfied that it is fair and reasonable to do so.
(3) For the purposes of subclause (2) , the Tribunal may take into account any of the following matters:
(a) whether the proceedings appear to the Tribunal to have been instituted merely to delay or obstruct;
(b) whether in the Tribunal's opinion a party has raised frivolous or vexatious issues;
(c) the relative merits of the claims made by each of the parties;
(d) whether in the Tribunal's opinion a party has unnecessarily or unreasonably prolonged the proceedings or increased the costs of them;
(e) whether a party has failed, without reasonable excuse, to comply with a direction or order of the Tribunal;
(f) whether a party has failed to comply with any relevant law or planning scheme, within the meaning of the Land Use Planning and Approvals Act 1993;
(g) the nature, complexity and outcome of the proceedings;
(h) the capacity of the parties to meet an order for costs;
(i) any other matter that the Tribunal considers relevant.
5. Clause 12(1) establishes a general rule that each party should pay their own costs. That is subject to a power in cl 12(2) permitting the Tribunal to make a costs order if it is satisfied that it is fair and reasonable to do so.
6. Clause 12(3) sets out matters which the Tribunal may take into account in considering whether it is fair and reasonable to make a costs order. The Tribunal is not confined to those matters and is not required to take them into account or to make specific findings in respect to them: Launceston City Council v Tasmanian Water and Sewerage Corporation Pty Ltd (No.2) [2015] TASSC 29 at [27]. It is, however, usual for parties to frame submissions in the context of some or all of the matters listed in cl 12(3).
7. The Tribunal should consider not only whether any single matter is sufficient on its own to exercise the discretion, but also the collective weight of relevant matters: 9 Sandy Bay Road Pty Ltd v Hobart City Council [2019] TASRMPAT 59B at [27]. If satisfied that it is fair and reasonable to award costs, the Tribunal has a broad discretion to make such orders as it sees fit: State of Tasmania v Anti-Discrimination Tribunal [2008] TASSC 23 at [13] and [17]-[20]. The discretion must be exercised judicially and not arbitrarily or capriciously: Summers v Repatriation Commission (No.2) [2015] FCAFC 64 at [13]- [14].
8. The principle articulated in Calderbank v Calderbank [1975] 2 All E.R 333, and applied widely in litigious matters, is intended to extract a resolution on particular terms at peril of a costs order if it is ignored. It requires an explicit notification to the other party of the fact that the proposal will be brought to the attention of the court or Tribunal on the question of costs. It is a principle which will allow a departure from the normal rule that costs follow the event, in circumstances where a successful party has previously rejected an offer to settle which was more favourable than the result that party ultimately obtained. Its function, or the function of an offer to settle in the context of planning matters is more difficult to judge.
9. Clearly it is a procedure more suited to an action in damages where the quantum offered and the quantum awarded can be compared and a conclusion reached about whether a more favourable result was achieved or not. This proposition is borne out by the fact that in some jurisdictions such as Victoria, offers are restricted to actions for damages. In many planning matters, it is difficult if not impossible to quantitatively and objectively assess whether a settlement proposal made before hearing is better than or worse than the result which ultimately ensued making it difficult to reach a correct view about whether any consequence should follow from the fact that an offer was made but not accepted.
10. The Tribunal considers that the role and function of the Calderbank offer in the Tribunal is limited. Its relevance to costs lies in the extent to which the fact of the offer and its terms, and its rejection constitute conduct which unreasonably prolongs the appeal (Section 28 (3) (d)) and perhaps the outcome of the appeal (Section 28 (3) (g)) but only to the extent that it can be concluded, in an objectively defensible way, that the outcome procured at hearing is actually worse than that which was offered. Such circumstances will be infrequent.
In every case there will be disparity between the merits of the cases, but the relative merits may be similar. The merits of the case lead to the result "on the merits", but a costs order does not automatically follow, otherwise the result would be the test under this part, when it is not. Something more is required, and the Tribunal considers that the provision requires that there must be a real disparity in the relative merits of the competing claims, such that it can be said "the relative merits so favoured one party over the other, that it is fair and reasonable that the successful party is compensated for their costs".
Carthew-Wakefield
Sorell Council