[2015] TASSC 29
General information, not legal advice.
Supreme Court of Tasmania
2015-06-26
Pearce J
Original judgment source is linked above.
CITATION: Launceston City Council v Tasmanian Water and Sewerage
Corporation Pty Ltd (No 2) [2015] TASSC 29
Administrative Law - Judicial review - Grounds of review - Error of law - Whether any evidence that costs order "fair and reasonable".
Statutes - Acts of parliament - Interpretation - General approaches to interpretation - General matter does not derogate from special matter - Application to provisions within same Act.
Anthony Hordern & Sons Ltd v Amalgamated Clothing and Allied Trades Union of Australia [1932] HCA 9; (1932) 47 CLR 1, applied.
Judgment Number: [2015] TASSC 29
(a) to the Tribunal an amount determined by the Tribunal as being the costs of the appeal; and
(b) to each other party to the appeal an amount determined by the Tribunal as being the appeal costs of that party." [Emphasis added.]
(1) Each party to an appeal is to pay its own costs.
(2) However, the Tribunal may order a party to proceedings to pay all or part of the costs of another party to the proceedings if the Tribunal is satisfied that it is fair and reasonable to do so.
(3) For the purposes of subsection (2), the Tribunal may take into account any of the following matters:
(a) whether the proceedings appear to the Tribunal to have been instituted merely to delay or obstruct;
(b) whether in the Tribunal's opinion a party has raised frivolous or vexatious issues;
(c) the relative merits of the claims made by each of the parties;
(d) whether in the Tribunal's opinion a party has unnecessarily or unreasonably prolonged the proceedings or increased the costs of them;
(e) whether a party has failed to comply with a direction or order of the Tribunal without reasonable excuse;
(f) whether a party has failed to comply with any relevant law or planning scheme;
(g) the nature, complexity and outcome of the proceedings;
(h) the capacity of the parties to meet an order for costs;
(i) any other matter the Tribunal considers relevant."
"When the Legislature explicitly gives a power by a particular provision which prescribes the mode in which it shall be exercised and the conditions and restrictions which must be observed, it excludes the operation of general expressions in the same instrument which might otherwise have been relied upon for the same power."
"Anthony Hordern and the subsequent authorities have employed different terms to identify the relevant general principle of construction. These have included whether the two powers are the 'same power', or are with respect to the same subject matter, or whether the general power encroaches upon the subject matter exhaustively governed by the special power. However, what the cases reveal is that it must be possible to say that the statute in question confers only one power to take the relevant action, necessitating the confinement of the generality of another apparently applicable power by reference to the restrictions in the former power." [Footnotes omitted.]
"However, that maxim, whilst a valuable servant, is apt to be a dangerous master and it is necessary to seek confirmation in the broader context of the whole Act."
"Like all such principles, however, it must be applied subject to the particular text, context and purpose of the statute to be construed."
"A number of considerations and sub-considerations outlined under Clause 6 of the Planning scheme are relevant to the application ... These considerations support the provision of essential services, tourism, and the protection of places of historic and scenic significance for the promotion of communities. They point to a balance between these objectives being achieved with appropriate setbacks, landscaping, external treatments, and lots having sufficient sizes. To ensure, that is, developments can be properly provided with the features and landscaping that they require to minimise visual impacts as much as possible.
In this regard the application is deficient". AB241
"31 The Tribunal is satisfied that an order should be made in favour of the Applicant pursuant to Section 28(2) of the RMPAT Act. The Tribunal is satisfied that it is fair and reasonable to depart from Section 28(1). That is because it finds that the conduct of the Council in refusing to accept the objective advice of its own planners, and in prolonging the resolution of the matter in the face of expert evidence which required such result, without any evidence to justify the contrary position, unnecessarily prolonged the proceedings; unnecessarily increased the costs of the proceedings; unreasonably prolonged the proceedings; and unreasonably increased the costs of them. (Section 28(3)(d) of the RMPAT Act) (original emphasis).
32 That conclusion exposes another relevant matter which is that the relative merits of the claims made by each of the parties were significantly in favour of the Applicant's case and not at all in favour of the position adopted by the Council up until the point it resolved the matter. In AJ deCesare v Clarence City Council [2010] TASRMPAT 178, at 13, the Tribunal dealt with the situation where the Council had refused a development application contrary to the recommendation of its own planning officer. The Tribunal said this:
'The Appellant seeks to introduce this fact as a matter the Tribunal might consider relevant under the catchall provision appearing in Section 28(3)(i). The Appellant submits that the refusal by the Council should be scrutinised carefully. It is acknowledged by the Applicant that Councils are entitled to make decisions contrary to officer recommendation, and indeed, this regularly occurs. It is important to recognise at the outset that it is not the failure of the Council to follow its planning officer's recommendation that is relevant. The Tribunal exercises no jurisdiction over the conduct of the Council, and has no jurisdiction to award costs on the basis of the conduct of the Council when it was seized of the matter. Thus, the failure to follow the recommendation of the Planning Officer will only be relevant insofar as, and if the Council at appeal maintains its refusal in the face of the Appellants' evidence, and itself, adduces little or no evidence to support its case against the Appellant. That would be relevant because it would amount to conduct that occurs in the context of the appeal and which is a relevant general consideration, as well as a matter which probably falls within the scope of Section 28(3)(c) and 28(3)(d).'
33 The Tribunal finds in this case that the conduct of the Council falls within the scope of Section 28(3)(c) of the RMPAT Act. Where, as here, the Councils failure was to do nothing, the impact of that failure was to necessitate the obtaining of expert reports and the preparation for a hearing. None of that should have been necessary and had the Council discharged its function with diligence would not have been. It should pay the Applicant's costs.
34 The Tribunal wishes to add one further observation about matters dealt with under section 17 of the RMPAT Act. That section requires the Tribunal to make a decision about a development application which has been appealed, and mediated, and about which a proposal intended to resolve the appeal, is put to it. In all such cases the Tribunal undertakes a process whereby it assesses the development application, the appeal grounds, and the proposed resolution recorded in the consent memorandum against the relevant parts of the planning scheme. If it is satisfied that the resolution which is proposed is 'appropriate' and a decision in those terms is open to it, the Tribunal may proceed to make such decision. The Tribunal powers on a Section 59 appeal include a power of refusal. In adopting the resolution contained in the consent memorandum the Tribunal was determining that a refusal of the development application was an inappropriate response to the development application having regard to the matters made relevant by the planning scheme. In that respect there has been a determination on the merits. Admittedly, that is not after a full merits hearing where oral evidence was led, and as that concept is described by Porter J, but it nevertheless constitutes a decision of the Tribunal arrived at after thorough and careful consideration of the matter. The Tribunal does not simply 'rubber stamp' consent memoranda. The Tribunal has made that point previously; see for example LA Arnold Pty Ltd v Sorell Council [2012] TASRMPAT 126, C and H Alexander v Glenorchy City Council [2012] TASRMPAT 019."
"The Government believes that the starting point should be that parties should meet their own costs. It is also believed that this was the intention of the Parliament when the original bill was considered in 1993.
In August the minister announced that legislation would be developed to deal with the recent decision of the Supreme Court and this bill delivers on that commitment. However, while the primary purpose of this bill is to make clear that, in matters before the tribunal, parties will ordinarily bear their own costs, at the same time there must be clear disincentives against inappropriate behaviour. In this context, inappropriate behaviour would include vexatious litigation, time wasting and non-compliance with tribunal requirements, et cetera.
There is also a need for the tribunal to be able to consider particular circumstances where it is fair and reasonable to order that one party pays the costs of another party. To deal with these matters, the bill both identifies a number of specific behaviours which are considered to be inappropriate as well as providing a general discretion to the tribunal to take account of any other matters relevant to its decision.
The net result of the passing of this bill, Mr President, will be an appropriate balance between, on the one hand encouraging public participation in planning and environment matters and, on the other, discouraging frivolous and vexatious legal action against well-thought-out development proposals and inappropriate behaviour in an appeal."
"16 Statutory powers to award costs may be found in one of three forms. The first is an unconstrained conferral of power without direction or limitation. ... As was explained by Gaudron J and Gummow J in Oshlack [v Richmond River Council [1998] HCA 11; (1998) 193 CLR 72], adapting the words of Dixon J in Water Conservation and Irrigation Commission (NSW) v Browning (1947) 74 CLR 492 at 505 the power is 'unconfined except in so far as "the subject matter and the scope and purpose" of the legislation may enable an appellate court to pronounce the reasons given by the primary judge to be "definitely extraneous to any objects the legislature could have had in view"': Oshlack (at 81 [22]).
17 As identified in Latoudis v Casey (1990) 170 CLR 532 the primary and generally the only relevant consideration is that the power is conferred 'to compensate the successful party against the expense to which that party has been put by reason of the legal proceedings': Oshlack (at 82 [25]); see also Ruddock v Vadarlis (2001) 115 FCR 229 at 235 [12] (Black CJ and French J).
18 The second category of cases covers those which expressly identify the principle that the power to award costs is intended to permit the successful party to be compensated or indemnified for costs incurred in the litigation, by providing that 'the court is to order that the costs follow the event unless it appears to the court that some other order should be made': Uniform Civil Procedure Rules 2005, r 42.1.
19 The third category of cases encompasses those, like Pt 16, r 4(2) [of the Land and Environment Court Rules 1996 (NSW)], which provide as a general rule that there shall be no order as to costs, with a discretionary power to depart from that rule in particular circumstances, including where the court considers that it is fair and reasonable."
"I think the guiding principle still stands as it left the House of Lords in the famous case of Donald Campbell & Co v Pollack [1927] AC 732, that the general discretion is absolute and unfettered, except that it must be exercised judicially, not arbitrarily or capriciously, and that it cannot be exercised on grounds unconnected with the litigation."
"The power conferred by the section is to be exercised judicially, that is to say not arbitrarily, capriciously or so as to frustrate the legislative intent. However, subject to such considerations, the discretion conferred is, to adapt the words of Dixon J, unconfined except in so far as 'the subject matter and the scope and purpose' of the legislation may enable an appellate court to pronounce the reasons given by the primary judge to be 'definitely extraneous to any objects the legislature could have had in view': Knight v FP Special Assets Ltd (1992) 174 CLR 178 at 205."
"The objectives of the resource management and planning system of Tasmania are -
(a) to promote the sustainable development of natural and physical resources and the maintenance of ecological processes and genetic diversity; and
(b) to provide for the fair, orderly and sustainable use and development of air, land and water; and
(c) to encourage public involvement in resource management and planning; and
(d) to facilitate economic development in accordance with the objectives set out in paragraphs (a), (b) and (c); and
(e) to promote the sharing of responsibility for resource management and planning between the different spheres of Government, the community and industry in the State." [Emphasis added.]
"When there is an issue of whether a thing falls within the description of a word or phrase in a statute, a question of law is shown if, on the facts found, only one conclusion is open; if different conclusions are reasonably possible, the determination of the correct conclusion only involves a question of fact: Attorney-General (Tas) v Cameron [2007] TASSC 22; (2007) 152 LGERA 45 per Blow J (as he then was) at 65 [71] and the cases cited. On that basis, the question is whether the conclusion was one that no tribunal, acting judicially and properly instructed as to the relevant law, could have reached: Protective Security Pty Ltd v Bedelph [2004] TASSC 128; (2004) 13 Tas R 354 per Crawford J (as he then was) at 363 -364 [22] - [23], per Blow J at 381 [69] - [70]."
"To say of a finding that it is perverse, that it is contrary to the overwhelming weight of the evidence, that it is against the evidence and the weight of the evidence, that it ignores the probative force of the evidence which is all one way or that no reasonable person could have made it, is to say the same thing in different ways. Upon proof that the finding of a jury is vitiated in this way, it will be set aside because it is wrong in fact. Since the Act does not allow this Court to correct errors of fact, any argument that the finding of a Workers' Compensation Commission judge is vitiated in the same way discloses no error of law and will not constitute a valid ground of appeal. It is also pointless to submit that the reasoning by which the court arrived at a finding of fact was demonstrably unsound as this would not amount to an error of law: R v District Court of the Metropolitan District Holden at Sydney: Ex parte White; [1966] HCA 69; (1966) 116 CLR 644 at 654."
"The court is limited, relevantly, to points of law. The finding of what have been called the primary facts of a case does not, in itself, expose the trial judge to review on a point of law, unless it can be shown that there is no evidence of a primary fact and that, this being crucial to his decision, the judge's fact finding has involved an error of law. If there is evidence, or if there are available inferences which compete for the judge's acceptance, no error of law occurs simply because the judge prefers one version of the evidence to another or one set of inferences to another. This is his function. The evaluation of competing evidence and inferences is reserved in compensation cases to the judge of the Compensation Court. Even if the evidence is strongly one way, the appeal court may not intervene simply because it reaches a different conclusion and this even if it regards the conclusion of the trial judge as against the weight of the evidence."
"The question whether there is any evidence of a particular fact is also a question of law: Sittingbourne Urban District Council v Lipton Ltd ([1931] 1 KB 539 at 544) and Mersey Docks and Harbour Board v West Derby Assessment Committee ([1932] 1 KB 40 at 110, 111). But if there is evidence of the fact, the question whether that evidence ought to be accepted in whole or in part, or ought to be accepted as sufficient to establish the fact, is itself a question of fact and not a question of law, unless, of course, there is some law which provides that the particular evidence, when given, is to be taken to establish the fact."
"The question whether there is any evidence of a particular fact is a question of law. Likewise, the question whether a particular inference can be drawn from facts found or agreed is a question of law. This is because, before the inference is drawn, there is the preliminary question whether the evidence reasonably admits of different conclusions. So, in the context of judicial review, it has been accepted that the making of findings and the drawing of inferences in the absence of evidence is an error of law." [Citations removed.]
Do the Tribunal's reasons disclose an error of law?
"(a) The Tribunal's finding (at [31]) that the Appellant by its conduct 'prolong[ed] the resolution of the matter in the face of expert evidence which required such result';
(i) is a finding of fact unsupported by any evidence.
(ii) is against the fact that none of the expert evidence supported the final outcome; it all supported the original proposal.
(iii) is against the fact that none of the plans appended to the consent memorandum and the final approval formed part of the original application or of any of the expert evidence.
(b) The Tribunal overlooked or failed to have any regard to the fact that the proposal that was approved by way of the consent orders that were made as the result of agreement between the parties, with the conditions imposed on it by the parties' agreement, differed substantially from the original proposal.
(c) The Tribunal's findings (at [31]) that the Appellant by its conduct 'unnecessarily prolonged the proceedings; unnecessarily increased the costs of the proceedings; unreasonably prolonged the proceedings; and unreasonably increased the costs of them' were all findings of fact that were unsupported by any evidence.
(d) The Tribunal has not identified in its reasons any evidence to support the findings of fact (at [31]) that the Appellant by its conduct 'unnecessarily prolonged the proceedings; unnecessarily increased the costs of proceedings; unreasonably prolonged the proceedings; and unreasonably increased the costs of them'.
(e) In making its findings (at [32] and [33]) purporting to be findings of fact concerning 'the relative merits of the claims made by each of the parties' (RMPAT Act, s 28(3)(c)):
(i) the Tribunal appears to have based those findings solely on the fact that an application for a permit was granted by consent orders subject to conditions agreed to by the parties together with 'the position adopted by the Council up until the point it resolved the matter'; but ignores the fact that the proposal that was approved by way of the consent orders that were made as the result of agreement between the parties, with the conditions imposed on it by the parties' agreement, differed substantially from the original proposal.
(ii) the Tribunal erroneously put the Appellant's failure to determine the original application for a permit, resulting in the application under the RMPAT Act, s 59(3), 'within the scope of s 28(3)(c)', that is, as a matter going to 'the relative merits of the claims made by each of the parties', ignoring the fact that the proposal that was approved by way of the consent orders that were made as the result of agreement between the parties, with the conditions imposed on it by the parties' agreement, differed substantially from the original proposal.
(iii) having regard to the fact, as the Tribunal observed (at [34]), that the LUPA Act, s 59, includes a power in the Tribunal to refuse the application for a permit (s 59(4)(c)), the Tribunal erroneously determined (at [34]) that its adoption of the consent orders that were proposed by the parties after mediation amounted to a determination that refusal of the original application was inappropriate, ignoring the fact that the proposal that was approved by way of the consent orders that were made as the result of agreement between the parties, with the conditions imposed on it by the parties' agreement, differed substantially from the original proposal."
Launceston City Council
Tasmanian Water and Sewerage Corporation Pty Ltd
(1932) 47 CLR 1
(1990) 169 CLR 625
(2006) 228 CLR 566
(2008) 163 LGERA 222
(2011) 244 CLR 144
(1998) 194 CLR 355
(2009) 239 CLR 27
(2010) 241 CLR 510
(2004) 13 Tas R 134
(1990) 170 CLR 534
(1998) 193 CLR 72
(2006) 68 NSWLR 177
(1947) 74 CLR 492
(1990) 170 CLR 532
(2001) 115 FCR 229
(1986) 6 NSWLR 497
(1975) 13 SASR 4
(1992) 174 CLR 178
(2008) 17 Tas R 227
(1935) 55 CLR 499
(1953) 94 CLR 62
(2007) 152 LGERA 45
(2004) 13 Tas R 354
(1985) 4 NSWLR 139
(1966) 116 CLR 644
(1990) 170 CLR 321
(2010) 241 CLR 390