(3) Where a breach of this Act would not have been committed but for the failure to obtain a consent under Part 4, the Court, upon application being made by the defendant, may:
(a) adjourn the proceedings to enable a development application to be made under Part 4 to obtain that consent, and
(b) in its discretion, by interlocutory order, restrain the continuance of the commission of the breach while the proceedings are adjourned."
8 As stated in Sahade v The Owners - Strata Plan No. 62022 [2006] NSWLEC 770 at [10] per Jagot J:
"In my view, s 124(3) of the Environmental Planning and Assessment Act 1979 is an important provision disclosing part of the legislative scheme that underlies the statute. That is, there is a clear intention disclosed by s 124(3) that, where the relevant breach of this Act is the carrying out of development without development consent, in circumstances where development consent can be obtained for the development, there should be an opportunity for prospective respondents to proceedings or actual respondents to proceedings to make application to adjourn proceedings to enable a development application to be made and determined under Pt 4. I consider that s 124(3) has an important role to play in achieving the objects of the Act, as set out in s 5, because it is through a process of assessment and determination of a development application that all relevant matters under s 79C of the Act can be weighed, assessed and determined."