[2017] NSWSC 779
Supreme Court of NSW
2017-05-10
Beech-Jones J
Original judgment source is linked above.
Background
The Supply Contract
The Loan Contract
The Proceedings Below
Ground 7 - Credit Finding
Grounds 5 and 6: Probation Period
Grounds 1, 2 and 3: Clause 11 of the Supply Contract
Contractual Penalties
The Presiding Magistrate's Reasons for Upholding Clause 11.3 of the Supply Contract
Clause 11.3 of the Supply Contract
Ground 4: Clause 12 of the Loan Contract
Disposition and Costs
Amendments 09 February 2018 - Reference to "clause 11.3" in [108] amended to read "clause 12" DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 09 February 2018
Café Du Liban Pty Ltd
Bespoke Garage Pty Ltd
The Australian Gas Light Co v The Valuer General (1940) 40 SR (NSW) 126 The Commonwealth of Australia v Amann Aviation Pty Ltd [1991] HCA 54; 174 CLR 64 Category: Principal judgment Parties: Café Du Liban Pty Ltd (First Plaintiff) Dorothy Krahe (Second Plaintiff) Bespoke Garage Pty Ltd (Defendant) Representation: Counsel: A Moutasallem (Plaintiffs) J Gatland (Defendant)
Judgment
[1986] HCA 63
(1988) 14 NSWLR 438
(1987) 10 NSWLR 247
[1954] HCA 72
[2003] HCA 22