[2022] QSC 62
General information, not legal advice.
Supreme Court of Queensland
2022-04-22
Williams J
Original judgment source is linked above.
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - COSTS - OFFERS OF COMPROMISE, PAYMENTS INTO COURT AND SETTLEMENTS - where defendant made formal offer to settle in accordance with Chapter 9, Part 5 of the Uniform Civil Procedure Rules - whether the plaintiff's offer meets the essential requirements for a valid offer under Chapter 9 Part 5 of the Uniform Civil Procedure Rules - whether the offer is a "complying offer" - where the offer was made to settle "all claims" by the Plaintiff and the Defendant - where the offer did not distinguish between the claim and counterclaim - where the offer required the parties to enter into a mutually acceptable deed of settlement and release reflecting the terms of the offer - where the offer did not specify a rate to calculate the interest component - where the offer specified a methodology to calculate the interest component
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - COSTS - OFFERS OF COMPROMISE, PAYMENTS INTO COURT AND SETTLEMENTS - where defendant made formal offer to settle in accordance with Chapter 9, Part 5 of the Uniform Civil Procedure Rules - where "all in" offer amount in respect of claim and counterclaim - where offer did not distinguish between the claim and counterclaim - where single judgment amount - whether offer more favourable to plaintiff than judgment - where an offer also made pursuant to the principles of Calderbank v Calderbank - whether the plaintiff acted unreasonably in not accepting the Calderbank offer - whether the defendant's costs should be paid on an indemnity basis - whether defendant showed another order for costs appropriate
TERRITORY COURTS - COSTS - OFFERS OF COMPROMISE, PAYMENTS INTO COURT AND SETTLEMENTS - INFORMAL OFFERS AND CALDERBANK LETTERS - UNREASONABLE REFUSAL OF OFFER - where defendant made an offer expressly stated to be made pursuant to the principles of Calderbank v Calderbank - where offer marked "without prejudice save as to costs" - whether offer more favourable to plaintiff than judgment - where the offer was an "all in" offer inclusive of costs and interest - where offer did not distinguish between the claim and counterclaim - where single judgment amount - where the offer foreshadowed an application for indemnity costs on the basis that the rejection of the offer was imprudent and/or unreasonable - whether the plaintiff acted unreasonably in not accepting the offer - whether the defendant's costs should be paid on an indemnity basis
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - COSTS - GENERAL RULE: COSTS FOLLOW EVENT - GENERAL PRINCIPLES AND EXERCISE OF DISCRETION - whether the general rule that costs should follow the event should apply - whether another order for costs is appropriate in the circumstances
Civil Proceedings Act 2011 (Qld), s 58
Court Procedures Rules 2006 (ACT), s 21
Uniform Civil Procedure Rules 1999 (Qld), r 5, r 184, r 352, r 353, r 353(1), r 354, r 355, r 357, r 358, r 360, r 360(1), r 361, r 361(1), r 361(2), r 365, r 680, r 681, r 684, r 687, r 698, r 702, r 703, schedule 3
Supreme Court of Queensland Practice Direction Number 7 of 2013
AJ Lucas Drillings Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd (No 2) [2010] VSCA 128
Alborn v Stephens [2010] QCA 58
Alves v Patel [2005] NSWSC 841
Amaca Pty Ltd (formerly James Hardie & Co Pty Ltd) v Hannell [2007] WASCA 158 (S)
Angelatos v Alternative Constructions Pty Ltd (unreported, Supreme Court of Victoria Full Court, #judge#, 30 November 1992)
AON Risk Services Australia Limited v Australian National University (2009) 239 CLR 175
Armstrong v Mitchell-Smith and Allianz Australia Insurance Limited (No 2) [2012] QSC 370
Australian Medica Innovations Pty Ltd v GO Medical industries Pty Ltd, Supreme Court of Western Australia (Wallwork J), 22 April 1996, BC9601613.
Avis v Mark Bain Constructions Pty Ltd (No 2) [2011] QSC 151
AVS Australian Venue Security Services Pty Ltd v Criminale (No 2) [2007] NSWCA 34
Badge Constructions Pty Ltd v Penbury Coast Pty Ltd [1999] SASC 6
Balnaves v Smith [2012] QSC 408
Barboza v Blundy & Ors [2021] QSC 82
Binaray Pty Ltd as Trustee for the Allen Family Trust v RAMS Financial Group Pty Limited [2019] QSC 280
BM Alliance Coal operations Pty Ltd v BGC Contracting Pty Ltd [2015] 1 Qd R 228; [2013] QCA 394
Brymount Pty Limited t/as Watson Toyota v Cummins (No 2) [2005] NSWCA 69
Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd [2021] QSC 224
Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd (No 2) [2021] QSC 301
Calderbank v Calderbank [1975] 3 All ER 333
Cameron v Nominal Defendant (2001) 1 Qd R 476; [2000] QCA 137
Campbell v Northern Territory of Australia (No 4) [2021] FCA 1413
Chambers v Brice [2014] QSC 52
Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd [2020] QSC 1
Comgroup Supplies Pty Ltd v Products for Industry Pty Ltd & Anor [2016] QCA 130
Dover Beach Pty Ltd v Geftine Pty Ltd [2008] VSCA 248
Dr Martens Australia Pty Ltd v Figgins Holdings Pty Ltd (No 2) [2000] FCA 602
Elite Protective Personnel Pty Ltd v Salmon [2007] NSWCA 322
Evans Shire Council v Richardson (No 2) [2006] NSWCA 61
Evans v Braddock (No 2) [2015] NSWSC 518
Farmer v Hoban [1919] HCA 13; (1919) 26 CLR 183
Godin v Godin [2004] WASCA 186
Hadgelias Holdings and Waight v Seirlis [2014] QCA 325
HAP2 Pty Ltd v Bankier [2020] QCA 152
Hazeldene's Chicken Farm Pty Ltd v Victorian WorkCover Authority (No 2) (2005) 13 VR 435
J & D Rigging Pty Ltd v Agripower Australia Limited [2014] QCA 23
Jones v Bradley (No 2) [2003] NSWCA 258
Kane Constructions Pty Ltd v Sopov (No. 2) [2005] VSC 492
Keeley v Horton [2016] QCA 253
Lamac Developments Pty Ltd v Devaugh Pty Ltd [2002] WASCA 245; (2002) 27 WAR 287
Lamac Developments Pty Ltd v Devaugh Pty Ltd [2001] WASC 298
Leichhardt Municipal Council v Green [2004] NSWCA 341
LNC Harper Davidson Pty Ltd t/as Allansons (WA) v Keywest Building Co Pty Ltd (unreported, Supreme Court of Western Australia, Kennedy J, 13 July 1988)
Mackinnon v Petersen (unreported, Supreme Court of New South Wales, Cole J, 19 April 1989)
Masters v Cameron (1954) 91 CLR 3535
McBride v ASK Funding Ltd [2013] QCA 130
McKay v Armstrong & Anor [2020] QDC 146
Megerditchian v Khatachadourian [2020] NSWSC 112
Mickelberg & Others v The State of Western Australia & Others [2007] WASC 140 (S)
Mr Green Pty Ltd v Broadbeach Bowls & Community Club Inc (No 2) [2018] QDC 65
Porter v Lachlan Shire Council (No 2) [2006] NSWCA 252
Preti v Sahara Tours Pty Ltd [2008] NTCA 2
Rival Nominees Pty Ltd v Craig Davis Constructions Pty Ltd (unreported, Supreme Court of Victoria Full Court, Starke ACJ, Crockett and McGarvie JJ, 26 June 1981)
Rooney (Litigation Guardian of) v Gray 53 OR (3d) 685, 198 DLR (4th) 1; 2001 CanLII 24064
Seven Network Ltd and Anor v News Ltd and Ors [2007] FCA 1489; [2007] 244 ALR 374
SHA Premier Constructions Pty Ltd v Niclin Constructions Pty Ltd (No 2) [2020] QSC 323
Shaw v Jarldorn (1999) 76 SASR 28
Smallacombe v Lockyer Investment Co Pty Ltd (1993) 42 FCR 97
SMEC Testing Services Pty Ltd v Campbelltown City Council [2000] NSWCA 323
Southwell v Staite (No 2) [2019] ACTSC 83
Speets Investment Pty Ltd v Bencol Pty Ltd (No 2) [2021] QCA 39
Stewart v Atco Controls Pty Ltd [No 2] [2014] HCA 31; (2014) 252 CLR 331
Taske v Occupation & Medical Innovations Ltd [2007] QSC 147
Tremco Pty Ltd v Thomson [2018] QDC 109
White v Director of Housing [2003] VSC 124
Wiggins Island Coal Export Terminal Pty Ltd v Civil Mining & Construction Pty Ltd [2021] QCA 8
"THE JUDGMENT OF THE COURT IS THAT the Defendant pay to the Plaintiff the amount of $459,354.38, plus interest in the amount of $209,307.30.
1. By 4.00 pm on 2 December 2021, the Plaintiff is to file and serve its written outline of submissions on costs, together with any material upon which it wishes to rely.
2. By 4.00 pm on 16 December 2021, the defendant is to file and serve its written outline of submissions on costs, together with any material upon which it wishes to rely.
3. By 4.00 pm on 23 December 2021, the Plaintiff is to file and serve its written outline of submissions on costs in reply, together with any material upon which it wishes to rely.
4. The matter be listed for oral hearing in respect of costs on a date to be fixed."
(a) A formal offer made under r 353, Chapter 9, Part 5 of the UCPR on 21 June 2018 to settle all claims in the proceeding by payment of $1,850,000, plus interest pursuant to the Civil Proceedings Act 2011 (Qld) (Civil Proceedings Act) calculated from 11 August 2016 and payment of costs on a standard basis to be agreed or assessed (defendant's UCPR offer).
(b) A Calderbank offer made on 21 June 2018 to pay the sum of $2,250,000 (inclusive of any interest and costs) to settle the entirety of the proceeding (defendant's Calderbank offer).
(a) The plaintiff pay the defendant's costs on the indemnity basis from the date of the Calderbank offer;
(b) Alternatively:
(i) the plaintiff pay the defendant's costs in respect of the plaintiff's claim on the standard basis from the date of the formal offer;
(ii) the plaintiff pay the defendant's costs in respect of the counterclaim on the indemnity basis from the date of the formal offer.
(c) further in the alternative, the plaintiff pay the defendant's costs on the standard basis from the date of the offers.
(a) The plaintiff should pay a "fair portion" of the defendant's costs, suggested at 50 per cent.
(b) Alternatively, there should be no order as to costs.
(a) an offer made by the plaintiff under the UCPR on 14 June 2018, by an email attaching a letter sent from Clayton Utz, the solicitors for the plaintiff to Jones Day, the then solicitors of the defendant (plaintiff's UCPR offer).
(b) An email from Ms Leeks of Jones Day to Mr Ursino of the defendant dated 15 June 2018 stating the amount that Ms Walton of Clayton Utz had informed Ms Leeks of Jones Day "[the plaintiff is] prepared to agree costs at" (June Costs Figure).
(a) As part of the course of "without prejudice save as to costs" correspondence between the parties. The plaintiff's UCPR offer was made a week prior to the defendant's UCPR offer and the defendant's Calderbank offer.
(b) As a business record of the defendant recording the statement of the costs amount that the plaintiff was "prepared to agree".
(a) In May and June 2018, Mr Brackin was the partner at Clayton Utz in charge of the file in respect of this proceeding.[4]
(b) He was aware of the UCPR offer made by the plaintiff as contained in the letter dated 14 June 2018.[5]
(c) Ms Walton was a solicitor who acted under Mr Brackin's supervision at the time.[6]
(d) Mr Brackin was aware that Ms Walton sought instructions from the plaintiff.[7]
(e) The total actual costs incurred by the plaintiff at the time were not ascertained from the Clayton Utz billing system.[8]
(f) The $550,000 June Costs Figure was not based on Clayton Utz's actual billed costs, but was a commercial figure.[9]
(g) Mr Brackin did not believe that the $550,000 would have been approximately 60 per cent of the actual costs incurred at that time.[10]
(h) Mr Brackin could not say whether the plaintiff's costs of the proceeding at that time (approximately one year into the litigation) were in excess of $1 million.[11]
"A party which has not been entirely successful is not inevitably or even, perhaps, normally deprived of some of its costs." (footnotes omitted)
"... In litigation involving the construction industry, it is common for there to be a sum claimed which is comprised of a multitude of smaller sums. Each constituent ingredient normally requires some separate consideration at the hearing to a limited extent. Frequently, reasons of a judge or arbitrator isolate a separate finding in respect of the constituent claims. However, in truth, the matter in dispute between a proprietor and a contractor is the ultimate sum due from one to the other. Particularly is that so at the conclusion of a construction contract.
In my view, as a general rule, it is wrong in concept to regard litigation in the construction industry in which a sum claimed compromises a multitude of claims requiring resolution, as being a series of separate and distinct claims each of which should attract separate consideration in relation to costs. Normally the general rule will apply. Of course, there may be cases in which a particular item, issue or aspect of a litigation is so dominant or separable that, in the exercise of a judicial discretion, it will be appropriate to award costs to a party successful on that issue although unsuccessful overall, or to decline to award that the successful party overall the costs of that issue. However, in the usual case where the parties are concerned with the amount of money payable by the owner to the builder, or vice versa, and resolution of that issue involves the determination of many separate issues, claims or aspects of liability, the normal approach should be to regard the party who obtains a verdict as being successful in the litigation and entitled to its costs. The real dispute between parties in such circumstances is not the entitlement in relation to each of a multitude of claims, but the overall entitlement or obligation of one party from or to the other."
"The power to adjust an order for costs by reference to particular issues upon which the generally successful party has failed, is properly exercised only where there are discrete and severable issues upon which the generally successful party has failed, and which have added to the cost of the proceedings in a significant and readily discernible way."
(a) The numerous issues and evidence in this case are not easily disentangled.
(b) Several witnesses gave evidence relevant to both the claim and counterclaim.
(c) Whilst the Mechanical Variation claim constituted a significant part of the plaintiff's monetary claim, it did not "ultimately consume a disproportionate amount of trial time and resources".
(d) The plaintiff brought 22 claims of which the Mechanical Variation was one.
(e) The defendant brought 23 individual counterclaims.
(f) The majority of these claims were addressed by witnesses, including cross-examination, and were addressed in written and oral submissions.
"2. The Plaintiff and Defendant will enter into a mutually acceptable deed of settlement and release reflecting the terms in this Offer to Settle."
(a) It was not unreasonable for the plaintiff to reject the offer at the time it was made as:
(i) significant changes were made to the defendant's counterclaim after the offer was made;
(ii) the defendant had not quantified its counterclaim but sought only rectification of alleged defects or unquantified damages for failure to rectify;
(iii) the reasons the defendant contended that the Mechanical Variation was not a variation were different at the time of the offer compared to the reasons relied upon by the defendant at trial;
(iv) it was reasonable for the plaintiff to seek to have the Court determine its entitlement in respect of the Mechanical Variation.
(b) The offer did not distinguish between amounts in respect of the claim or in respect of the counterclaim.
(c) The offer was said to be inclusive of costs and interest.
(a) identifies in the letter that it is a Calderbank offer.
(b) sets out the orders that the defendant would seek should the matter proceed to judgment.
(c) states that the defendant would be relying on the letter to seek indemnity costs on the ground that the failure to accept the offer was imprudent and/or unreasonable.
(d) indicates a time for acceptance, consistent with the applicable statutory regime for making settlement offers. The offer was open for 14 days.
(e) states the reasons why the offer should be accepted, including the highlighted weaknesses of the plaintiff's case.
(a) The plaintiff's claim was quantified at $5,257,165.22.[25]
(b) Of that amount, $4,060,284.03 comprised the Mechanical Variation claim including GST and including delayed damages of $2,473,250.03 plus the sum of $1,587,032 for its repayment of liquidated damages claim.[26]
(c) The balance amount was $1,196,881.19.[27]
(d) The defendant's counterclaim at the time was principally a claim for specific performance requiring rectification of the defective work or damages in lieu.
Agreed position - pleaded amounts at time of offer and trial and amounts reflected in judgment amount
(a) setting out the amounts claimed at the time of the defendant's UCPR offer and the defendant's Calderbank offer (21 June 2018); and
(b) setting out:
(i) the amounts claimed at the trial; and
(ii) the amounts determined in the reasons for judgment, and reflected in the final judgment amount.
(a) how the security amount is to be incorporated into the table; and
(b) the total figures for the claim and counterclaim (in light of the disagreement about the treatment of the security amount).
(a) Chapter 9 Part 5 Offer to Settle: r 353 (if offer available), r 354 (Time for making offer), r 355 (Withdrawal or end of offer), r 357 (Disclosure of offer), r 358 (Acceptance of offer), r 360 (Costs if offer by plaintiff), r 361 (Costs if offer by defendant) and r 365 (Failure to comply with offer).
(b) Chapter 17A Part 2 Costs of Proceeding: r 680 (Entitlement to recover costs), r 681 (General rule about costs), r 684 (Costs of question or part of a proceeding), r 687 (Assessed costs to be paid unless court orders otherwise), r 698 (Reserved costs), r 702 (Standard basis of assessment) and r 703 (Indemnity basis of assessment).
"(1) Costs of a proceeding, including an application in a proceeding, are in the discretion of the court but follow the event, unless the court orders otherwise.
(2) Subrule (1) applies unless these rules provide otherwise."
(a) the plaintiff makes an offer that is not accepted by the defendant and the plaintiff obtains an order no less favourable than the offer; and
(b) the court is satisfied that the plaintiff was at all material times willing and able to carry out what was proposed in the offer;
the court must order the defendant to pay the plaintiff's costs calculated on the indemnity basis unless the defendant shows another order for costs is appropriate in the circumstances.
(a) the defendant makes an offer that is not accepted by the plaintiff and the plaintiff does not obtain an order that is more favourable to the plaintiff than the offer; and
(b) the court is satisfied that the defendant was at all material times willing and able to carry out what was proposed in the offer.
(2) Unless a party shows another order for costs is appropriate in the circumstances, the court must -
(a) order the defendant to pay the plaintiff's costs, calculated on the standard basis, up to and including the day of service of the offer; and
(b) order the plaintiff to pay the defendant's costs, calculated on the standard basis, after the day of service of the offer.
Does the defendant's UCPR offer enliven r 360 and/or r 361 UCPR?
"(1) A party to a proceeding may serve on another party to the proceeding an offer to settle 1 or more of the claims in the proceeding on the conditions specified in the offer.
(3) An offer must be in writing and must contain a statement that it is made under this part."
(b) in which the court has made an order under rule 14 ordering the proceeding to continue as it started by claim; or
(c) started by originating application if an order or direction has been made for pleadings, or other documents defining the issues, to be filed and served."
"[27] A counterclaim does not meet the definition of 'proceeding' in r 352 because .... the reference in that rule to 'a proceeding' is to the proceeding as a whole as commenced by the plaintiff's claim or application. Correspondingly, r 353 does not contemplate a counterclaim or third party notice as constituting proceedings of themselves for the purposes of that rule. In my view, a counterclaim or third party proceeding meets the Supreme Court of Queensland Act definition of proceeding as extending to "an incidental proceeding in the course of ... a proceeding". It is an incident of the principal proceeding as commenced by the plaintiff's claim, in that it flows from it. But the 'proceeding' in the expression 'claims in the proceeding' is the principal proceeding as commenced by the plaintiff's claim (or application)."
1 A claim is a document under chapter 2, part 3 starting a proceeding.
2 If the court orders a proceeding started by application to continue as a claim, the application is also a claim for these rules."
"[28] What are the relevant "claims" in that proceeding? Neither party now contends that the definition of 'claim' in the Dictionary ... is applicable to r 353. There are a number of instances in the [UCPR] in which the context indicates that the Dictionary definition of "claim" is not applicable. So, for example, in the rules concerning pleadings (such as r 150(4) and r 154), the term is plainly used in reference to a cause of action or claim for relief. Rule 353 is also an instance in which the context indicates that the Dictionary definition is inapposite ... on my construction, the Dictionary definition of "claim" refers solely to the plaintiff's claim, and it is improbable that the capacity to make an offer would be correspondingly limited to that claim.
[29] The more obvious reading of the expression "claims in the proceeding" in r 353 is ... that it refers to causes of action or claims for relief, rather than a plaintiff's claim, a counterclaim or claim against a third party."[30]
(b) Interest on the sum of $1,850,000.00 from 11 August 2016 pursuant to the Civil Proceedings Act 2011 (Qld);
(c) The Plaintiff's costs on the standard basis, to be agreed or assessed.
1 The Plaintiff's acceptance of this offer to settle must be communicated in writing to the solicitors for the Defendant.
2 The Plaintiff and the Defendant will enter into a mutually acceptable deed of settlement and release reflecting the terms in this Offer to Settle.
3 This Offer to Settle will remain open for acceptance for a period of 14 days after the date of service of this offer upon the Plaintiff's solicitors."
(a) is the way interest is to be calculated and the condition requiring the parties to enter into a "mutually acceptable deed" sufficiently certain and capable of acceptance?
(b) does the way interest is to be calculated and the condition requiring the parties to enter into a "mutually acceptable deed" result in the comparison exercise required by r 360 and r 361 UCPR being ineffective?
"[10] Part 5 specifies the requirement of a compliant offer to settle.
[12] An offer capable of triggering adverse costs consequences for the offeree[33] must, as r 353(1) states, offer to settle "one or more of the claims in the proceeding...". But r 353(1) does not, in terms at any rate, preclude the inclusion of a condition for the resolution of other contests between the parties.
[13] More generally, the broadly expressed provision in r 353(1) that the offer may be "on the conditions specified in it" - without restriction - is at odds with the notion that an offer which extends beyond the claims in the proceeding is not an "offer to settle". And no such limitation on the range of compliant proposals is suggested by the content of any other rule.
[14] In short, nothing in the language of the UCPR indicates that an offer is non-compliant if it includes a term that extends "beyond the claims in the proceeding".
[17] Of course, conditions of an offer to settle "that extended beyond the claims in the proceeding" could complicate things. Uncertainty might be generated about the meaning or effect of the offer. Problematic complexities might be avoided were the permissible conditions constrained as Taske envisages.[34] But that is not a sufficient reason to imply into Part 5 the Taske restrictions.
[19] To gain the benefit of the Part 5 regime, the offer must, in a phrase, better the judgment...
[20] To be effective for that purpose, the offer must permit fairly ready comparison between the nature and extent of the advantages (and any disadvantages) arising from the judgment with the situation that would have been obtained had the offer been accepted...
[21] So an offer to settle should be clear in its terms.[36] And its effect should be capable of prompt, comparatively inexpensive, assessment - by the recipient, and, where a judicial evaluation needs to be made of the relative benefits and burdens of offer and judgment, by the court.
[22] Difficulty in comparing offer and judgment may well jeopardize the chances of showing that the former was more advantageous to the offeree than the latter.[37] That reality will encourage clarity in the description of the benefits the offeree will derive by acceptance of the offer. For the Part 5 scheme to work, there is no need to interpret rules that prescribe just a handful of formal requirements as impliedly invalidating an offer that incorporates proposals that extend "beyond the claims in the proceeding"."
"It is trite to observe that the terms of the offer must be clear, precise, certain and capable of acceptance so that if a party fails to accept the offer, the Court is in a position to give effect to the Rules relating to a failure to accept .... In my opinion, there is no way that a court could evaluate in money terms, the terms imposed by the defendant in the present offer of compromise, namely, release and confidentiality. Because it is not possible for the Rules to operate in relation to the offer of compromise ... the offer of compromise is not one within the provisions of Order 26 of the Rules.
Of course, that does not mean that the offer could not be accepted in accordance with its terms. Clearly, it could have been accepted. It follows that the Rules do not apply to the offer".[39]
"It is unclear whether Byrne SJA's reference in Balnaves v Smith to the need for clarity in the terms of the offer was a precondition for an offer being a complying offer, or whether the uncertainty arising from such a lack of clarity is a matter that is relevant in deciding whether a party relying on the offer has met its burden of proof.[45] However, in the present case, I do not need to decide this question because to the extent that the offer contemplates a costs assessment regime beyond that stated in terms of the offer, it would be a non-complying offer.[46] It is analogous to a provision for a deed of release being included in an offer the terms of which are not disclosed.[47] Rule 353(1) provides for the offer to settle the proceeding 'on the conditions specified in the offer" (emphasis added)."
"[37] My view is that Byrne SJA was not suggesting that certainty is a strict requirement of Part 5 of Chapter 9, but that some degree of certainty is necessary to allow ready comparison between the offer and the order obtained for the purposes of rr 360 and 361. This accords with a plain reading of the rules. In some cases, the uncertainty will be immaterial because it is plain that the offer, despite some ambiguity, is less (r 360) or more (r 361) favourable than the order obtained. Conversely, the uncertainty in an offer may prevent a party from engaging rr 360 and/or r 361. It may also be relevant to consider the uncertainty of an offer in deciding whether another costs order is appropriate. Finally, as in Binaray, the uncertainty in an offer may stem from the fact that it is on unspecified terms. Such an offer is not rules-compliant because it fails to satisfy r 353(1), and not because of uncertainty per se."
"The terms of the offer were so uncertain that the plaintiff would not have known what it was committing to, in terms of the separate regime contemplated by agreeing to a third party costs assessor assessing costs on an unspecified or yet to be agreed basis. In those circumstances, the plaintiff would not have been able to assess the overall value of the offer and the benefits thereunder.
In my view, for that reason, the offer is not one which is clear in its terms and capable of prompt, comparatively inexpensive assessment by the recipient."[53]
"Acceptance of this offer is in full and final satisfaction of all the claims and rights which the plaintiff has against the first or second defendant in connection with the damage which the plaintiff alleges or could have alleged in this action". (This was referred to as the condition).
(a) Interest: the offer identified a methodology to calculate the interest component. While it did not specify a rate, the rate was arguably able to be ascertained. For the purposes of r 353 UCPR the interest component was sufficiently certain for the offer to be a "rule-compliant" offer.
(b) Deed of Settlement: the scope of the deed is constrained to that "reflecting terms in [the] Offer to Settle". The inclusion of a non-monetary term does not make the offer "non-compliant". It is contended that the restricted scope of what was to be in the deed avoids the problems associated with other conditions which are "on terms to be agreed". While this issue needs to be considered further at the comparison stage, I consider the better view is that on the particular wording of the condition in this case the offer is "rule-compliant".
"[40] ... In this case, there was unquestionably more than one relevant order. His Honour gave two judgments, one on the claim, the other on the counterclaim. There was no warrant for treating them as though they were a single judgment, or as though there were only one decision or determination, or as if they could somehow be regarded as a single order. That conclusion is reinforced by consideration of what rr 360 and 361 respectively require by way of comparison.
[41] The focus, for each rule, is on the order obtained by the plaintiff. In the present case, judgments were given in favour of two different plaintiffs: the judgment relevant for r 360 purposes was that given to Wiggins on its counterclaim and, for r 361, for Civil Mining on its claim. What had to be considered for the purposes of the two rules was different.... the necessary comparisons for the purposes of those rules individually could not be made."
"[43] The trial judge was right to conclude that the offer was not one to which rr 360 and 361 could be applied and that, in consequence, it was unnecessary to consider whether the offer was sufficiently certain for the purposes of those rules".
"[42] I depart, with respect, from the trial judge's reasoning to this extent: I am inclined to think that a defendant can properly serve an offer under r 353 to settle the entire proceeding without quantifying claim and counterclaim separately, and that if judgment is given for a net amount under r 184, nothing prevents assessment under r 361(1) of the offer against the order. The judgment in that event is given in favour of a party to the proceedings as a whole, plaintiff or defendant, rather than in their separate capacities as plaintiff on the claim and defendant on the counterclaim and vice versa. However, my view in that regard is not critical to the issues to be decided in this case."
"[84] I agree with the reasons for judgment of Holmes CJ save for two minor caveats ... Nor do I decide whether an offer can be properly served by a defendant under r 353 to settle an entire proceeding without quantifying the claim and counterclaim separately, as discussed by her Honour in [42] of her Honour's reasons."
(a) a formal offer made under Part 5 of the UCPR does not need to identify the separate components in respect of the claims and counterclaims included in the offer to be a valid offer under r 353 UCPR; and
(b) it is not necessary to "trigger" rr 360 or 361 to identify the separate components in respect of the claims and counterclaims included in the offer.
(a) The defendant makes an offer that is not accepted by the plaintiff and the plaintiff does not obtain an order that is more favourable to the plaintiff than the offer...".
"The primary purpose of rules such as UCPR 361 and the similar rules which it replaced[64] is to encourage litigants through favourable costs orders to make realistic offers in order to achieve a just compromise and to avoid where possible the expense time and effort of a trial. The interpretation of UCPR 361 in accordance with its ordinary and natural meaning is not inconsistent with this purpose or with the purpose of the rules set out in UCPR 5(1), namely "to facilitate the just and expeditious resolution of the real issues in civil proceedings at a minimum of expense"."[65]
"(1) The purpose of these rules is to facilitate the just and expeditious resolution of the real issues in civil proceedings at a minimum of expense.
(2) Accordingly, these rules are to be applied by the courts with the objective of avoiding undue delay, expense and technicality and facilitating the purpose of these rules."
"Accordingly, these rules are to be applied by the courts in civil proceedings with the objective of achieving-
(a) The just resolution of the real issues in the proceedings; and
(b) The timely disposal of the proceedings, and all other proceedings in the court, at a cost affordable by the respective parties."
"The overriding purpose of r 21, to facilitate the just resolution of the real issues in civil proceedings with minimum delay and expense, is stated in the rules of other courts in Australia, although those purposes and the obligations cast upon the court and the parties may be stated in somewhat different terms.
The purposes stated in r 21 reflect principles of case management by the courts. Such management is now an accepted aspect of the system of civil justice administered by courts in Australia. It was recognised some time ago, by courts here and elsewhere in the common law world, that a different approach was required to tackle the problems of delay and cost in the litigation process.
Rule 21(2)(b) indicates that the rules concerning civil litigation no longer are to be considered as directed only to the resolution of the dispute between the parties to a proceeding. The achievement of just but timely and cost-effective resolution of a dispute has an effect upon the court and upon other litigants ...".[68] (footnotes omitted)
"The purposes stated in r 21 cannot be ignored. The Court Procedures Rules make plain that the Rules are to be applied having regard to the stated objectives of the timely disposal of the proceedings at an affordable cost. There can be no doubt about the importance of those matters in litigation in the courts of the Australian Capital Territory.
Of course, a just resolution of proceedings remains the paramount purpose of r 21; but what is a "just resolution" is to be understood in light of the purposes and objectives stated. Speed and efficiency, in the sense of minimum delay and expense, are seen as essential to a just resolution of proceedings ...".[69]
(a) The defendant made an offer to the plaintiff that was not accepted.
(b) The plaintiff does not obtain an order that is more favourable to the plaintiff than the offer.
(c) The defendant establishes that the defendant was at all material times willing and able to carry out the offer.
(a) As discussed above, the defendant made a complying offer by way of the defendant's UCPR offer dated 21 June 2018.
(b) The defendant's UCPR offer was not accepted.
(c) The affidavit of Mr Ursino at [11] and [12] addresses the defendant's capacity to carry out the offer.
(a) The defendant to pay to the plaintiff $459,354.38; and
(b) The defendant to pay to the plaintiff interest in the amount of $209,307.30.
(a) The defendant to pay the plaintiff $1,850,000.00;
(b) The defendant to pay to the plaintiff interest from 11 August pursuant to the Civil Proceedings Act. This amount has been calculated by the defendant using the Queensland Court's online interest calculator as $191,259.77.[71]
(c) The parties enter into a "mutually acceptable deed of settlement and release reflecting the terms in this Offer to Settle".
(a) The only referable section is s 58 Civil Proceedings Act which confers power on the Court to award interest at a rate that the "Court considers appropriate".
(b) The Court has published Practice Direction No 7 of 2013, which expressly ties the interest rate under s 58 Civil Proceedings Act to the default judgment rate.
(c) The consequence is that the rate of interest which the Court considers to be appropriate is that calculated under the Practice Direction.
(d) The "conventional practice" is for interest under s 58 of the Civil Proceedings Act to be calculated according to Practice Direction No 7 of 2013 when awarding statutory interest pursuant to the Civil Proceedings Act.[72]
"It is common, if not usual, for Queensland courts to award interest under s 58 at the default rate under the practice direction."
"As to the rate to be applied for pre-judgement interest, no evidence was advanced in the court below, or here, regarding the prevailing commercial rates of interest over the period in question. In the absence of such evidence, the primary judge allowed interest on the sum awarded in favour of the second appellant ... in accordance with the rates prescribed for default judgments. That was the correct approach.
Although a court is not obliged to apply the rates prescribed for default judgments, since 19 April 2013 those rates have been the product of an agreement reached by representatives of all Australian jurisdictions to establish nationally uniform rates of interest applying to default judgments (and, in Queensland, money order debts pursuant to s 59 of the Civil Proceedings Act). For default judgments, the prescribed rate is four per cent above the cash rate last published by the Reserve Bank of Australia and that rate is adjusted bi-annually. In the absence of contrary evidence, the prescribed rates are generally accepted as satisfying the need for economic loss to be compensated by an award of interest on the principal debt at ordinary commercial rates. They should therefore be applied to the damages awarded in the first appellants' favour as varied by the Court."[75] (emphasis added by the defendant) (citations omitted)
"The usual practice in current times has been, as Burns J explained in Keeley, to apply the rate specified by practice direction for the Registrar's purposes."[77]
(a) The authorities support the position that an offer is not invalidated if the terms go beyond the claims in the proceeding or beyond what could be ordered by the Court.
(b) Further, an offer including terms that go beyond the claims in the proceeding or beyond what could be ordered by the Court can be compared to the judgment.
(c) The relevant question is whether the effect of the judgment is overall more or less favourable than the offer.
"The offer must permit fairly ready comparison between the nature and extent of the advantages (and any disadvantages) arising from the judgment with the situation that would have been obtained had the offer been accepted."[79]
(a) In Balnaves v Smith[80] Byrne SJA undertook the comparison exercise in respect of an offer containing a consent discontinuance term. His Honour concluded that there was no disadvantage in such a term as the prospect that the defendants might have pursued a claim for costs was fanciful. Consequently, the judgment was not more favourable than the offer.
(b) In Tremco Pty Ltd v Thomson[81] Porter QC DCJ considered an offer under the UCPR containing a condition that "[t]he parties execute an appropriately worded Settlement Deed reflecting these terms within 7 days of acceptance" of the offer.
(i) His Honour concluded that the inclusion of non-monetary terms did not make the offer non-compliant with Part 5 UCPR but noted that such terms may make it difficult to determine whether the condition in r 360 was met (as was relevant in respect of an offer from a plaintiff).
(ii) In undertaking the comparison exercise, his Honour concluded:
"[13] The settlement offer by the plaintiff was for $250,000 to be paid in full settlement of the claims in the proceedings including costs, interest and any GST. Judgment was substantially more favourable than that offer. None of the non-monetary terms are capable of impacting on that conclusion."
(c) In McKay v Armstrong & Anor[82] Morzone QC DCJ considered an offer by the defendant that included a monetary sum and a condition requiring the execution of a release and discharge. The Deed of release/Discharge was attached to the offer and included other extraneous terms and binding acknowledgements as well as the release and discharge.
(i) His Honour concluded that the terms including "matters beyond the purview of a court's jurisdiction and adjudication of the proceeding, in particular the condition of requiring execution of the release and its terms" did not vitiate the offer or render it "non-compliant" with the rules and the offer was "caught" by r 361.[83]
(ii) Further, his Honour observed:
"[15] In my view both quantitative and qualitative matters are relevant to my consideration of whether the overall effect of the judgment was more favourable, or not, to the plaintiff than the offer pursuant to r 361(1)."
(iii) In undertaking the comparison exercise, his Honour stated:
"[17] Of course, hybrid offers are not merely unfavourable because they contain extraneous matters beyond the relief available in a court. Some of the extraneous matters included in an offer are consistent with the available relief flowing from a court adjudication. For example, in the wake of a judgment parties are barred from bringing future like actions (with rare exceptions), rights are merged in the judgment, and liabilities discharged by the operation of the judgment, executory obligations will include statutory refunds and setting time for payment after clearances.
[18] Although the offer exceeded the judgment by over $3000, it contains terms extending beyond the claims in the proceeding and conditional on the agreement of a deed, which in turn imposed on the plaintiff conditions of strict confidentiality and a contradictory acknowledgement that the defendant does "not admit injury, loss or damage". Consequently, the terms of the offer sought to burden the plaintiff with a lifelong silence without any acknowledgement of liability for her injury, loss or damage. These extraneous matters did not, and could not, form part of any judgment in the proceeding. The court did not, and could not, compel the plaintiff to execute a form of release and discharge in those terms. As for the acknowledgement that the second defendant does "not admit injury, loss and damage", that contradicts the defendants' pleadings and the conduct of the case for the sole purpose of adjudicating causation and consequential loss and damage. Further, the judgment did not restrain the plaintiff from publication or force confidentiality about the nature and effect of the outcome."
(iv) His Honour found that the extraneous aspects of the offer were "incongruent with the fundamental attributes of ... open justice". This was particularly so given the case was a personal injuries compensation case with no dispute about liability.[84] In comparison, the "overall effect of the judgment" was:
"... to acknowledge the nature and extent of the plaintiff's loss and damage, to attribute liability for her loss caused by the defendant, to quantify compensation, and to acknowledge the defendants' responsibility of the plaintiff's past and future impairment and incapacity."[85]
(v) In all of the circumstances of that case, his Honour found that the plaintiff did obtain a judgment that was overall more favourable to the plaintiff than the offer with the extraneous terms.[86]
"(2) Unless a party shows another order for costs is appropriate in the circumstances, the court must -
(a) order the defendant to pay the plaintiff's costs, calculated on the standard basis, up to and including the day of service of the offer; and
(b) order the plaintiff to pay the defendant's costs, calculated on the standard basis, after the day of service of the offer."
(a) up to and including 21 June 2018:
(i) the plaintiff to pay 50 per cent of the defendant's costs; or
(ii) there be no order as to costs; and
(b) after 21 June 2018, the plaintiff pay the defendant's costs on the indemnity basis.
Does the defendant's Calderbank offer establish that another order for costs is appropriate in the circumstances?
(a) was marked "without prejudice save as to costs".
(b) was expressly stated to be made pursuant to the principles of Calderbank v Calderbank.[93]
(c) Was stated to be open for 14 days from the date of the letter. The defendant's Calderbank offer was contained in a letter that was sent by email on 21 June 2018 at 9.31am.
(d) Contained an offer to settle as follows:
"On the basis of the matters set out in Part 2 below, our client offers to settle your client's claim and our client's counterclaim on a purely commercial basis by paying to your client the total sum of $2,250,000 (inclusive of fees and interest) within 14 days after your client's acceptance of this offer".
(e) The letter sets out the basis identified by the defendant to establish that the offer is a genuine attempt to settle the issues in dispute "at least for the reasons discussed ... in this Part 2".
(f) The offer:
(i) Sets out reasons as to why the plaintiff's claim would be unsuccessful in relation to the Mechanical Variation, Delay Costs and Repayment of Liquidated Damages claims.
(ii) Refers to the reasons pleaded in the defence[94] as to:
- (A) why the Joinery Delay and Bathroom Design Variation claims were "doomed to fail", including that the plaintiff failed to comply with the express notice provisions in the Contract.
- (B) why the Disputed Variation claims in Schedule 3 and 4 of the statement of claim would fail, including that the Superintendent had correctly assessed each variation in accordance with the pricing mechanism in the Contract.
- (C) why the provisional Sum claims in Schedule 5 of the statement of claim would fail, including that the Superintendent had correctly assessed each provisional sum in accordance with the adjusted mechanism in the Contract.
- (D) why the Variation Pricing Claims in Schedule 6 of the statement of claim would fail, including that the Superintendent had correctly assessed each provisional sum in accordance with the pricing mechanism in the Contract and that each variation had been correctly individually priced.
- (E) why the Wrongful Set-Offs and Deductions claims in Schedule 7 of the statement of claim would fail, including that the Superintendent had correctly assessed each set-off and deduction in accordance with the Contract.
(iii) Refers to the reasons pleaded in the counterclaim as to why the plaintiff would be obliged to rectify all defective work under the Contract and would be 100% liable for the rectification costs.
(g) If the offer was not accepted, foreshadowed an application for indemnity costs on the basis that the rejection of the offer was imprudent and/or unreasonable.
(a) The plaintiff's claim was $5,257,165.22. Of that sum:
(i) $4,060,284.03 related to the Mechanical Variation Claim (including GST, Delay Damages and Repayment of Liquidated Damages):
(ii) $1,196,881.19 related to the balance of the claims.[95]
(b) The defendant's counterclaim was principally a claim for specific performance for the plaintiff to rectify the defective work or damages in lieu.
(a) The relevant question is whether it was reasonable for the plaintiff to reject the offer.
(b) This question is to be considered at the time the offer was made.
(a) who bears the onus; and
(b) the effect of the Calderbank offer being "inclusive of costs".
"The basis on which the respondents seek their costs on an indemnity basis is because they made an offer to the applicant pursuant to the principles in Calderbank v Calderbank[98] which was not accepted. The law with regard to costs when a Calderbank offer has been made was set out by the High Court in a joint judgment in Stewart v Atco Controls Pty Ltd [No 2][99] where the court held at [4]:
'This Court has a general discretion as to costs. The non-acceptance of a Calderbank offer is a factor, in some cases a strong factor, to be taken into account on an application for indemnity costs. The respondent submits that its rejection of the offer was not unreasonable. If that be the test, it would appear to require at the least that the respondent point to a reason for not accepting the offer beyond the usual prospects of being successful in litigation'." (emphasis added)
"It has been held that a Calderbank letter which is expressed to be 'inclusive of costs', is insufficiently precise to qualify as a Calderbank offer, for the reason that the offeree is placed in a position of not being able to determine the appropriate amount to attribute to the substantive claim and the costs incurred in advancing it ...".[105]
"In an ex tempore judgment in DSE (Holdings) Pty Ltd v InterTAN Inc [2004] FCA 2151; (2004) 51 ACSR 555 (at [12] - [13]), Allsop J referred to Smallacombe, Hanave Pty Ltd v LFOT Pty Ltd (formerly Jagar Pty Ltd) [1998] 1429 FCA (Federal Court of Australia, Moore J, 11 November 1998, unreported) and Dr Martens Australia Pty Ltd v Figgins Holdings Pty Ltd (No 2) [2000] FCA 602. He did not regard Smallacombe as having articulated "a definitive rule that in an application for costs, an offer that was an all inclusive sum could not, in any circumstances, be taken into account by a Court in considering whether thereafter indemnity costs should be awarded".
"I agree with Allsop J that Smallacombe does not lay down a 'definitive rule' that an 'all-in' Calderbank offer can never be considered on the question of indemnity costs. The Court cannot fetter the s 98 discretion by legal rules: Oshlack (at [35]). Smallacombe does, however, afford guidance as to the exercise of the s 98(1) discretion. It informs the question of the reasonableness of an offeree's refusal to accept an "all-in" offer. In my view it has a sound practical basis. While I accept each case should be considered on its facts, Smallacombe provides sound reasons to discourage offerors from drafting Calderbank letters on an "all-in" basis."
"[5] ... I do not agree that an offer which is inclusive of costs cannot ever be the basis upon which the court exercises its discretion to award indemnity costs. The award of indemnity costs involves the exercise of a discretion. The application of an overarching 'rule' or 'principle' that only offers exclusive of costs could ground a favourable exercise of the court's direction would operate as a fetter on that discretion and would introduce a rigidity to the making of so called Calderbank offers which has no basis in principle.
[6] There is, however, as discussed in the judgments of McColl JA and Basten JA, some disputation in the authorities as to whether an offer that is inclusive of costs may be the basis upon which an indemnity costs order can be made. Notwithstanding a number of first instance decisions that state that an offer inclusive of costs does not operate as a Calderbank offer, there are authorities of this Court that an offer of compromise which is inclusive of costs may form the basis upon which the court awards indemnity costs.
[7] As is apparent from the short remarks I have made, I consider that the proper approach to any such offer of compromise is to consider it according to its terms and determine whether, in all the circumstances, the court should exercise its discretion to award indemnity costs. Having said that, there may be difficulties in the path of a party who seeks indemnity costs when the application is based upon an offer inclusive of costs, as is examined and explained by Basten JA".
"[143] With respect, I would not accept that reasoning. If a party in receipt of an offer wishes to know how far the sum offered will go in meeting its costs up to that time, all it has to do is ask its lawyers. In an age where lawyers are required to provide advance estimates of their fees and in circumstances where commercial services are billed on a monthly basis, it is unrealistic to suggest that the recipient of an inclusive offer will be confused or otherwise unable to assess the financial risk of proceeding with litigation. In any event, the offeree is likely to be liable for legal fees exceeding the costs recoverable from the other party. Most litigants, in considering offers, will want to know from their own lawyers, how much they will receive in hand. Of course, if the offer is not left open for a reasonable time, that might itself make non-acceptance a reasonable course. However, an offeree which is genuinely seeking to assess it position, might be advised to seek more time, if it thinks that is reasonably required.
[144] The suggestion that a Calderbank letter which is expressed to be inclusive of costs is "insufficiently precise to qualify as a Calderbank offer" requires to be addressed in particular circumstances. A defendant who fears that even if successful it will be unable to recover costs awarded against the plaintiff, may wish to make an offer in full and final settlement, without further disputation over costs. It may wish to place pressure on the plaintiff to consider the offer favourably by reserving an entitlement to use the offer in relation to costs if the matter proceed to trial. There is no reason based on policy or principle which would preclude a defendant relying on such an offer only when it is said to be exclusive of costs. Such as inclusive offer will not cause the plaintiff embarrassment: its value will be that amount remaining to him or her after deducting costs already incurred, which the plaintiff's lawyer should be readily able to quantify. The disadvantage of an inclusive offer lies with the defendant if the matter proceeds to judgment. Where the judgment is equal to or above the inclusive figure, the defendant will have failed to better its own offer. However, if the judgment is below the offer there may be uncertainty because the offer included an unquantified element for costs incurred up to the time when it lapsed or was rejected. ..."
"[38] Making an offer inclusive of costs may sometimes have the result that it is difficult to demonstrate unreasonableness in rejecting it. This is particularly so where the offeror is the plaintiff. In such a case the defendant will have no direct knowledge of the costs which the plaintiff has actually incurred and will only be able to make the broadest estimate.
[39] But that is not so where the offer is made on an inclusive basis from the defendant to the plaintiff. The plaintiff knows, or can readily find out, what his or her costs are. Where it is sufficiently clear afterwards that, taking into account the costs the plaintiff had incurred at the date of the offer, the offer was more than favourable than the ultimate result, there is no objection in principle to concluding that refusal of the offer was unreasonable: see Elite Protective Personnel Pty Ltd v Salmon [2007] NSWCA 322 at [136] - [145], per Basten JA."
(a) The court is to consider whether the rejection of the offer was unreasonable by considering, among other relevant circumstances, the strengths and weaknesses of the relevant party's case "prospectively at the time the offer was made" (emphasis added); and
(b) A matter to be taken into account is that the relevant party ultimately failed in the proceedings.[109]
"[8] The relevant considerations were identified in J & D Rigging Pty Ltd v Agripower Australia Limited [2014] QCA 23 at [5] to [6] per Holmes JA and Applegarth and Boddice JJ, and in Hadgelias Holdings and Waight v Seirlis [2014] QCA 325 at [11] to [12] per Holmes JA with whom Gotterson and Morrison JJA agreed. In each case, the Queensland Court of Appeal followed the approach taken by the Victorian Court of Appeal in Hazeldene's Chicken Farm Pty Ltd v Victorian WorkCover Authority (No 2) (2005) 13 VR 435.
[9] The following propositions may be distilled from those appellate decisions.
[10] First, the usual rule is that where the Court orders the costs of one party to litigation to be paid by another party, the order is for assessment of those costs on the standard basis.[111]
[11] Second, the Court will depart from the usual rule where the circumstances of the case warrant that course.[112]
[12] Third, one feature which may justify a departure from the usual rule is the rejection of a Calderbank offer to compromise.[113] However, it is wrong to think that an offeree's rejection of a Calderbank offer gives rise to a presumption that the offeree should pay the offeror's costs on an indemnity basis if the offeree obtains a less favourable result than contained in the offer.[114] Rather, the correct approach is to consider whether the rejection of the Calderbank offer, in all the circumstances, justifies a departure from the usual rule.[115]
[13] Fourth, the balance between the competing policy considerations of, on the one hand, appropriately encouraging settlement and, on the other, not discouraging potential litigants from bringing their disputes to the courts, is found by applying a test of "reasonableness".[116] The policy rationale for requiring the offeree to indemnify the offeror for costs incurred after the offeree's unreasonable rejection of an offer is that, from the time of the unreasonable rejection, notionally the real cause and occasion of the litigation is the unreasonable attitude adopted by the offeree.[117]
[14] Fifth, deciding the critical question of whether the offeree's rejection of the offer is unreasonable in all the circumstances will always involve matters of judgment and impression.[118] However, the discretion as to costs must be exercised judicially and is subject to review in accordance with the principles set out in House v The King (1936) 55 CLR 499 at 505.[119] Without being exhaustive concerning the considerations which should be taken into account, a court should ordinarily have regard to at least the following matters:[120]
(a) the stage of the proceeding at which the offer was received;
(b) the time allowed to the offeree to consider the offer;
(d) the offeree's prospects of success, assessed as at the date of the offer;
(e) the clarity with which the terms of the offer were expressed; and
(f) whether the offer foreshadowed an application for indemnity costs in the event of the offeree rejecting it."
The stage of the proceedings at which the offer was received
(a) Significant changes were made to the defendant's counterclaim after the offer was made.
(b) At the time of the offer, the counterclaim was not quantified. The relief sought was rectification or alternatively unquantified damages for failure to rectify.
(c) The defendant's pleaded case in respect of why the Mechanical Variation was not a variation changed after the offer.
The time allowed to the offeree to consider the offer
(i) On 14 June 2018 the plaintiff made an offer pursuant to Part 5 of Chapter 9 of the UCPR as follows:
(A) Settle all claims made by the plaintiff, the defendant to pay to the plaintiff:
(I) $3,100,000; and
(II) The plaintiff's costs assessed on the standard basis.
(B) Settle all counterclaims made by the defendant, the plaintiff will provide an irrevocable undertaking to rectify all defects listed in Schedule 1 in accordance with the terms of the Contract.[124] Schedule 1 listed Defect 3 in Annexure 4 and Defects 2, 15, 19, 32, 33 and 34 in Annexure 6 to the Counterclaim.[125]
(ii) On or about 15 June 2018, the plaintiff was prepared to settle costs, on a commercial basis, for the amount of $550,000.[126]
(iii) By email sent at 9.29am on 21 June 2018 the defendant's UCPR offer was made to the plaintiff as follows:
(A) In full and final settlement of all claims and counterclaims, the defendant pay to the plaintiff:
(I) the sum of $1,850,000;
(II) interest pursuant to the Civil Proceeding Act; and
(III) the plaintiff's costs on the standard basis.
(B) The parties enter into a mutually acceptable deed of settlement and release reflecting the terms of the offer.
(iv) By email at 9.31 am on 21 June 2018 the defendant's Calderbank offer was made to the plaintiff as follows:
- (A) In full and final settlement of all claims and counterclaims, the defendant pay the plaintiff the sum of $2,250,000 (inclusive of legal fees and interest) within 14 days of acceptance of the offer.
The clarity with which the terms of the offer were expressed
Whether the offer foreshadowed an application for indemnity costs in the event of the offeree rejecting it
The offeree's prospects of success, assessed at the date of the offer
"The offer outlined why the defendants suggested that the plaintiff would fail at any trial. In support of that contention, the offer advanced reasons which were the equivalent of two critical propositions which I ultimately accepted in my judgment on the merits .... I made equivalent points in my judgment on the merits". (footnotes omitted)
"The terms of the offer explained critical matters fatal to the plaintiff's case which were entirely consistent with the way in which the trial and my judgment played out."
(a) It avoided the need for further costs being incurred to obtain an assessment of costs.
(b) If the offer was accepted the money would be paid within 14 days, giving certainty of cash-flow.
(c) It would give finality to the issues then in dispute between the parties.
(d) It would have removed the then current risk of the defendant having recourse to the security bond in respect of the defects (and/or as happened here, the plaintiff having to pay an equivalent cash security to avoid a call on the security bond).
(a) The 2018 Defence and Counterclaim pleading in respect of the Mechanical Variation differed to that at trial; and
(b) The counterclaim was unquantified at the time of the offer and changed significantly after the offer.
(a) Denies that the notices constituted a direction to undertake a variation under the Contract ([8(d)]);
(b) Says that the Contract ( clauses 1, 2,1, 2.2, 8.5(a) and annexures L, K and O) required the plaintiff to provide an air-conditioning system that provided independent heating and cooling ([8(aa)]);
(c) Says that the air-conditioning system installed by the plaintiff:
(i) did not provide independent heating and cooling; and
(ii) as a result if (i) was defective ([8(ab)]);
(d) Says that the notices to the plaintiff dated 11 August 2016, 16 August 2016 and 17 September 2016 were notices of defective works ([8(b) and (c)]).
(a) At [9]:
(i) The plaintiff undertook the work to replace the 2-pipe heat pump air conditioning system with a 3-pipe air conditioning system ([9(a)]);
(ii) Denied this work was additional and stated "it was not" ([9(b)]);
(iii) Denied that this work was required to give effect to the alleged Mechanical Direction or any direction or variation and says "as it was not" ([9(c)]);
(iv) Repeats and relied on the matters pleaded in [8].
(b) At [10]:
(i) The work required as a consequence of the notices dated 11 August 2016, 16 August 2016 and 17 September 2016 was not a variation of the work under the Contract ([10(c)]);
(ii) Identifies the Mechanical Services Specification ([10(h)]);
(iii) Identifies that the "Mechanical Services Specification and Mechanical Services Preliminary Design Drawings set out those performance requirements listed in the 11 August 2016 notice from the Superintendent" ([10(i)]);
(iv) Says that "Annexure O of the Contract expressly required that any alternative mechanical systems, including the air-conditioning system, proposed by the Plaintiff were required to meet the performance requirements set out in the tender drawings and specifications" ([10[j)]);
(v) Says that "the work required as a consequence of the 11 August 2016 notice was work required to rectify, or partly rectify, the non-compliance of the mechanical system designed and installed by the Plaintiff with the performance requirements set out in the Mechanical Services Specification and Mechanical Services Preliminary Design Drawings" ([10(k)]). (emphasis added)
"the mechanical services system installed by the Contractor does not comply with the Contract and, in particular, paragraph 1(u) of the Annexure Part O, as that mechanical services system does not meet the performance requirements set out in the Thwaite Consulting Group Mechanical Services Specification, Reference 3235, October 2014 document which form part of the preliminary design."[129] (emphasis added)
"2.2 Mechanical Variation, Delay Costs and Repayment of Liquidated Damages claims are doomed to fail
2.3 The crux of the claims made in the Proceeding arise out of your client's claim for the Mechanical Variation. Specifically, what system the Contract required your client to design and install, and whether that system was the 2-pipe VRF system which your client initially commenced the installation of, or the 3-pipe VRF system which your client has ultimately completed the installation of. Out of your client's claim for the Mechanical Variation flows your client's Delay Cost claim, which ultimately flows into your client's claim for the repayment of the Liquidated Damages.
2.4 Paragraph 1(u) of Annexure Part O of the Contract provides as follows:
(u) The Contractor's alternative proposal for structural and mechanical systems on the basis that the Contractor meets the performance requirement of the tender drawings and specifications.' (emphasis added)
2.5 Clause 8.1 of the Contract relevantly provides that:
When construing the Contract Documents, the following rules of construction apply:
(a) in the event of any inconsistency between the Contract Documents:
(i) the formal instrument of agreement and these general conditions have precedence; and
(ii) the clarifications have precedence over the preliminary design;
(i) where inconsistent levels of quality are required, the higher level of quality shall apply
The Contractor shall have no entitlement as a consequence of a direction given by the Superintendent under this subclause 8.1 which is consistent with the rules of construction in this clause 8.1.'
2.6 Your client has adopted an interpretation of the Contract that makes the emphasised part of paragraph 1(u) of Annexure Part O of the Contract otiose. If it was the case that, by the Contract, the parties had agreed on a position that your client's alternative proposal was to be used, whether or not it satisfied the drawings and specifications, there would be no need to include that qualification within paragraph 1(u) of Annexure Part O of the Contract. It follows that the mechanical system still needed to comply with the performance requirements of the drawings and specifications (including that the system independently heats and cools) and if your client's alternative system was unable to comply with the drawings and specifications, then your client was required to design and install a system that did."
"2.10 In the premises of paragraphs 2.3 to 2.9 of this letter, your client's claim for Delay Costs will fail because your client will not establish that the Mechanical Variation is in fact a variation under the Contract and therefore no Qualifying Cause of Delay under the Contract has occurred. Even if your client could establish that a Qualifying Cause of Delay under the Contract has occurred (which is denied), your client will not succeed in establishing an entitlement to delay costs under the Contract because:
(a) the Project was more than 100 days late as at the date that the Superintendent issued the notice of defect for the Mechanical System;
(b) there was a further delay of more than two months before your client confirmed that it would comply with the Superintendent's direction;
(c) your client appears to have manipulated its programs to try and keep the Mechanical System on the critical path.
2.11 In the premises of paragraph 2.10 of this letter, your client's claim for repayment of Liquidated Damage will also fail."
"The critical issue for determination in in this matter is whether or not the Independent Heating/Cooling Function was a performance requirement of the tender drawings and the Specification."
(a) The plaintiff's asserted construction was inconsistent with the language of the Contract, in that clause 3.1 of the Specification did not contain the only performance requirements of the Contract.
(b) The plaintiff's asserted construction was contrary to the language of the drawings and specifications forming part of the Contract, indicating that each room was to be individually air conditioned.
(c) The plaintiff's asserted construction was not consistent with the construction that a reasonable businessperson would make of the Contract, in particular that 'conditioned air' did not mean 'unconditioned air' from outside ventilation.
(d) The plaintiff's asserted construction was contrary to accepted facts, in particular that it was possible to design a VRF air conditioning system providing for independent heating and cooling. This was in fact what happened.
(a) [157(b)] and [168] - [169];
(b) [158] - [159];
(c) [160] - [161]; and
(d) [164].
"The circumstances which are most likely to arise and which might justify relieving a defendant from the obligation to pay solicitor and client costs, will be those where there is such a significant change in the manner in which the plaintiff's case is presented at the trial, or the manner in which the evidence emerges at the trial, that it might fairly be said that the full dimensions of the plaintiff's entitlement could not possibly have been foreseen before the hearing commenced."[135] (emphasis added)
(a) Significant changes were made to the counterclaim after the offer was made.
(b) At the time of the offer the counterclaim was not quantified.
(c) The plaintiff rectified some of the alleged defects at some stage after the offer.[137]
(d) The offer did not identify an amount referable to the defects claim.
(e) The defendant abandoned close to 80 per cent of the defects alleged at the time of the Calderbank offer.[138]
"When dealing with the issue of costs in the context of settlement negotiations it is important to recognize, as it seems to me, that such negotiations often take place before the trial commences, well before the evidence is concluded and often before its detail is clear. Moreover, as the matter proceeds, the absence of settlement in the period - sometimes lengthy - before trial will often lead to further investigation and the collection of further evidence. The notion that Calderbank offers can safely be ignored without costs consequences just because the offeror's case is not ready for trial or all pre-trial requirements as to service of reports or supply of particulars have not been complied with cannot be right: much will depend on a commonsense approach to the case and the particular circumstances at the time of the offer.
... The mere fact that a defendant does not know precisely what the value of the plaintiff's claim or the scope of the evidence proposed to be led in support of it when a Calderbank offer is made does not mean that it is not unreasonable for such an offer to be ignored. After all, the defendant is not without the means of independently estimating the value of the case. Offers are very often made and accepted because the value of the claim is difficult to estimate. Much also depends also on the extent to which the offer is exceeded by the judgment. (emphasis added).
In short, the question is not so much what is the 'true' value of the plaintiff's case but having due regard to the imponderables and uncertainties in the case, whether it was 'plainly' unreasonable to refuse the plaintiff's offers, bearing in mind the 'ordinary rule is that costs when ordered in adversary litigation are to be recovered on the party and party basis': per Sheppard J in Sanko Steamship Co (supra). These are all very much matters of fact and degree."
(a) The Mechanical Variation and associated claims by far constituted the largest component of the plaintiff's claim. If the plaintiff was unsuccessful in respect of those claims, the plaintiff could only recover an amount substantially less than the defendant's Calderbank offer.
(b) The other claims by the plaintiff totalled $1,196,881.19.[140] Even if the plaintiff was totally successful on those claims (which it was not) and successfully defended all the counterclaim, the amount paid to the plaintiff (even including interest and costs) would be substantially less than the defendant's Calderbank offer (and also the defendant's UCPR offer).
(c) Factoring in a mixed result on the other claims and the counterclaims (which is what occurred), then the prospect of the plaintiff obtaining a judgment more favourable than the defendant's Calderbank offer is even further diminished.
(d) While the plaintiff may have considered that its construction of the Contract in respect of the Mechanical Variation was open, the prospects of success have to be considered in light of the advantages and disadvantages of the offer.
(e) The issues at the heart of the Mechanical Variation claim had been ventilated during the project and explored in detail in project correspondence. The dispute resolution procedures in the Contract had also been activated.
(f) The plaintiff and the defendant are sophisticated parties and are familiar with the evaluation and allocation of time, costs and risk. These are at the heart of every construction contract and project.
(g) The plaintiff should have been aware of the difficulties it faced in respect of its Mechanical Variation claim.
(h) Similarly, the plaintiff was uniquely placed to be able to evaluate the claims in respect of defective work then included in the counterclaim. It did in fact do so at least the week prior to the defendant's Calderbank offer when the plaintiff made its UCPR offer.
(i) The plaintiff should have been aware of the consequences of the rejection of the defendant's UCPR offer and the defendant's Calderbank offer. After that point, by proceeding to have the Court determine the claims, the plaintiff did so knowing that the litigation risks included the potential reallocation of the costs risk.
(a) The evidence in chief constituted by witness statements and expert reports devoted to the Mechanical Variation claim; and
(b) The closing submissions and transcripts by reference to each claim and counterclaim.
(a) The Court is empowered to determine that some other order is more appropriate in the exercise of the broad discretion.[143]
(b) The general approach is that there must be special or exceptional circumstances to warrant depriving a successful party of its costs and the mere fact that the successful party has been unsuccessful on some issues will ordinarily not be sufficient to do so.[144]
(c) One circumstance where it might be appropriate to award costs of a particular question or part of a proceeding is where that matter is definable and severable and has occupied a significant part of the proceeding.[145]
(d) Where there are multiple issues which are determined in different directions as between the parties, a court may form the "overall impression" having regard to the significance of the issue, the way they were determined, and the amount of time and cost spent on them.[146]
(e) An appropriate costs order may be that a party pay a portion of another party's costs as a way to reflect fairly the parties' comparative success or failure in the outcome which was obtained.[147]
(f) Further, if different issues are determined in different directions and costs were awarded in respect of issues, this may result in overly complicated costs assessments.[148]
(g) It is open to the Court to "net-off" orders for issues in different directions and to arrive at a "rough and ready" assessment.[149]
(a) Claims by the plaintiff:
(i) Mechanical Variation, including:
- (A) Delay Damages;
- (B) Extension of Time claim; and
- (C) Repayment of Liquidated Damages
(ii) Joinery Delay;
(iii) Bathroom Design Variation;
(iv) The Schedule 3 and 4 variations;
(v) The Schedule 5 provisional sums;
(vi) The Schedule 6 variations;
(vii) Other claims by the plaintiff, including:
- (A) Utility back charges;
- (B) Amounts withheld for defects; and
- (C) Amounts unpaid.
(b) Counterclaims by the defendant:
(i) Alleged non-mechanical defects;
(ii) Alleged mechanical services defects;
(iii) Additional liquidated damages.
1. The defendant pay the plaintiff's costs, calculated on the standard basis, up to and including 21 June 2018; and
2. The plaintiff pay the defendant's costs, calculated on the indemnity basis, after 21 June 2018.
Annexure A - Agreed tables of amounts claimed and amounts reflected in judgment figure
Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd
Amounts claimed at trial and amounts included in judgment of $459,354.38
An extension of the Date of Practical Completion until at least 3 March 2017[152]
The Plaintiff was not entitled to an extension of the Date of Practical Completion
Schedule 4: $189,993.45 (plus GST)[156]
$28,910.78 plus GST, being $31,801.86.[159]
$141,626.65 plus GST, being a total of $155,789.32[164]
$53,758.37 plus GST, being a total of $59,134.21[166]
$834,150.68[168] [NOT AGREED] [DEFENDANT: $91,757.29]
Annexure B - Agreed tables of amounts claimed at time of defendant's Calderbank and UCPR offers
Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd
At time of offer - Amounts claimed (21 June 2018)
Entitled to an extension of the Date for Practical Completion until at least 3 March 2017[175]
Schedule 4: $188,167.30 (plus GST)[179]
The Defendant sought an order requiring specific performance by the Plaintiff of its obligation to rectify the defective works, and in the alternative, the Defendant sought damages (but with no quantification of the damages).[184]
Note: In relation to the calculation of the judgment sum, the parties agreed to the below calculations on the basis of the table in paragraph [8] of Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd (No 2) [2021] QSC 301:
Unpaid portion of progress claim 24 and unpaid contract sum
Balance of security amount not attributable to defects
[1] Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd [2021] QSC 224.
[2] Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd (No 2) [2021] QSC 301.
[13] Unreported Court of Appeal Supreme Court of New South Wales 19 April 1989.
[17] The Law Book Company; 1986 at 258.
[18] London Publishing Partnerships; 3rd edition; 2020 at pp 2266.
[19] See eg. Rival Nominees Pty Ltd v Craig Davis Constructions Pty Ltd (unreported) Supreme Court of Victoria, Full Court; 26 June 1981, see especially Starke ACJ at 11-12; LNC Harper Davidson Pty Ltd t/as Allansons (WA) v Keywest Building Co Pty Ltd Unreported; Supreme Court of Western Australia; 13 July 1988 per Kennedy J at 11; Angelatos v Alternative Constructions Pty Ltd Unreported; Supreme Court of Victoria; Full Court; 30 November 1992 per Brooking J at 6 (with whom Phillips and Byrne JJ agreed); Lamac Developments Pty Ltd v Devaugh Pty Ltd [2001] WASC 298 at [90] per Roberts-Smith J, which was endorsed on appeal: Lamac Developments Pty Ltd v Devaugh Pty Ltd [2002] WASCA 245; (2002) 27 WAR 287; Kane Constructions Pty Ltd v Sopov (No. 2) [2005] VSC 492 at [64] and [68] per Warren CJ. See also Badge Constructions Pty Ltd v Penbury Coast Pty Ltd [1999] SASC 6 at [10].
[20] [2007] WASCA 158 (S) at 115, [7].
[21] [2020] QSC 1 per Flanagan J and upheld on appeal [2021] QCA 8.
[22] Giles JA in SMEC Testing Services Pty Ltd v Campbelltown City Council [2000] NSWCA 323 at [37]. See also AVS Australian Venue Security Services Pty Ltd v Criminale (No 2) [2007] NSWCA 34, [7]; Porter v Lachlan Shire Council (No 2) [2006] NSWCA 252, [6]; Jones v Bradley (No 2) [2003] NSWCA 258, [8]; Leichhardt Municipal Council v Green [2004] NSWCA 341, [19]; Brymount Pty Limited t/as Watson Toyota v Cummins (No 2) [2005] NSWCA 69, [14].
[23] See Annexure A to the defendant's written submissions.
[25] See Defendant's written submissions at [68]. This figure was confirmed as correct by email dated 16 March 2022.
[26] See Defendant's written submissions at [68]. These figures were confirmed as correct by email dated 16 March 2022.
[27] Figure at [69] missing a digit. Figure corrected at hearing.
[28] Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd [2020] QSC 1 at [6] (Flanagan J).
[30] The Chief Justice identified at [30] a possible broader construction, however, did not decide the issue. Philippides JA and Brown J also expressly did not decide the issue. It is not necessary to consider that possible broader construction further in the current circumstances.
[33] Under r 360 (plaintiff's offer) and r 361 (defendant's offer).
[34] Cf Australian Medica Innovations Pty Ltd v GO Medical industries Pty Ltd, Supreme Court of Western Australia (Wallwork J), 22 April 1996, BC9601613.
[35] There may be more than one incentive to clarity and certainty. Rules 360(1)(d) and 361(2) empower the court to make a different order for costs than that which otherwise obtains where the offeree does not better the offer by the judgment. The more the complications arising from the offer, the greater the prospect that the court may order a departure from the ordinary costs consequences: Godin v Godin [2004] WASCA 186 at [37]- [38]; cf Preti v Sahara Tours Pty Ltd [2008] NTCA 2 at [46]- [49].
[36] Dover Beach Pty Ltd v Geftine Pty Ltd [2008] VSCA 248 at [118].
[37] Cf Williams Civil Procedure, Victoria I 26.02.30; AJ Lucas Drillings Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd (No 2) [2010] VSCA 128 at [31]- [33], where the court refrained from ruling on whether the uncertainty also affected validity as an "offer of compromise"; and Armstrong v Mitchell-Smith and Allianz Australia Insurance Limited (No 2) [2012] QSC 370 at [10]- [13].
[41] At [28]. His Honour also refers to the decision of the Ontario Court of appeal in Rooney (Litigation Guardian of) v Gray 53 OR (3d) 685, 198 DLR (4th) 1; 2001 CanLII 24064 on the basis that the Ontario rules were the source of Part 5 UCPR.
[45] See Balnaves v Smith [2012] QSC 408 at [27], referring to Rooney (Litigation Guardian of) v Gray 53 OR (3d) 685, 198 DLR (4th) 1; 2001 CanLII 24064.
[46] Armstrong v Mitchell-Smith and Allianz Australia Insurance Limited (No 2) [2012] QSC 370 at [10]- [13].
[47] See Armstrong v Mitchell-Smith and Allianz Australia Insurance Limited (No 2) [2012] QSC 370 at [10]- [13]. In this regard, Byrne SJA in Balnaves v Smith did not appear to differ from the view of Moynihan SJA in Taske: see Balnaves v Smith [2012] QSC 408 at [8].
[56] Taske at [16]. Armstrong at [14].
[57] See [27] Plaintiff's written submissions.
[58] See [27] and [34] Plaintiff's written submissions.
[71] See [51] Defendant's written submissions on costs and Annexure A, being a printout from the Queensland Court's online interest calculator.
[72] Avis v Mark Bain Constructions Pty Ltd (No 2) [2011] QSC 151 at [3]- [5] (Atkinson J); BM Alliance Coal operations Pty Ltd v BGC Contracting Pty Ltd [2015] 1 Qd R 228 at [86] (Muir JA; Holmes JA and Ann Lyons J agreeing); Chambers v Brice [2014] QSC 52 at [9], [12] & [16] (Peter Lyons J); Keeley v Horton [2016] QCA 253 at [13] (Burns J; Holmes CJ and Peter Lyons J agreeing); Mr Green Pty Ltd v Broadbeach Bowls & Community Club Inc (No 2) [2018] QDC 65 at [41] (McGill SC DCJ).
[87] See for example, Campbell v Northern Territory of Australia (No 4) [2021] FCA 1413 at [36] which included a condition "the parties enter into a Deed of Settlement and release in terms agreed by the parties".
[88] Defendant's written submissions at [43].
[89] Farmer v Hoban [1919] HCA 13; (1919) 26 CLR 183, 193 (Barton J); Masters v Cameron [1954] HCA 72; (1954) 91 CLR 353, 360.
[90] McKay v Armstrong & Anor [2020] QDC 146.
[91] Binaray Pty Ltd as Trustee for the Allen Family Trust v RAMS Financial Group Pty Ltd [2019] QSC 280 at [40] where Brown J considered the alternative to her main reasoning.
[92] Defendant's written submissions at [40] and [53] and footnote 50.
[94] Being the 2018 Defence and Counterclaim.
[95] See Defendant's written submissions at [68] and [69].
[96] See document entitled "Schedule of Defects - as identified by Built as similar and referable to defects included in 2018 Defence and Counterclaim" (which was handed up at the hearing and attached to the back of the Defendant's submissions on costs).
[100] Seven Network Ltd and Anor v News Ltd and Ors [2007] FCA 1489; [2007] 244 ALR 374 at [59]- [63]; Evans Shire Council v Richardson (No 2) [2006] NSWCA 61 at [26]; Evans v Braddock (No 2) [2015] NSWSC 518 at [49]; Southwell v Staite (No 2) [2019] ACTSC 83 at [15].
[101] Rule 360 UCPR expressly says unless "the defendant shows" another costs order is appropriate.
[102] Equally, the onus would be on the plaintiff to show that an alternative order was appropriate.
[106] Elite Protective Personnel Pty Ltd v Salmon [2007] NSWCA 322 at [100].
[111] See Hadgelias Holdings at [11].
[112] See Hazeldene's Chicken Farm at [16], [18], [20].
[113] See Hazeldene's Chicken Farm at [20]; J & D Rigging at [5]; Hadgelias Holdings at [11], footnote 2 and the citation of Velvet Glove Holdings Pty Ltd v Mount Isa Mines Ltd [2011] QCA 312 at [105].
[114] See Hazeldene's Chicken Farm at [19]; J & D Rigging at [5].
[115] See Hazeldene's Chicken Farm at [19]-[20]; J & D Rigging at [5].
[116] See Hazeldene's Chicken Farm at [21]-[23]; J & D Rigging at [5].
[117] See Hazeldene's Chicken Farm at [21]
[118] See Hazeldene's Chicken Farm at [24].
[119] See Hazeldene's Chicken Farm at [25]
[120] See Hazeldene's Chicken Farm at [25]; J & D Rigging at [6]; Hadgelias Holdings at [11].
[121] But no GST on $10,025.62 utility backcharges. See Annexure B relating to amounts claimed at time of offer. This sum is derived from adding the amounts at A(1) to A(8).
[122] See Annexure A table dealing with amounts claimed at time of the offer. See Annexure B relating to amounts claimed at time of offer. This sum is derived from adding the amounts at A(1) to A(3)
[123] This amount is calculated by adding A(1) to A(8) of Annexure B, and adding GST as applicable.
[124] The covering letter confirmed that the defects in the offer did not include those the plaintiff had already rectified or provided further information about to confirm they had been rectified.
[125] This appears to include four of the defects on which the defendant was ultimately successful at trial, including the item in respect of the Guestroom and Maids rooms exhausts air conditioning where the amount awarded was $376,727.68.
[126] Affidavit of Anthony Ursino sworn 16 December 2021, Exhibit ADV-4, at 8. See also T1-24 line 15-18.
[127] Particularly where, as here, both parties are represented by experienced legal teams.
[129] See [2(b)] of the notice dated 11 August 2016 at Exhibit SGS-3 to the affidavit of Samuel Speechly sworn 16 December 2021.
[130] Plaintiff's written submissions in reply at [32].
[132] Defendant's written submissions at [73].
[133] Defendant's written submissions at [76].
[137] Plaintiff's written submissions on costs at [43].
[138] Plaintiff's written submissions at [48].
[139] [2005] NSWSC 841 at [14]- [16].
[140] Defendant's written submissions at [69]. This sum is the product of the amount claimed, $5,257,165.22, less the sum of $4,060,284.03, which itself is the aggregate of the other amounts referred to in paragraph [68].
[141] Further, the inference may be open that 60 per cent of the plaintiff's actual costs at the time of the plaintiff's UCPR offer was less than $550,000. But I do not need to conclusively determine that issue.
[142] The deed of release reflecting the terms of the offer could not impact that effect.
[150] This figure was confirmed as correct by email dated 4 April 2022. The approach to calculating the judgment (ignoring the security amount) was to a) add up the amounts in A(2), (5), (6), (8)(i), (ii) and (iii) of Annexure A (incl GST) (being $367,597.09); and b) take that amount away from the amount the defendant was successful on at (B) of Annexure A, the difference being $374,796.30 in favour of the defendant.
Built Qld Pty Ltd
Pro-Invest Australian Hospitality Opportunity
(2009) 239 CLR 175
(2001) 1 Qd R 476
(1919) 26 CLR 183
(2005) 13 VR 435
(2002) 27 WAR 287
(1954) 91 CLR 3535
(1999) 76 SASR 28
(1993) 42 FCR 97
(2014) 252 CLR 331
(1936) 55 CLR 499
(1954) 91 CLR 353
(2007) 244 ALR 374
(j) The potential reallocation of the costs risk was as set out in r 361 UCPR and the principles in the Calderbank line of authorities. If the plaintiff did not "better" the defendant's UCPR offer and/or the defendant's Calderbank offer it was at risk of having to pay the defendant's costs on the standard basis from 21 June 2018 and potentially on an indemnity basis.
(k) The amount of the defendant's Calderbank offer was generous, particularly factoring in the prospects of success in respect of the Mechanical Variation.
(l) The plaintiff was in a position to sufficiently assess and analyse the defendant's Calderbank offer even though it was inclusive of all claims, interest and costs. The plaintiff would have been able to identify its actual costs to date and estimate costs on a standard basis with the assistance of the plaintiff's solicitors.
(m) Further, there is evidence that the plaintiff would have accepted $550,000 (on a commercial basis) in respect of its standard costs for the purposes of the plaintiff's UCPR offer at the time just prior to the defendant's Calderbank offer.[141]
(n) The defendant's UCPR offer received immediately prior to the defendant's Calderbank offer is also a relevant circumstance. The overall effect of the defendant's UCPR offer was that the defendant would pay the plaintiff over $2 million (principal sum and interest) plus costs on the standard basis to finalise the claims in the claim and counterclaim.[142]
(o) If the defendant's UCPR offer operated such that the order under r 361 were mandated, then the defendant's Calderbank offer may be relied on to support another order, namely costs on the indemnity basis. This was clearly foreshadowed in the defendant's Calderbank offer.