[2025] WASAT 94
General information, not legal advice.
State Administrative Tribunal (WA)
2025-09-11
Original judgment source is linked above.
CITATION : BLACKWELL and BOOY [2025] WASAT 94
Building dispute - Defects in construction - Home building contract work - Breach of contract - Respondent's conduct - Costs of remedial work - Exercise of Tribunal discretion in making a building remedy order - Whether order to remedy or order to pay - Applicant's costs of proceeding
Brooks and Gransden Building Company Pty Ltd [No 2] [2021] WASAT 86
Deshmukh and Distinctive Building Services Pty Ltd [2024] WASAT 15
Electricity Generation and Retail Corporation t/as Synergy v EIT Kwinana Partner Pty Ltd [2022] WASCA 3
Gemmill Homes Pty Ltd v Sanders [2018] WASC 179
Owners of Island Apartments Strata Plan 52597 and Pindan Pty Ltd [2018] WASAT 2
(1) In early May 2022 Mr Booy and Mr Blackwell formed a friendship when they met by chance at a Bunnings store.
(2) In mid-May 2022 Mr Booy was experiencing difficulties in engaging trades to perform building work at his home and he asked Mr Blackwell if he was interested in constructing a complete deck with jarrah decking boards at the home. At that time Mr Blackwell was unemployed and so was open to doing work for Mr Booy.
(3) Mr Blackwell originally provided Mr Booy with a quote for the supply of a complete deck inclusive of jarrah decking boards. Over time, however, Mr Booy changed the proposed scope of works to exclude the supply of jarrah decking boards as he believed he could source jarrah boards for a lower price than Mr Blackwell could.
(4) On 24 May 2022 Mr Blackwell provided Mr Booy with a quote for the supply and installation of a deck exclusive of jarrah decking boards. This quote was titled 'Jarrah Decking Job As Discussed' and consisted of a number of briefly described items with a total price of $6,133.24. Both parties accept that under this quote Mr Blackwell was not offering to supply the decking boards and these were to be sourced and supplied by Mr Booy. However, importantly for what happened later, the quote is silent as to whether Mr Blackwell was offering under this quote to lay the decking boards that were to be supplied by Mr Booy.
(5) On or shortly after 24 May 2022, through Mr Booy's verbal acceptance of Mr Blackwell's written quote dated 24 May 2022, Mr Blackwell and Mr Booy entered into a contract for the supply and installation of a deck exclusive of jarrah decking boards (the original contract).
(6) In June 2022 Mr Booy asked Mr Blackwell if he was interested in renovating a partially enclosed patio at the rear of the home. On 26 June 2022 Mr Blackwell provided Mr Booy with a quote titled 'Rear Room Renovation' for the price of $3,589.19. Again, importantly for what happened later, the quote is silent as to whether Mr Blackwell was offering to renovate the enclosed patio area to the standard of a habitable room or to the standard of an uninhabited room. On or shortly after 26 June 2022 Mr Blackwell and Mr Booy agreed to vary the original contract through Mr Booy's verbal acceptance of Mr Blackwell's written quote dated 26 June 2022, so that in addition to the supply and installation of a deck, exclusive of jarrah decking boards, Mr Blackwell was to renovate a partially enclosed patio at the rear of the home (the amended contract).
(7) On 19 July 2022 Mr Booy told Mr Blackwell he wanted to increase the size of the deck that was to be supplied and installed by Mr Blackwell. On that same day Mr Blackwell verbally agreed to vary the amended contract to effectively double the size of the deck to around 54m2. Mr Blackwell's invoice dated 9 August 2022 titled 'Extra Addition to Decking' in the amount of $3,260.24 is for this variation.
(8) On or around 9 August 2022 Mr Booy paid Mr Blackwell $4,000. On another date Mr Booy paid Mr Blackwell $800.
(9) On 2 September 2022 Mr Blackwell issued Mr Booy with an invoice titled 'Rear Room And Deck Extras' in the amount of $836.07. This invoice for 'Extras' along with the variation to increase the size of the decking works brought the total contract price to $13,818.74, of which $9,018.74 remains outstanding.
(10) Between 19 July 2022 and 20 October 2022 Mr Blackwell performed works at the home in furtherance of the amended contract. These works consisted of supplying and installing a deck frame and performing renovation work to the enclosed rear patio area of the home.
(11) On 20 October 2022 Mr Booy emailed Mr Blackwell to inquire when he would attend the home to 'finish off the decking', that is, to inquire when Mr Blackwell would attend the home to lay the decking boards supplied by Mr Booy on the deck frame. Mr Blackwell replied to Mr Booy's email on the same day by stating 'I will not be laying your decking'. It was around this time that the relationship between Mr Blackwell and Mr Booy changed from friendship to hostility.
(12) On or about 30 October 2022 Mr Booy engaged a third party, BGH Enterprises Pty Ltd (BGH), to lay the boards on the deck frame. Mr Booy paid BGH $3,000 plus GST ($3,300 in total), consisting of $2,300 for labour and $700 for materials such as additional timbers and stainless-steel decking screws.
(13) In early 2023 Mr Booy engaged Mr Chamberlain, a registered builder, to inspect the works performed by Mr Blackwell.
(14) On 16 March 2023 Mr Chamberlain produced his first report on the renovation works performed by Mr Blackwell at the home (the 16 March 2023 report).
(15) On 7 July 2023 the Building Commissioner's delegate, with Mr Blackwell's consent, issued 'Building Remedy Order 0202327 Building Service at 7 Emilia St, Coolbellup' (BRO).
(16) On 7 August 2023 Mr Blackwell lodged with the Building Commissioner a complaint containing five complaint items relating to monies not paid by Mr Booy for the decking works. The total sought by Mr Blackwell at that time was $9,920.61 plus interest. On 8 January 2024 the Building Commissioner's delegate pursuant to s 11(1)(d) of the Building Services (Complaint Resolution and Administration) Act 2011 (WA) (BSCRA Act) referred the five complaint items to the Tribunal, which gave it matter number CC 8 of 2024.
(17) Between 7 July 2023 and 31 August 2023 Mr Blackwell performed some remedial works at the home in accordance with the BRO.
(18) On 1 September 2023 Mr Booy lodged with the Building Commissioner a complaint that Mr Blackwell had failed to comply with the BRO. On 5 January 2024 pursuant to s 51 of BSCRA Act the Building Commissioner transferred Mr Booy's complaint to the Tribunal, which gave it matter number CC 10 of 2024, and which transfer was consented to by the Tribunal on 23 January 2024.
(19) On 17 October 2023 Mr Chamberlain produced his second report, which is an assessment of the remedial works performed by Mr Blackwell in accordance with the BRO (the 17 October 2023 report).
(20) On 17 September 2023 Mr Booy lodged with the Building Commissioner a complaint containing four complaint items relating to loss of rent incurred as a result of Mr Blackwell's failure to complete the decking works in accordance with the contract and that the renovation works were defective. Mr Booy seeks compensation from Mr Blackwell for the cost of completing the decking works, loss of rental income due to the defective renovation works and the cost of engaging a building expert to inspect and report on the renovation works. On 8 January 2024 the Building Commissioner's delegate pursuant to s 11(1)(d) of the BSCRA Act referred Mr Booy's four complaint items to the Tribunal, which gave it matter number CC 9 of 2024.
(21) On 23 January 2024 Mr Booy lodged with the Building Commissioner a complaint containing eight complaint items, seven of which related to the renovation works and one which related to a claim for lost income and expenses in attending to a claim lodged by Mr Blackwell in the Fremantle Magistrates Court. Mr Booy seeks compensation from Mr Blackwell for the cost of remedying the renovation works, the cost of engaging a building expert to inspect and report on the renovation works and loss of income due to attending to this complaint. On 25 February 2024 the Building Commissioner's delegate pursuant to s 11(1)(d) of the BSCRA Act referred six of Mr Booy's eight complaint items to the Tribunal, which gave it matter number CC 124 of 2024.
(22) On 2 July 2024 Mr Blackwell lodged with the Building Commissioner a complaint containing one complaint item which related to monies not paid by Mr Booy for the decking works and the renovation works plus interest. On 9 July 2024 the Building Commissioner's delegate pursuant to s 11(1)(d) of the BSCRA Act referred two complaint items (one item relating to the claim for unpaid invoices and another as a claim for interest) to the Tribunal, which gave it matter number CC 446 of 2024.
(23) Between 1 September 2023 and 16 September 2024 Mr Blackwell performed some further remedial works in accordance with the BRO.
(24) On 16 September 2024 Mr Chamberlain produced his third report which is an assessment of these further remedial works performed by Mr Blackwell in accordance with the BRO (the 16 September 2024 report).
(1) Mr Blackwell did provide Mr Booy with construction drawings for the decking works but he did not provide any construction drawings for the renovation works;
(2) Mr Blackwell is not a registered builder and did not obtain a building permit from the local authority for either the decking works or the renovation works; and
(3) Mr Blackwell did not obtain indemnity insurance for the works and given the contract was under $20,000 he was not required to obtain such insurance.
(1) If the Building Commissioner refers a HBWC complaint to the State Administrative Tribunal, the Tribunal may -
(a) if satisfied that the order is justified, make a HBWC remedy order; or
(1) Is there a valid home building work contract between the applicant and the respondent to the proceeding?
(3) Has the respondent breached the relevant terms of the contract?
(4) Has the applicant suffered loss, damage, or detriment which can be addressed by a HBWC remedy order?
(1) The principles applicable to the determination of a building service complaint set out by the Tribunal in Owners of Island Apartments Strata Plan 52597 and Pindan Pty Ltd [2018] WASAT 2 (Pindan Pty Ltd) at [27] - [35]:
(2) The statements of Smith AJ (as her Honour then was) as to the proper construction of s 38 of the BSCRA Act in Gemmill Homes Pty Ltd v Sanders [2018] WASC 179 (Gemmill Homes) at [96], [102], [103], [106] - [111], [125] - [129], [133] and [134] as these are summarised in Deshmukh at [46] to [48]:
(3) The observations as to the differing natures of building remedy orders under s 36(1)(a) and s 36(1)(b) of the BSCRA Act made by the Tribunal in Brooks and Gransden Building Company Pty Ltd [No 2] [2021] WASAT 86 (Brooks) at [14] to [17]:
(1) With respect to CC 8 of 2024 and CC 446 of 2024, which are HBWC complaints made by Mr Blackwell:
(a) Is Mr Booy in breach of the amended contract by failing to pay all monies owed by him to Mr Blackwell and, if so, what amount should he pay?
(b) Should the Tribunal make a HBWC order requiring Mr Booy to pay these monies to Mr Blackwell?
(c) Is Mr Booy required to pay interest on any monies owed by him to Mr Blackwell?
(2) With respect to CC 9 of 2024, which is a building services complaint made by Mr Booy about the decking works and the renovation works:
(a) Are the decking works and the renovation works a 'regulated building service' under the BSCRA Act?
(b) If so, were either the decking works or the renovation works not carried out in a proper or proficient manner or are faulty or unsatisfactory?
(c) If the decking works or the renovation works are a regulated building service which are not carried out in a proper or proficient manner or are faulty or unsatisfactory, whether the Tribunal should make a building remedy order with respect to the decking works or renovation works?
(d) If the answer is that the Tribunal should make a building remedy order with respect to the decking works or renovation works, what is the appropriate order?
(e) If a building remedy order should be made, has Mr Booy suffered loss (rent and income)? If so, is Mr Booy to be compensated for that loss?
(3) With respect to CC 10 of 2024, which is an allegation made by Mr Booy that Mr Blackwell failed to complete works required under BRO 0203-27:
(a) What were the remedial works Mr Blackwell was required to perform pursuant to the BRO?
(b) Has Mr Blackwell complied with the BRO by completing the required remedial work?
(c) If Mr Blackwell has not complied with the BRO, should the Tribunal exercise its discretion under s 51 of BSCRA Act and revoke the BRO and make a building remedy order pursuant to s 36(1)(b) or (c)?
(4) With respect to CC 124 of 2024, which is a building services complaint made by Mr Booy about the renovation works on the enclosed rear patio area:
(a) Did the amended contract require Mr Blackwell to perform the renovation works to the standard of a habitable room?
(b) Were the renovation works not carried out in a proper or proficient manner or are faulty or unsatisfactory?
(c) If the renovation works are faulty or satisfactory, whether the Tribunal should make a building remedy order?
(d) If the answer is that the Tribunal should make a building remedy order with respect to the renovation works, what is the appropriate order including:
(i) Has Mr Booy suffered loss (rent and income)? If so, is Mr Booy to be compensated for that loss?
(b) renovate the rear enclosed patio to the standard of a bedroom which is a habitable room.
(a) construct a frame and then on that frame lay the decking boards that Mr Booy was to himself supply; and
(b) renovate the rear enclosed patio area to the standard of a habitable room, as he had told Mr Blackwell at the time he requested Mr Blackwell's quote that the enclosed patio area was to be used as a bedroom which he would then rent out for profit.
(1) The joints between the ceiling linings are not flush and so are defective. There are bubbles in the paintwork next to some of the joints between the ceiling sheets and these joints need to be prepared and repainted.
(3) The joints in the cornices are not well aligned or flush and were not sanded prior to painting and need to be prepared and repainted.
(4) The exposed underside of 'plate' timber secured to the face of the wall was planed, filled or sanded prior to being painted.
(5) The recessed edges of ceiling linings have not been flushed and sanded prior to painting and need to be prepared and repainted.
(6) Where paintwork on the ceiling has been touched up the variation in colour and texture of the paintwork is readily seen and needs to be prepared and repainted.
(7) The ceiling/cornice above the aluminium sliding door frame sags by 10 millimetres, and this will need to be adjusted.
(8) The joints between the ceiling linings and the plasterboard wall sheets were not proficiently flushed and sanded prior to the end wall being painted.
(9) Excess filler material has been applied to the edges of the timber window frame and was not removed prior to painting and will now need to be stripped back and redone.
(10) Excess screed material was not cleaned off the painted skirting at the west end of the room, which will now need to be broken off before being prepared and repainted.
(11) The screed applied to the slab floor is uneven and has broken up. This will need to be stripped back and professionally resurfaced.
(12) There is no flashing or damp-proof course material between the concrete floor and glass sliding door in the rear room.
(13) The concrete slab floor extends out well beyond the external wall which makes it impossible to waterproof the wall to floor junction.
(14) The verge capping at the east end of the roof is not adequately secured to the roof sheets.
(15) There are too few support battens for the length of the roof sheets for a habitable room.
(16) The gutter is too short for the length of the room which has been partly covered by an 'untidy piece of pressed metal', which will result in water running off the capping and down onto the pier at the eastern rear end brick wall.
(17) An acrylic texture coating was not applied to the top of the east wall which is therefore exposed to weather and to water run-off. It is necessary to remove and refit the downpipe and to eliminate gaps at the edges of the exposed timber beam.
(18) The timber support beam to the aluminium sliding door is exposed to the weather and should have been pre-painted prior to installation.
(19) An alternative outlet to the gutter needs to be installed so as to prevent overflow.
(20) The exposed edges of 'blue-board' sheets need to be covered and where needed trimmed back and covered.
(21) Electrical installation is incomplete e.g. there is no provision for a ceiling light and a junction box marked 'P1 LIVE' protrudes through the plasterboard wall lining at the east end of the room.
(1) The roof gutter on the rear room has been replaced but the replacement gutter is defective as it contains a dip which retains more than 10 millimetres of water contrary to AS 3600.3 and item 8.03 in the WA Guide to Standards and Tolerances and does not contain any overflow devices. It also does not match the profile of guttering on other areas of the home.
(2) The top of the pillar at the rear room has not been remedied in accordance with the BRO but it has been painted, which may be sufficient.
(3) [complaint withdrawn by Mr Booy, no action required]
(4) [complaint withdrawn by Mr Booy, no action required]
(5) The screed material has been removed from the concrete floor and this has exposed a portion of limestone footing, that is, there is a gap between the floor and interior wall of the room. The removal of the screed material has also exposed uneven surfaces on the floor up to 10 millimetres in height over a distance of 700 millimetres.
(6) The gap between the floor and glass sliding door has been unevenly filled with mortar and with a sealant which is not appropriate for outdoor use. This sealant has shrunk and there are now gaps which will allow water to enter the room. Flashing has not been installed. The concrete floor has been cut back but at an insufficient distance to allow water to properly drain. The 'blue-board' wall is in contact with the concrete floor, which is contrary to the manufacturers installation guide. The cutting of the concrete floor has exposed the steel reinforcing mesh which has clearly been placed at the bottom of the floor rather than in the top third of the floor, which significantly compromises the strength of the floor. Some portions of the mesh now protrude from the cut profile and these will over time rust and then transmit rust into the mesh inside the floor which will further compromise the floor. The profile of the cut floor also shows that the thickness of the floor varies between 90 millimetres and 50 millimetres whereas for a habitable building it should have a minimum thickness of 150 millimetres. We note here that Mr Chamberlain in his oral evidence stated that the thickness of a slab in a non-habitable building should also have a minimum thickness of 150 millimetres.
(7) Apart from paint left on the sliding door frame and material left on the skirting, the rear room has been repainted to a minimal acceptable standard. However, the cornice line above the sliding door is not in alignment.
(1) No further work has been done on the guttering and the replacement gutter remains defective.
(2) No further work has been done on the top of the pillar, but the works previously done may be sufficient.
(3) [complaint withdrawn by Mr Booy, no action required]
(4) [complaint withdrawn by Mr Booy, no action required]
(5) A durable surface has been placed on the concrete floor but the gap between the floor and interior wall of the room which shows an exposed limestone footing remains.
(6) Flashing has not been installed. A water test showed water ingress at each end of the sliding door frame. Blue-sheet remains in contact with the concrete floor, contrary to the manufacturer's recommendations, which is therefore ineffective in controlling condensation. The gaps in the sealant remain. The reinforcing mesh remains at the bottom of the concrete floor, some parts of the reinforcing mesh remain exposed, the exposed mesh is rusting and the thickness of the concrete floor remains inadequate. All these difficulties mean that the concrete slab should be taken up and replaced.
(7) The cornice is still not in alignment and paint has not been removed from the sliding door frame.
(8) [complaint withdrawn by Mr Booy, no action required].
(9) No further work has been done on the cracks in the driveway, but the works previously done may be sufficient.
(a) On 20 June 2024 Mr Booy lodged with Fremantle Magistrates Court an application for a violence restraining order against Mr Blackwell. This application was later withdrawn, apparently, after an apology was given by Mr Blackwell to Mr Booy;
(b) On 17 August 2024 Mr Booy emailed Mr Blackwell complaining about Mr Blackwell's conduct towards his tenants and warning that his tenants may pursue a restraining order against Mr Blackwell; and
(c) On 6 May 2024 Mr Booy's tenant emailed Mr Booy complaining that Mr Blackwell was 'hostile and argumentative' and that the tenants did not want him to ever return to the home.
Our conclusions as to the decking works and renovation works questions
(a) 'builder' means 'a person who carries on ... a business which consists of or includes the performing of home building work for others'; and
(b) 'home building work' means 'the whole or part of the work of ... constructing or carrying out any associated work in connection with ... an existing dwelling';
(a) the amended contract is a valid home building work contract which is binding on Mr Blackwell and Mr Booy;
(b) that Mr Blackwell is the builder of the decking works and is the builder of the renovation works under the amended contract;
(c) the amended contract price is $13,818.74, of which $9,018.74 remains outstanding;
(d) Mr Blackwell is in breach of the amended contract by not laying the decking boards and Mr Booy is also in breach of the amended contract by not paying the monies he is obliged to pay to Mr Blackwell under the contract for the decking works; and
(e) The renovation works performed by Mr Blackwell must be removed and replaced and almost all of the materials used will be destroyed in the process of removal, that the existing works and the materials are of no value to Mr Booy.
(a) Question: Is Mr Booy in breach of the amended contract by failing to pay all monies owed by him to Mr Blackwell and, if so, what amount should he pay? Answer: Yes, with respect to the decking works and no with respect to the renovation works.
(b) Question: Should the Tribunal make a HBWC order requiring Mr Booy to pay these monies to Mr Blackwell? Answer: Yes, with respect to the decking works in the amount of $2,093.48 and no with respect to the renovation works.
(c) Question: Is Mr Booy required to pay interest on any monies owed by him to Mr Blackwell? Answer: No.
(a) a building service carried out by a registered building service provider or an approved owner builder;
(b) home building work that is -
(i) carried out by a person for another person under a home building work contract or other contract or arrangement for gain or reward; and
(ii) not carried out for a person who is in turn obliged to perform the work under another contract; [and]
(c) any other service or work prescribed for the purposes of this definition[.]
(a) Question: Are decking works and the renovation works a 'regulated building service' under the BSCRA Act? Answer: Yes, both the decking works and the renovations works are a 'regulated building service'.
(b) Question: Were the decking works and the renovation works not carried out in a proper or proficient manner or are faulty or unsatisfactory? Answer: Yes, both the decking works and the renovations works were faulty or unsatisfactory. The decking works because the works were incomplete as the decking boards were not laid by Mr Blackwell and with respect to the renovation works, for the reasons set out in Mr Chamberlain's evidence, the slab floor installed by Mr Blackwell must be removed and replaced which will require the destruction of almost all of the other works performed by Mr Blackwell on that room, the majority of which were also faulty or unsatisfactory.
(c) Question: If the decking works or the renovation works are faulty or unsatisfactory, whether the Tribunal should make a building remedy order with respect to the decking works or renovation works? Answer: No with respect to the decking works, as the applicant is provided with a remedy equivalent to the remedy he is seeking in this proceeding in proceeding CC 8 of 2024. Yes, with respect to the renovation works as they require rectification in the manner recommended by Mr Chamberlain, which is the removal and replacement of the works.
(d) Question: If the answer is that the Tribunal should make a building remedy order with respect to the decking works or renovation works, what is the appropriate order? Answer: With respect to the renovation works, given the deep mutual hostility between the parties which makes it very likely that there will be conflict between the parties should Mr Blackwell return to the home to do building works, a monetary order that Mr Blackwell is to pay Mr Booy $20,000, being the cost of removing and replacing the works to the standard of an uninhabited room, is justified.
(e) Question: If a building remedy order should be made, has Mr Booy suffered loss (rent and income)? If so, is Mr Booy to be compensated for that loss? Answer: A building remedy order should be made, but for the reasons given above relating to our finding that the renovation works were not required to be performed to the standard of a habitable room, no order can or should be made compensating Mr Booy for loss of rent and income.
CC 10 0f 2024 - Alleged failure to comply with BRO 02023-27
(a) In CC 8 of 2024 Mr Booy is to pay Mr Blackwell $2,093.48;
(b) In CC 8 of 2024 Mr Blackwell is to repay Mr Booy $800; and
(c) In CC 9 of 2024 Mr Blackwell is to pay Mr Booy $20,000.
I certify that the preceding paragraph(s) comprise the reasons for decision of the State Administrative Tribunal.
[1] List of All Complaint Items lodged with Building Commissioner dated 5 January 2024.
[2] List of Complaint Items lodged with Building Commissioner dated 5 January 2024.
[3] List of All Complaint Items lodged with Building Commissioner dated 9 July 2024.
[5] Electricity Generation and Retail Corporation t/as Synergy v EIT Kwinana Partner Pty Ltd [2022] WASCA 3 [230].