[2019] WASC 248
General information, not legal advice.
Supreme Court of WA
2019-07-10
Smith J
Original judgment source is linked above.
Application for summary dismissal or strike out of counterclaim and result
(a) describes the sequencing of mining of iron ore mined from the mines (as defined) on the site and delivered to the OHP (ROM ore) during the term (as defined); and
(b) incorporates the key parameters for mining, including mining sequence plans, landform designs, access and haulage roads,
as amended by the Principal in accordance with the mining services contract.
(a) BGC was required by the mining services contract, and specifically, the Principal's Mine Plan, to crush ore in certain quantities and having certain metallurgical properties in each month of the 2017 calendar year;[4]
(b) BGC failed to meet the requirements as to quantity and metallurgical properties of the crushed ore in each month of the 2017 calendar year, as required by particular quarters of the 2017 Principal's Mine Plan, or alternatively, particular quarters of the 2016 Principal's Mine Plan;[5] and
(c) by reason of BGC's alleged failure to deliver the quantity and quality of crushed ore required, Cliffs suffered loss and damage. Cliffs pleads the particulars of the loss that is claimed as the loss of profit, or the opportunity to obtain a profit, from the sale of the additional quantity of crushed ore which it would have been able to sell but for the breaches by BGC of the mining services contract.[6]
Principles concerning an application for summary judgment
Order 16 r 1 RSC requires the Court to be satisfied either that the action is frivolous or vexatious, or that the defendant has a good defence on the merits, or that the action should be disposed of summarily.
The principles in relation to the determination of applications for summary judgment are well established. A party should not ordinarily be denied the opportunity to have his or her case determined following trial, and for that reason, the jurisdiction to grant summary judgment should be reserved for the clearest of cases, where there is a high degree of certainty about the ultimate outcome of the action if it were allowed to go to trial. In other words, the question is whether, on the material before the Court, it has been demonstrated that the plaintiff's action should not be permitted to proceed to trial because it is apparent that it must fail.
However, that does not mean that summary judgment will be given only where the case is so hopeless as not to require argument. Extensive argument may be necessary to demonstrate that a party's case is so clearly untenable that it cannot possibly succeed.
A defendant bringing a summary judgment application bears the legal onus of establishing that there is no serious question to be tried on any cause of action raised by the plaintiff. Under O 16 r 1(2), the defendant is required to file an affidavit verifying the facts upon which the application is based.
Pleadings and strike out application principles
A statement of claim must not plead allegations at too high a level of generality. A pleading must be sufficiently particular to conform with one of the primary objects of pleadings, to inform the opposing party of the case that it must meet. Whether it is sufficient to plead simply that one thing caused another, or whether further facts must be pleaded to establish a causal link, will depend on the pleaded facts and circumstances.
The caution with which a pleading will be struck out on the ground that it does not disclose a reasonable cause of action is well known.
Pleadings may be struck out on the ground that they may prejudice, embarrass or delay the fair trial of the action 'because they are evasive, they conceal or obscure the real questions in controversy, they are ambiguous or not reasonably intelligible, they raise immaterial or irrelevant issues, they fail to confine the issues or state the case of the party in question with reasonable particularity, or they raise a case in terms which are simply too general'.
The indemnities clause cl 24 of the mining services contract
Subject to the Contractor's right to recover Direct Costs, the Contractor indemnifies each Principal's Indemnified Party against, must hold each Principal's Indemnified Party harmless from, and must pay to each Principal's Indemnified Party on demand the amount of, any Loss or Claim paid, suffered or incurred by the Principal's Indemnified Party to the extent it arises directly or indirectly out of any act or omission of the Contractor or the Contractor's Personnel in providing or failing to provide the Mining Services, including any Loss or Claim arising from:
(a) any breach by the Contractor or the Contractor's Personnel of the Contractor's obligations under this document save to the extent the breach is caused or contributed to by the Principal's or any Principal's Indemnified Party's breach of the Principal's obligations under this document;
(b) any breach of any applicable Law, save to the extent the breach is caused or contributed to by the Principal or any Principal's Indemnified Party's breach of the Principal's obligations under this document;
(c) any Environmental Liability, save to the extent where the breach is caused or contributed to by the Principal or any Principal's Indemnified Party's breach of the Principal's obligations under this document;
(d) any OHS Liability;
(e) any damage to any property owned by or under the control of a Principal's Indemnified Party;
(f) any loss, damage or destruction of any records, files and materials provided to the Contractor or the Contractor's Personnel;
(g) the Contractor or any of the Contractor's Personnel acting outside the scope of its authority under this document;
(h) the provision of the Mining Services or any Intellectual Property owned or created by the Contractor infringing any Intellectual Property or other rights of any third party; or
(i) fraud, criminal conduct, breach of trust or fiduciary duty, bad faith, misrepresentation, negligence or wilful misconduct by the Contractor or any of the Contractor's Personnel.
The Principal indemnifies each Contractor's Indemnified Party against, must hold each Contractor's Indemnified Party harmless from, and must pay to each Contractor's Indemnified Party on demand the amount of any Loss or Claim arising out of:
(a) injury to or death of any of the Contractor's Personnel engaged in performing the Mining Services at the Site, paid, suffered or incurred by the Contractor's Indemnified Party to the extent it arises directly or indirectly out of any wilful misconduct or negligent act or omission of the Principal, the Principal's officers, employees, contractors (including Separate Contractors), agents and any other person authorised by the Principal under this document; or
(b) any Intellectual Property owned or created by the Principal infringing any Intellectual Property or other rights of any third party.
(a) is an additional, separate and independent obligation of the indemnifying party and no one indemnity limits the generality of any other indemnity; and
(b) applies whether the Loss arises in connection with negligence, misrepresentation, or other cause.
Neither party will be liable to the other party in any circumstances for any indirect, special or consequential loss or damage, including loss of revenue, loss of production, loss of product, loss or deferment of opportunity, loss or deferment of contract, loss of profit (whether direct, indirect, anticipated or otherwise, but such loss of profit does not include the Performance Fee), loss or reduction of goodwill, damage to reputation, howsoever arising and whether in an action in contract, tort (including without limitation, negligence), in equity, product liability, under statute, or on any other basis.
Are there contestable constructions of cl 24.6?
[T]his Court has reaffirmed the objective approach to be adopted in determining the rights and liabilities of parties to a contract. The meaning of the terms of a commercial contract is to be determined by what a reasonable businessperson would have understood those terms to mean. That approach is not unfamiliar. As reaffirmed, it will require consideration of the language used by the parties, the surrounding circumstances known to them and the commercial purpose or objects to be secured by the contract. Appreciation of the commercial purpose or objects is facilitated by an understanding 'of the genesis of the transaction, the background, the context [and] the market in which the parties are operating'. As Arden LJ observed in Re Golden Key Ltd, unless a contrary intention is indicated, a court is entitled to approach the task of giving a commercial contract a businesslike interpretation on the assumption 'that the parties ... intended to produce a commercial result'. A commercial contract is to be construed so as to avoid it 'making commercial nonsense or working commercial inconvenience'.
Also, the observations of Kiefel, Bell and Gordon JJ in Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd are pertinent:
'[The relevant clause] is to be construed by reference to the commercial purpose sought to be achieved by the terms of the lease. It follows, as was pointed out in the joint judgment in Electricity Generation Corporation v Woodside Energy Ltd, that the court is entitled to approach the task of construction of the clause on the basis that the parties intended to produce a commercial result, one which makes commercial sense. It goes without saying that this requires that the construction placed upon [the relevant clause] be consistent with the commercial object of the agreement. (footnotes omitted) (emphasis added)'
At each point where a constructional choice is available, it is important to consider what reasonable business people reading the relevant clause or agreement would understand it to mean.
Implication of a term in fact, by reference to what is necessary to give the contract business efficacy, is an exercise in construction, raising issues as to the meaning and effect of the contract, albeit not an orthodox instance of construction.
The observations of Barwick CJ in Upper Hunter are also important in approaching the proper construction of the Agreement:
'[A] contract of which there can be more than one possible meaning or which when construed can produce in its application more than one result is not therefore void for uncertainty. As long as it is capable of a meaning, it will ultimately bear that meaning which the courts, or in an appropriate case, an arbitrator, decides is its proper construction: and the court or arbitrator will decide its application. The question becomes one of construction, of ascertaining the intention of the parties, and of applying it. Lord Tomlin's words in this connexion in Hillas & Co Ltd v Arcos Ltd ought to be kept in mind. So long as the language employed by the parties, to use Lord Wright's words in Scammell (G) & Nephew Ltd v Ouston is not "so obscure and so incapable of any definite or precise meaning that the Court is unable to attribute to the parties any particular contractual intention", the contract cannot be held to be void or uncertain or meaningless. In the search for that intention, no narrow or pedantic approach is warranted, particularly in the case of commercial arrangements. Thus will uncertainty of meaning, as distinct from absence of meaning or of intention, be resolved. (footnotes omitted) (emphasis added)'
Similarly, in Meehan v Jones, Mason J said that the traditional doctrine of construction is that courts should be astute to adopt the construction which will preserve the validity of the contract.
Given the nature of the CITIC parties' contentions, we bear in mind the limits inherent in the process of construction. As Gageler and Keane JJ observed in Taylor v The Owners - Strata Plan No 11564, albeit in the context of statutory construction, construction involves expounding the meaning of the text, not remedying the parties' inattention. Like construction of a statute, construction of a contract is not repair.
(a) necessarily ignore the effect of cl 24.1 or have the effect of overriding cl 24.1; and
(b) necessarily requires for the words 'indirect, special or consequential loss or damage' to be ignored or to be regarded as having no effect.
I agree in the conclusion that sub-s (2) of s 24 exhaustively prescribes the ambit of the word 'security' for the purposes of the section. It is expressed as a statement of what the word 'security' in the section 'includes'. Unlike the verb 'means', 'includes' has no exclusive force of its own. It indicates that the whole of its object is within its subject, but not that its object is the whole of its subject. Whether its object is the whole of its subject is a question of the true construction of the entire provision in which the word appears. The well-known statement of Lord Watson in Dilworth v Commissioner of Stamps should not be taken so literally as to reduce the inquiry in a case like the present to an inquiry into the meaning of the word 'includes'. Strictly speaking, that word cannot be equivalent to 'means and includes'. But a provision in which it appears may or may not be enacted as a complete and therefore exclusive statement of what the subject expression includes. A provision which is of that character has the same effect as if 'means' had been the verb instead of 'includes'. The question whether a particular provision is exclusive although 'includes' is the only verb employed is therefore a question of the intention to be gathered from the provision as a whole.
(b) In Urica Library System BV v Sanderson Computers Pty Ltd [1997] NSWSC 454, Sheller JA (with whom Mason P and Meagher JA agreed), observed that the word 'including' can serve a number of different functions:
(i) one is to 'extend the meaning of the word defined beyond its ordinary meaning';
(ii) another is 'not merely to add to the natural significance of the word defined, but to afford an exhaustive explanation of the meanings to be attached to that word in the particular document'; and
(iii) a third might be 'not so much to extend the ordinary meaning of the defined term as to specify as falling within the definition that which might otherwise have been in doubt.
(a) The term 'including' is used in cl 24.6 to both extend (where necessary) the meaning of 'indirect, special or consequential loss and damage' to include each of the defined losses and damage[54] and to specify and remove any doubt that each of those defined losses or damage falls within the definition of 'indirect, special or consequential loss or damage'. In either event, loss of profit and anticipated profits are excluded.
(b) To construe the word 'including' in cl 24.6 in the manner articulated above removes any socalled 'tension' (real or imagined) within the clause, and gives meaning to both the list of defined losses (which would be redundant otherwise), and to the words in parenthesis 'whether direct, indirect, anticipated or otherwise' by which the parties were at pains to put it beyond doubt that the excluded 'loss of profit' extends to loss of profit of any kind other than BGC's Performance Fee.
(c) If the word 'including' was to be construed in such an unusual manner as to confine the objects in cl 24.6 (ie each of the defined losses and damage, including loss of profit) to those falling within the subject ('indirect, special or consequential loss or damage') such that only loss or damage answering the description of 'indirect, special or consequential loss' was excluded, it would:
(i) be contrary to cl 1.2(b)(v) of the mining services contract; and
(ii) also tend to render both the defined losses themselves, and the words in parenthesis after 'loss of profit', a nullity and of no effect,
and so it cannot reasonably be suggested that this is the proper construction of cl 24.6 or that this was the objective intention of the parties.
In H & E Van Der Sterren v Cibernetics (Holdings) Pty Ltd Walsh J said:
'The terms of exception clauses must sometimes be read down if they cannot be applied literally without creating an absurdity or defeating the main object of the contract ... But such a modification by implication of the language which the parties have used in an exception clause is not to be made unless it is necessary to give effect to what the parties must be understood to have intended.'
The construction of a clause limiting liability depends on the language used, read in context, and not on assumptions that particular events were not to be protected. The exclusion of liability may still apply even where those events may defeat the main object of the contract.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
Research Associate/Orderly to the Honourable Justice Smith
[1] Cliffs' amended counterclaim, filed 17 May 2019 [1].
[2] Cliffs' amended counterclaim, filed 17 May 2019 [2(a)].
[3] Cliffs' amended counterclaim, filed 17 May 2019 [2(j)].
[4] Cliffs' amended counterclaim, filed 17 May 2019 [6] - [12]; see generally, the requirements pleaded by Cliffs in its amended defence, filed 3 May 2019 [4] - [12].
[5] Cliffs' amended counterclaim, filed 17 May 2019 [13].
[6] Cliffs' amended counterclaim, filed 17 May 2019 [14].
[7] Cliffs' amended counterclaim, filed 17 May 2019 [15].
[9] Gerovich v Gerovich [2018] WASC 153 [26] [29] (citations omitted).
[10] EDWF Holdings 1 Pty Ltd v EDWF Holdings 2 Pty Ltd [2010] WASCA 78; (2010) 41 WAR 23 [124] (Buss JA; Owen & Newnes JJA agreeing); Great Southern Finance Pty Ltd (in liq) v Rhodes [2014] WASC 431 [28] (Beech J); Betfair Pty Ltd v Racing New South Wales [2010] FCAFC 133; (2010) 273 ALR 664 [49] (Keane CJ, Lander & Buchanan JJ).
[11] DM Drainage & Constructions Pty Ltd v Karara Mining Ltd [2014] WASC 170 [32] - [34].
[12] Great Southern Finance Pty Ltd (in liq) v Rhodes [2014] WASC 431 [26] (Beech J); applying Batistatos v Roads and Traffic Authority of New South Wales [2006] HCA 27; (2006) 226 CLR 256 [46] (Gleeson CJ, Gummow, Hayne & Crennan JJ); Agar v Hyde [2000] HCA 41; (2000) 201 CLR 552 [57] (Gaudron, McHugh, Gummow & Hayne JJ).
[13] Great Southern Finance Pty Ltd (in liq) v Rhodes [2014] WASC 431 [26] (Beech J).
[14] Moran v Atrum Coal NL [No 5] [2016] WASC 23 [11] - [13] (Mitchell J).
[15] Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640 [35] (French CJ, Hayne, Crennan & Kiefel JJ).
[16] Sino Iron Pty Ltd v Mineralogy Pty Ltd [2019] WASCA 80 [296] (Buss P, Murphy & Beech JJA); Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 256 CLR 104 [46] - [52] (French CJ, Nettle & Gordon JJ); Simic v New South Wales Land and Housing Corporation [2016] HCA 47; (2016) 260 CLR 85 [79] (Gageler, Nettle & Gordon JJ).
[17] Sino Iron Pty Ltd v Mineralogy Pty Ltd [2019] WASCA 80 [297] [302].
[18] BGC's outline of submissions in support of its application, filed 1 April 2019 [18].
[19] BGC's outline of submissions in support of its application, filed 1 April 2019 [19].
[20] BGC's outline of submissions in support of its application, filed 1 April 2019 [20].
[21] BGC's outline of submissions in reply, filed 6 May 2019 [10(e)].
[22] BGC's outline of submissions in support of its application, filed 1 April 2019 [15] [16].
[23] BGC's outline of submissions in support of its application, filed 1 April 2019 [17]; citing Transocean Drilling UK Ltd v Providence Resources Plc [2016] EWCA Civ 372; [2016] 1 CLC 585 [24] (Moore-Bick LJ; MacFarlane & Briggs LJJ agreeing).
[24] Patersons Securities Ltd v Financial Ombudsman Service Ltd [2015] WASC 321 [127] (Mitchell J); applying Kenneth Martin J's observations in Regional Power Corporation v Pacific Hydro Group Two Pty Ltd [No 2] [2013] WASC 356; (2013) 46 WAR 281 [88] [89].
[25] Patersons Securities Ltd v Financial Ombudsman Service Ltd [2015] WASC 321 [125].
[26] Patersons Securities Ltd v Financial Ombudsman Service Ltd [2015] WASC 321 [126]; his Honour gives the example of where the relevant contractual obligation is to secure a minimum net rental return, the failure to deliver such a return would then produce a 'normal loss' which any plaintiff having the benefit of that contractual promise would suffer.
[27] BGC's outline of submissions in support of its application, filed 1 April 2019 [21].
[28] BGC's outline of submissions in support of its application, filed 1 April 2019 [23].
[29] BGC's outline of submissions in support of its application, filed 1 April 2019 [24].
[30] BGC's outline of submissions in support of its application, filed 1 April 2019 [25].
[33] Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [14].
[34] Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [15].
[35] Cliffs state that whether the 'Performance Fee' is profit will be in issue at trial.
[36] Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [17].
[37] Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [18]; citing Suisse Atlantique Societe d'Armement Maritime SA v NV Rotterdamsche Kolen Centrale [1967] 1 AC 361, 432 (Lord Wilberforce). However, if the words are clear and fairly susceptible to only one meaning that may be the effect of such a clause; noting the discussion in Transocean Drilling UK Ltd v Providence Resources Plc [2016] EWCA CIV 372; [2016] 1 CLC 585 [25] [31] (Moore-Bick LJ; MacFarlane & Briggs LJJ agreeing).
[38] Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [19].
[39] Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [20].
[40] Regional Power Corporation v Pacific Hydro Group Two Pty Ltd [No 2] [2013] WASC 356; (2013) 46 WAR 281 [88]-[96] (Kenneth Martin J); SMEC Australia Pty Ltd v Valentine Falls Estate Pty Ltd [2011] WASCA 138 [23] (Pullin, Newnes & Murphy JJA).
[41] Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [21].
[42] Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [22].
[43] Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [22].
[44] Cliffs' amended counterclaim, filed 17 May 2019 [14(a)]; Cliffs' submissions in opposition to BGC's application, filed 18 April 2019 [23].
[47] BGC's outline of submissions in reply, filed 6 May 2019 [12].
[49] Sherritt Gordon Mines Ltd v Federal Commissioner of Taxation [1977] VicRp 42; [1977] VR 342; (1976) 10 ALR 441, 353 (McInerney J) (a statute case); applied in Hagipantelis v Legal Services Commissioner of New South Wales [2010] NSWCA 79; (2010) 78 NSWLR 82 [20] (Spigelman CJ; Allsop P & Handley AJA agreeing).
[50] YZ Finance Co Pty Ltd v Cummings [1964] HCA 12; (1964) 109 CLR 395.
[51] YZ Finance Co Pty Ltd v Cummings [1964] HCA 12; (1964) 109 CLR 395, 401 402.
[52] Credit Suisse AG, Sydney Branch v Springsure Property Holdings Pty Ltd (in liq) [2017] QSC 142 [35].
[53] BGC's outline of submissions in reply, filed on 12 June 2019 [11].
[54] Being 'loss of revenue, loss of production, loss of product, loss or deferment of opportunity, loss or deferment of contract, loss of profit etc ... '.
[55] BGC's outline of submissions in reply, filed 14 June 2019 [12].
[56] AGC Industries Pty Ltd v Karara Mining Ltd [2019] WASC 140 [326] - [327]; applying Nissho Iwai Australia Ltd v Malaysian International Shipping Corporation, Berhad [1989] HCA 32; (1989) 167 CLR 219, 226 227; H & E Van Der Sterren v Cibernetics (Holdings) Pty Ltd (1970) 44 ALJR 157, 158 (Barwick CJ & Kitto J agreeing) (citations omitted).
(1970) 44 ALJR 157
(2000) 201 CLR 552
(2014) 251 CLR 640
(2015) 256 CLR 104
(2013) 46 WAR 281
(1976) 10 ALR 441
(2010) 78 NSWLR 82
(2010) 41 WAR 23
(2010) 273 ALR 664
(2006) 226 CLR 256
(2016) 260 CLR 85
(1964) 109 CLR 395
(1989) 167 CLR 219