[2018] VCAT 1242
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2018-09-12
Original judgment source is linked above.
For the reasons set out at paragraph 121 below, I accepted Mr Turnbull's file note into evidence and I accept that it is a true record of the conversation.
Report: An inspection of the above property revealed that the building work is not in compliance with the provisions of the Act, Regulations, BCA and/or Australian Standards as are relevant to the approved Building Permit documents. The following works are required to be carried out and notification given to this office to arrange a reinspection of the prescribed mandatory notification stage..."
The following items are not directly related to the framing of the dwelling, although these matters were observed on site and require attention:
- Provide amended Architectural drawings reflecting all as built changes i.e. additional/omitted windows, window sizes, dining room setbacks, garage wall heights etc.
- ...[items referring to blockwork issues]"
The first MBS Inspection Report "Approved - subject to" - 16 April
Inspection Item: Inspection of Structural Framework (re-framework)
Report: An inspection of the above property revealed that the building work is generally in compliance with the provisions of the Act, Regulations, BCA and/or Australian Standards as are relevant to the approved Building Permit documents.
The following items are not directly related to the Structural framing of the dwelling, although these matters were observed on site and require attention ...
The second MBS Inspection Report "Approved - subject to" - 17 April
The third MBS Inspection Report "Approved - subject to" - 22 April
"An inspection was carried out on site where it was found that excavations had been carried out. The excavations, reinforcement, et cetera, and whatever else was looked at at the time was found to be satisfactory from a structural point of view. There were changes noted on site. The building inspector was happy with what he saw on site but required the submission of amended structural drawings and certificates of compliance to verify the changes. "Approved subject to" was often used. It's not a practice employed by my office any longer. It was approved where construction or an aspect or a component of the building on site was found to be satisfactory and, generally, the "subject to" items tend to be either administrative or a document type of scenario where there is not the need to revisit site to carry out a further inspection."[11]
"The "subject to" issue - and in this instance the amended structural drawings - remains a live issue which is monitored through the construction phase. Eventually, if these documents aren't forthcoming then they are raised at final inspection stage and the "subject to" item needs to be satisfied before we will issue any final inspection or certificate of occupancy."[12]
Discussion and conclusion on the frame stage approval
"As to the introductory words ['subject to'], the section should first be construed without them, and then, if there is anything in the other provisions of the Act inconsistent with the interpretation so arrived at, these other provisions must yield"[17].
Is claiming the frame stage progress claim necessarily repudiatory conduct?
Did the owners instruct the builder to depart from the contractual requirement for a frame approval?
(2) A builder must not demand or recover or retain under a major domestic building contract of a type listed in column 1 of the Table more than the percentage of the contract price listed in column 2 at the completion of a stage referred to in column 3....
(4) Subsections (2) and (3) do not apply if the parties to a contract agree that it is not to apply and do so in the manner set out in the regulations.
"...non-compliance [with section 40(4) of the DBCA] means that, pursuant to s 40(2), [the builder] was not entitled to demand, recover, or retain more than the percentage of the contract price specified in the prescribed payments regime ... [The builder] remains entitled to the sequence of payments specified in the prescribed payments regime under s 40(2) of the Act, insofar as the stages of construction identified under the Act were completed... [T]he progress payments revert to the statutory regime as expressed schematically in the Contract in Method 1."
I find that the builder was not entitled to claim the payment of the frame stage in December 2014, nor to maintain that claim throughout 2015. As a result, I am satisfied that its conduct in so doing was repudiatory.
Was the builder entitled to claim the Lock-Up Progress Claim?
"82. The failure of the builders to install either the roller doors specified in the plans, or temporary doors, left the home in a state where its external doors were not fixed. The dwelling did not satisfy the definition of 'lock-up stage'...
Was the builder entitled to suspend the works?
"You, the Owner(s) have failed to make a Progress Payment that is due within 14 days after it became due. The Progress Payment you have failed to make is Progress Claim Certificate for: Frame Stage".
"[The builder's] suspension of the works, in response to the owners' refusal to pay for lock-up stage, was thus in breach of the contract. The owners were correct to accept the suspension of the works, in the circumstances, as a repudiation of the contract and were entitled at common law to bring the contract to an end."
Was the builder entitled to refuse the owners and their experts access to site to inspect the works?
"as we have advised you many time before, the building site is a very dangerous site. Please no person or owners or public or visitors are allowed to enter the building site... without a written permission from [the builder]. No entry to the site without our supervision".
Did the builder make improper demands for money and/or refuse to build in accordance with the approved drawings?
Does the nature and extent of defective work amount to a repudiation or serious breach of the contract?
"can't do much inside because the owner didn't give me dimension to get which kitchen, which front door. There's no response about all the email I sent for any item. I send about five email requesting meeting, requesting item essential for me to start work on site and she say you will get another inspection. I get email. I receive email saying you get another inspection in March, which is from VBA, and don't do anything until inspection. I waiting and when I get Mr (indistinct) here and I waiting for a report. I get a report back at the same day I go oversea. When I come back there's no access for me"[24]
Did the builder's letter of 31 August 2015 amount to a repudiation?
B: DID THE OWNERS ELECT TO CONTINUE THE CONTRACT?
"... Pursuant to the Surveyor's Notice the Frame stage is not in compliance with the provisions of the Act, regulations, BCA and/or Australian Standards as are relevant to the approved Building Permit documents and therefore the Frame Stage is not complete. Further, as Frame stage is incomplete Lockup stage is also not complete....
Our clients demand that you refund all monies paid for the Frame and Lockup stages in the sum of $423,225 within 7 days... Should you fail to pay the said monies... we are instructed to immediately issue proceedings in the [VCAT]...
This letter in no way forms any repudiation of Contract on the part of our clients but merely requires you to comply with your obligations pursuant to the Act and the Building Contract. We note that as a result of you failing to allow our clients access to the property we have not been able to obtain an expert's report... Unless you allow our client's expert access to the property... we shall proceed to file an application with VCAT to obtain access..."
"The doctrine of election between two inconsistent legal rights is well-established but certain of its features are not without their obscurities. The doctrine only applies if the rights are inconsistent the one with the other and it is this concurrent existence of inconsistent sets of rights which explains the doctrine...
For the doctrine to operate there must be both an element of knowledge on the part of the elector and words or conduct sufficient to amount to the making of an election between the two inconsistent rights which he possesses..."
"...a binding election to affirm a contract may be made by a person who then has knowledge of the facts giving rise to a right of rescission, though unaware of the existence of the right of rescission, and that unequivocal conduct affirming the contract will in such circumstances preclude the exercise of the right of rescission."
"A promisor's repudiation of obligation continues to operate as such - and remains available as a basis for an election to terminate the contract - until it has been withdrawn, or the promisee elects to continue with the contract. Accordingly, if a promisor repudiates the contract, but the promisee elects against termination, the promisee is entitled to terminate the contract if the promisor nevertheless continues to repudiate.
The position is the same if the promisor repudiates the contract on a subsequent occasion, following the promisee's election to continue performance. The promise obtains a fresh right to terminate unless what is put forward is an effective exercise of a right to terminate enjoyed by the promisor against the promise."
(2) Missing control joints and movement gaps $1,782
(3) Bricks used as subfloor bearer supports $1,114
(6) No silicone to plumbing hot cold pipes through frame $535
(7) Wall blocks not fully nailed or fitted $594
(10) Heat/air conditioning voids not fitted $683
(12) Roof over first-floor balcony not per plan $2,836
(14) Windows missing study and storerooms - supply and install or credit to O $3,742
(15) Incorrect window sizing (20) - replace all windows $40,986
"I think the following principles concerning the assessment of damages for the breach by a builder of a domestic building contract can be spelled out from the cases referred to:
Where the work and materials are not in conformity with the contract, the prima facie measure of damages is the amount required to rectify the defects complained of and so give to the owner the equivalent of a building which is substantially in accordance with the contract (Bellgrove v Eldridge[33]);
Quite obviously, this list is by no means exhaustive. Other matters might be relevant according to the facts of the particular case. For example, the innocent party might have elected to accept the non-conforming work, whether by taking the benefit of it or otherwise; the owner might have waived the breach or so acted after becoming aware of the breach as to create an estoppel or to make rectification impracticable. There might also be many circumstances in which it could be argued that an award of rectification cost would give the innocent party an uncovenanted profit (Radford v De Froberville[36]."
(16) Window 39 faulty - service and replace winders $683
(17) Alfresco whaler plate not per plan $3,712
(20) Subfloor access door not closing and jamming $89
(22) Electricity meter located on council land $2,495
(27) Timber retaining wall leaning and no permit $3,088
(29) As-built dimensions vary from plans $668
(30) Excavation to study and store room not completed
(31) Subfloor ventilation incorrectly positioned and partially blocked $1,217
(33) Timber under box gutter in garage $1,485
(37) Curved bulkhead framework over kitchen needs battens $238
(38) Window head trimmers not fully nailed $386
(40) Rear retaining wall steel constructed without a permit or inspection $1,900
(41) Pergola foundation not inspected by RBS $1,900
(42) Foundation west boundary retaining wall $1,900
(43) Render repairs including scaffold $43,970
(44) Remove foam cladding and reconstruct with brickwork $23,091
Section 37 - variation by builder
Section 38 - variation by owner
Both sections 37 and 38
Variation for footing to the retaining wall - $9,750
Sleeper retaining wall between no.41 and no.43 - $8,810
Change to wall from foam to brickwork - $22,534
Work and labour carried out at no.43 - $7,645
"10. ... There is no guidance in the Act as to the circumstances in which such damages should be awarded, apart from s.53(1) which indicates that it must be "fair" to do so.
"Interest is awarded to compensate the aggrieved party for having been deprived of the amount awarded from the date that it should have been paid until the date of judgement."
[1] Mrs B' witness statement paragraph 16; Mr Bishara witness statement paragraphs 13 and 14
[4] Builder's closing submission paragraph 4
[5] As a variation to the building contract, the builder performed some works at no.43, which are part of the variation claims considered at Part H below
[7] Progressive Mailing House Pty Ltd v Tabali Pty Ltd [1985] HCA 14; (1985) 157 CLR 17 at 33, 40
[8] Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007] HCA 61; (2007) 233 CLR 115 t [44]
[9] Shevill v Builders Licensing Board ([1982] HCA 47; 1982) 149 CLR 620 and Cheshire & Fifoot at p.1108
[13] Including s 33, s 34 Building Act; reg.901 Building Regulations 2006; reg.167 Building Regulations 2018
[16] Which has since been replaced by s.37F of the Building Act and reg.175 of the Building Regulations 2018, which are even more prescriptive
[17] Re Bland Bros and the Council of the Borough of Inglewood (No.2) [1920] ArgusLawRp 103; [1920] VLR 522 at 533
[18] Sweet & Maxwell v Universal News Services Ltd [1964] 2 QB 699 at p. 734 and cases referred to in the builder's closing submission at paragraph 50
[20] reg.13 DBC Regulations 2017 and reg.12 DBC Regulations 2007
[23] [1931] HCA 21; (1931) 45 CLR 359 at 377-8
[25] Builder's closing submission paragraphs 24-29 and the cases cited therein
[26] (1974) 131 CLR 634 per Stephen J (with whom McTiernan ACJ agreed) at 641-2
[27] [1974] HCA 41; (1974) 131 CLR 660 at 670
[28] Carter's Breach of Contract, LexisNexis Butterworths 2011 at [11-61]
[31] Which is a recognised cost estimator used in the building industry
[36] [1977] 1 WLR 1262 per Oliver J
[38] Points of defence and counterclaim paragraph 11 and 45
[43] In its Closing Submission, the builder reduced the amount of the claim from $24,860 to $18,323.75 to account for double counting
[46] Per Owners' closing submission at paragraph 232 - "the amount that would have been payable to the builder" - which does not appear to include the amounts of the disputed variations.
Barbour
Australian Elegant Homes Pty Ltd
(1974) 131 CLR 660
(1954) 90 CLR 613
(2009) 83 ALJR 390
(2012) 35 VR 538
(1931) 45 CLR 359
(1985) 157 CLR 17
(2007) 233 CLR 115
(1974) 131 CLR 634