DOMESTIC BUILDING DISPUTE - Termination of contract; whether exercise of a contractual right to terminate was effective; Repudiation of contract - whether ineffective contractual termination constitutes a repudiation of the contract - whether defective works constitutes a repudiation of the contract; Damages - whether cost to rectify defects should be calculated on the basis of what it would cost an owner to rectify or alternatively what it would cost the builder to rectify - contractual damages distinguished from quantum meruit claim.
Australian Dream Homes Pty Ltd v Stojanovski (Building and Property)
Plus interest accrued on the Owner's loan calculated from 7 August 2012:
Lock up Stage - means when the homes external wall cladding and roof covering is fixed, the flooring is laid and external doors and external windows are fixed (even if those doors or windows are only temporary).[1]
Moreover, it is unlikely that the expression 'lock-up stage', as chosen by Parliament under s 40, and as adopted by the parties to the contract, is no more than a label; the very expression conveys the achievement of some degree of security. Indeed, the reference in the definition of 'lock-up stage' to 'temporary doors or windows' suggests that there may be a need for interim works to be done for the purpose of ensuring that the home is completely enclosed. This suggests that some minor temporary construction may indeed be required beyond the specifications in the plans. While the definition does not make reference to temporary external wall cladding, it remains the case that the cladding had to be fixed in some form over the entire wall between the master suite in the garage, from the foundations to the roof, before lock-up stage was completed.[3]
the Owner may give written notice by registered post to the Builder:
[77] Neither party made any submissions as to what sort of a breach or breaches would constitute alone or singly a substantial breach. The word substantial is protean and quite ambiguous. It refers to a concept which one might think is pre-eminently in the eye of the beholder. Building defects which may seem very serious and very annoying to a proprietor may seem to a builder to be matters of relative triviality. One of the best known and most frequently quoted expositions of what the word 'substantial' means is to be found in the judgment of Deane J, then a judge of the Federal Court of Australia, in the context of Section 45D of the Trade Practices Act 1974 which prohibited secondary boycotts which would have the effect of causing substantial loss or damage to a third person. His Honour's exposition was as follows:
The word 'substantial' is not only susceptible of ambiguity: it is a word calculated to conceal a lack of precision. In the phrase 'substantial loss or damage', it can, in an appropriate context, mean real or of substance as distinct from ephemeral or nominal. It can also mean large, weighty or big. It can be used in a relative sense or can indicate an absolute significance, quantity or size. The difficulties and uncertainties which the use of the word is liable to cause are well illustrated by the guidance given by Viscount Simon in Palser v. Grinling ([1948] 1 All ER 1 at 11; [1948] AC 291 at 317) where, after holding that, in the context there under consideration, the meaning of the word was equivalent to 'considerable, solid or big', he said: 'Applying the word in this sense, it must be left to the discretion of the judge of fact to decide as best he can according to the circumstances of each case ...' (See also Terry's Motors Ltd. v. Rinder [1948] SR (SA) 167 at 180 and Granada Theatres Ltd. v. Freehold Investment (Leytonstone) Ltd. [1958] 1 WLR 845 at 848). In the context of s.45D(1) of the Act, the word 'substantial' is used in a relative sense in that, regardless of whether it means large or weighty on the one hand or real or of substance as distinct from ephemeral or nominal on the other, it would be necessary to know something of the nature and scope of the relevant business before one could say that particular actual or potential loss or damage was substantial. As at present advised, I incline to the view that the phrase, substantial loss or damage, in s.45D(1) includes loss or damage that is, in the circumstances, real or of substance and not insubstantial or nominal. It is, however, unnecessary that I form or express any concluded view in that regard since the ultimate conclusion which I have reached is the same regardless of which of the alternative meanings to which reference has been made is given to the word 'substantial' in s.45D(1). Tillmanns Butcheries Pty Ltd v Australasian Meat Industry Employees' Union [1979] FCA 85; (1979) 27 ALR 367, 382.
[78] His Honour's analysis refers to a number of interpretations which have been applied to the word substantial over the years in different contexts. In broad terms the two strands of meaning are on the one hand 'of substance as distinct from ephemeral or nominal'. If applied in the present context this would mean that any breach going beyond the de minimis would be a substantial breach. The view which I think was espoused by Mr Gurr, counsel for the Serongs and the view adopted by Viscount Simon in the case referred to by Deane J in the passage quoted above, namely 'considerable, solid or big' in the context of a building contract would mean that only really important breaches would count. In my view, in the context of a building contract, the latter meaning is the one which should be given to the word 'substantial' or the phrase 'substantial breach'.
[79] Experience sitting in the Domestic Building List and a reading of judgments in building disputes demonstrates that building is a complex process and this complexity and human frailty mean that defects in a structure are common and sometimes, at least on a temporary basis, unavoidable. The evidence before me in this case was for instance that the existence of defects in a building frame would not render it inappropriate for a builder to claim payment for the frame stage. Given that it is difficult to avoid some defects and that the process of rectification may take some time it seems inherently unlikely that a standard form building contract prepared by a builders' association (The Master Builders' Association of Victoria) would intend to leave a builder at risk of contract cancellation for failure to rectify within 14 days of a notice any defect which was more than ephemeral or de minimis.
We refer to the above matter and to your letter of even date enclosing the Notice of Intention to Terminate the Contract with the report of Mr David Cheong dated 5 April, 2012.
It is unfortunate that your client has taken this stance given that to date our client has been at the site on almost a daily basis and has had regular weekly meetings with your client and daughter. One would have thought it appropriate to have first provided our client with Mr Cheong's report and then affording him a reasonable period of time to consider it and respond before serving a Notice of Intention to Terminate. In any event our client will respond within the limited timeframe provided.
We shall today refer the report to our client's building consultant and we will provide you with a response within the 14 day period.
We refer to the above matter and advise that we have engaged the services of Building Surveying Services to prepare a response to the Building Report prepared by Mr David Cheong...
... The defects outlined in your client's building report are not admitted and we are currently arranging for our client's expert to view the works and we shall provide you with our report shortly...
My client (the Builder) has engaged BSS to carry out a report (Mr Ian Johnson).
Mr Johnson would like access to the site for inspection on Friday, 11 May 2012. Is this acceptable?
Further to my email to you of yesterday regarding access to the site for Mr Ian Johnson BSS to inspect.
The suggested date was Friday next week, i.e. 11 May.
Please note that, as the building contract is still on foot, and the Builder obviously still has access to the land in any event to progress the works, our client and his expert will just assume that the request for access for the consultant is accepted and will proceed on 11 May.
20.1 Owners right to serve notice of intention to terminate contract
the Owner may give written notice by registered post to the Builder:
20.2 If builder fails to remedy breach owner may terminate contract
If the Builder fails to remedy the breach or breaches of this Contract as stated in any notice served by the Owner under Clause 20.1 THEN the Owner may, without prejudice to any other rights or remedies, give further written notice by registered post to the Builder immediately terminating this Contract.
20.3 Owner may not terminate contract in certain circumstances
The Owner may not terminate this Contract unreasonably or vexatiously or if the Owner is in substantial breach of this Contract.
It is trite law that the primary duty of a court in construing a written contract is to endeavour to discover the intention of the parties from the words of the instrument in which the contract is embodied. Of course the whole of the instrument has to be considered, since the meaning of any one part of it may be revealed by other parts, and the words of every clause must if possible be construed so as to render them all harmonious one with another. If the words used are unambiguous the court must give effect to them, notwithstanding that the result may appear capricious or unreasonable, and notwithstanding that it may be guessed or suspected that the parties intended something different. The court has no power to remake or amend the contract for the purpose of avoiding a result which is considered to be inconvenient or unjust. On the other hand, if the language is open to two constructions, that will be preferred which will avoid consequences which appear to be capricious, unreasonable, inconvenient or unjust, 'even though the construction adopted is not the most obvious, or the most grammatically accurate', to use the words from earlier authority cited in Locke v Dunlop, which, although spoken in relation to a will, are applicable to the construction of written agreements generally; see also Bottomley's Case. Further, it will be permissible to depart from the ordinary meaning of the words of one provision so far as is necessary to avoid an inconsistency between the provision and the rest of the instrument.[6]
My starting point is that parties to a contract are free to agree upon any terms which they consider appropriate, including a term requiring one of the parties to do the impossible, although it would be highly unusual the parties knowingly so to agree. If they do so agree and if, as is inevitable, he fails to perform, he will be liable in damages. That said, any court will hesitate for a long time before holding that, as a matter of construction, the parties have contracted for the impossible, particularly in a commercial contract. Parties to such contracts can be expected to contemplate performance, not breach.
Gibbs CJ in Sheville & Anor v The Builders Licensing Board likewise observed that a contract may be repudiated where one party renounces their liabilities under it, evincing any intention to no longer be bound by the contract. His Honour further observed that repudiation may also occur when one party demonstrates an intention to fulfil the contract, but in a manner "substantially inconsistent with his [or her] obligations and not in any other way..." The conduct of the allegedly repudiatory party must be "such as to convey to a reasonable person, in a situation of the other party, repudiation or disavowal either of the contract as a whole or on a fundamental obligation under it".[9]
For the respondents it was submitted that such an intention should be inferred from the appellant's continued adherence to an incorrect interpretation of the contract. It was urged that the appellant, because it was acting on an erroneous view, was not willing to perform the contract according to its terms. No doubt there are cases in which a party, by insisting on an incorrect interpretation of a contract, evinces an intention that he will not perform the contract according to its terms. But there are other cases in which a party, though asserting a wrong view of the contract because he believes it to be correct, is willing to perform the contract according to its tenor. He may be willing to recognise his heresy once the true doctrine is enunciated or may be willing to accept an authoritative exposition of the correct interpretation...
In this case the appellant acted on its view of the contract without realising that the respondents were insisting upon a different view until such time as they purported to rescind. It was not the case in which any attempt was made to persuade the appellant of the error of its ways or indeed give it any opportunity to reconsider its position in light of an assertion of the contract. There is therefore no basis on which one can infer that the appellant was persisting in its interpretation willy nilly in the face of a clear enunciation of the true agreement.[14]
... - he is entitled to damages for loss of bargain (expectation loss) and damages suffered including expenditure incurred in reliance on the contract (reliance interest).[17]
The cost of employing a third party repairer is likely to be higher than the cost to the contractor of doing the work himself would have been. So the right to return in order to repair the defect is valuable to him. The question arises whether, if he is denied that right, the employer is entitled to employ another party and to recover the full cost of doing so as damages for the contractors original breach.
In my judgment, the contractor is not liable for the full cost of repairs in those circumstances. The employer cannot recover more than the amount which it would have cost the contractor himself to remedy the defects. Thus, the employer's failure to comply with clause 2.5, whether by refusing to allow the contractor to carry out the repair or by failing to give notice of the defects, limits the amount of damages which he is entitled to recover. This result is achieved as a matter of legal analysis by permitting the contractor to set off against the employers damages claimed the amount by which he, the contractor, has been disadvantaged by not being able or permitted to carry out the repairs himself, or more simply, by reference to the employers duty to mitigate his loss.[22]
[21] ... It is because the quantum meruit remedy rests on the fiction of the contract's having ceased to exist ab initio that the contract can have no 'continuing influence' when the value of the work is being assessed on a quantum meruit. It is because this alternative remedy does ignore the bargain which the parties struck, and does ignore the rights accrued under the contract up to the date of termination, that the availability of quantum meruit in the alternative is now seen as anomalous. But, for reasons we have already given, those incongruities are as entrenched as the remedy itself. It is true that the contract price is relevant on a quantum meruit, but not because of any 'continuing influence' of the contract. The price is merely a piece of evidence, showing what value the parties attributed - at a particular time - to the work which the builder was agreeing to perform.[23]
In my opinion, benefit in this context must be seen from the perspective of the recipient who is, after all, the person to be charged. It may be that for some idiosyncratic reason the defendant seeks the performance of work which another would see as without benefit or, indeed, as a positive dis-benefit. Examples of these are given by Goff J in B.P. Exploration Co (Libya) Ltd v Hunt (No.2) [1979] 1 WLR 783, at p. 803. But where a person requests another to do something, it is not unreasonable for the law to conclude that the former sees some benefit in its performance, however wrong this view may be on an objective basis and for the law to act upon the perception of the recipient. [24]
[25] The proper approach to assessment of a quantum meruit claim is, as the trial judge said, to ascertain the fair and reasonable value of the work performed. Axiomatically, the measure of the restitutionary remedy is the value of the benefit conferred on the party which received it.
Brickwork (Items 1, 2, 3, 6, 7, 9, 10, 11 and 19)
Gutters and fascias embedded in brickwork (Item 8)
Roof and eaves not constructed according to drawings (Item 12)
Metal capping in lieu of tiled capping to roof (Item 15)
Box gutter and valley gutter not laid on marine ply (Item 16)
Box gutter does not comply and batten exposed (item 17)
Anti ponding not restored after removal of scaffold (Item 18)
Gas pipe touching metal frame brace (Item 21)
[4] [2009] VCAT 760 at [77].
[5] Clause 20.1 is more fully set out in paragraph 25 above.
[6] [1973] HCA 36; (1973) 129 CLR 99 at 109-110.
[10] Wilson v Kirk Contractors Pty Ltd (1991) 7 BCL 284 at 295.
[11] Laurinda Pty Ltd v Capalaba Park Shopping Centre [1989] HCA 23; (1989) 166 CLR 623 at 657].
[12] Wilson v Kirk Contractors Pty Ltd (1991) 7 BCL 284 at 295.
[15] Letter from Lovegrove Solicitors to Noble Lawyers dated 27 April 2012.
[16] See also judgment of Muir J in Qline Interiors Pty Ltd v Jezer Construction Group Pty Ltd & Ors [2002] QSC 88 at [28-30].
[17] Gates v City Mutual Life Assurance Society Ltd (1986) CLR 1 at 11-12.
[20] Ibid at paragraph 5. See also paragraph 12 of the judgment.
[23] Sopov and Anor v Kane Constructions Pty Ltd (No 2) [2009] VSCA 141 at [21].
[24] [1993] VicRp 71; [1993] 2 VR 221 at p. 258.
[25] Items 4, 5, 8, 14, 16, 17 and 20 in Appendix E2A of Mr Johnson's report dated 24 May 2014.
[26] This includes Items 1, 2, 3, 6, 7, 9, 10, 11 and 19.