Australian Competition and Consumer Commission v J Hutchinson Pty Ltd
[2022] FCA 1007
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2022-08-30
Before
Downes J
Source
Original judgment source is linked above.
Judgment (30 paragraphs)
INTRODUCTION 1 The first respondent (Hutchinson) is a large, privately owned construction company which was the head contractor for the Southpoint A construction project located at 269 Grey Street, South Brisbane in Queensland (the Southpoint project). 2 The second respondent, which was described at trial as the CFMEU, is a trade union organisation. In 2016, the CFMEU was an organisation for the purposes of s 27 of the Fair Work (Registered Organisations) Act 2009 (Cth). On 27 March 2018, the CFMEU amalgamated with the Maritime Union of Australia and the Textile, Clothing and Footwear Union of Australia to become the CFMMEU. 3 Waterproofing Industries Qld Pty Ltd (WPI) is a company which entered into a subcontract with Hutchinson to perform certain waterproofing works at the Southpoint project. 4 On 14 February 2022, the Court delivered judgment in this matter in Australian Competition and Consumer Commission v J Hutchinson Pty Ltd [2022] FCA 98 (liability judgment or LJ). 5 WPI did not have a CFMEU enterprise bargaining agreement (or EBA) and the CFMEU complained that it was not consulted prior to its engagement. Shortly after this, the CFMEU threatened to engage in industrial action if Hutchinson allowed WPI to continue working on the Southpoint project. WPI was excluded from the site from 11 June 2016 and its subcontract was terminated by letter dated 26 July 2016: [8]-[10] LJ. 6 Hutchinson was found to have contravened s 45E(3) of the Competition and Consumer Act 2010 (Cth) by making an arrangement or arriving at an understanding with the CFMEU containing a provision to the effect that Hutchinson would no longer acquire waterproofing services from WPI at the Southpoint project and would terminate the WPI subcontract, which provision would prevent or hinder Hutchinson from acquiring or continuing to acquire services from WPI: [351] LJ. This provision is described as the boycott provision: [11] LJ. 7 Hutchinson was also found to have contravened s 45EA of the Act because, by ceasing to acquire waterproofing services from WPI, and further by terminating the WPI subcontract, it gave effect to the boycott provision: [352] LJ. 8 The CFMEU was found to have been knowingly concerned in, or party to, the contraventions by Hutchinson of ss 45E(3) and 45EA of the Act within the meaning of s 76 of the Act: [361] LJ. 9 The CFMEU was also found to have induced Hutchinson's contraventions of ss 45E(3) and 45EA within the meaning of s 76 of the Act by threating or implying that there would be conflict with, or industrial action by, the CFMEU if Hutchinson did not cease using WPI: [362] LJ. 10 Declarations were made on 14 February 2022 which reflected these findings. The ACCC seeks the following additional relief: (1) pecuniary penalties pursuant to s 76 of the Act; (a) for a total sum of $1.2 million against Hutchinson; (b) for a total sum of $1.5 million against the CFMEU; (2) injunctions pursuant to s 80 of the Act; (3) orders for the establishment of a competition law compliance program pursuant to s 86C of the Act; (4) adverse publicity orders against the CFMEU pursuant to s 86D of the Act; and (5) that the respondents pay its costs on the standard basis. 11 The relief sought in (1), (2) and (3) is opposed. The CFMEU does not oppose the relief sought in (4) and no submissions were made by the respondents against (5). 12 For the following reasons, it will be ordered that: (1) Hutchinson pay a pecuniary penalty in the total sum of $600,000; (2) the CFMEU pay a pecuniary penalty in the total sum of $750,000; (3) the adverse publicity orders sought against the CFMEU be made, with one minor modification; and (4) the respondents pay the ACCC's costs on the standard basis.