2 Elizabeth Bay Road Pty Ltd v The Owners - Strata Plan No 73943
[2014] NSWCA 409
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2014-10-08
Before
Basten JA, Barrett JA, Leeming JA
Catchwords
- CORPORATIONS - commencement of proceedings by owners corporation without authority - effect of ratification by general meeting
Source
Original judgment source is linked above.
Catchwords
Judgment (6 paragraphs)
Background 70The factual and procedural background is both uncontroversial and concise. 71The respondent owners corporation sued the appellant (Developer) by proceedings commenced in the District Court of New South Wales for allegedly defective residential building work carried out between 2002 and 2005. It was alleged that there were a series of defects in the common property of its building in Elizabeth Bay in inner Sydney, caused by breaches of the warranties implied under s 18B of the Home Building Act 1989 (NSW) that (a) the work be done in a proper and workmanlike manner and in accordance with the plans and specifications, (b) the materials be good and suitable for the purpose for which they were used, and unless otherwise specified, that they be new, and (c) the work be done in accordance with any applicable laws. The Developer had retained a builder to undertake the building work the subject of the pleading. However, by the time the proceedings were commenced, the builder was being wound up. The owners corporation relied upon the deeming provision in s 18C of the Home Building Act to the effect that the work had been done by the Developer and that the owners corporation, as a successor in title, was entitled to the benefit of the statutory warranties. 72Section 18E of the Home Building Act formerly provided that proceedings for a breach of a statutory warranty must be commenced within 7 years after the completion of the work to which it relates. The appeal was argued on the basis that the amendment to that section, shortening the limitation period, effected by the Home Building Amendment Act 2011 (NSW), was inapplicable (this accords with the transitional provision contained in cl 109 of Schedule 4 of the Home Building Act). The occupation certificate was dated 22 November 2005. Proceedings were commenced in November 2012. The materials in the appeal book do not include the originating process, but an amended statement of claim was filed on 4 December 2012, and it is plain that the owners corporation and its executive committee were aware of, and had received advice concerning, the limitation period. (In fact, both parties' submissions state that a statement of claim was filed on 6 November 2012.) 73It was common ground that when proceedings were commenced, a resolution approving the litigation had not been passed at a general meeting. The owners corporation did not contend that any of the exceptions in s 80D applied. 74The need to comply with s 80D was drawn to the attention of the owners corporation's solicitors in December 2012. In January 2013 the executive committee formed the view that, since the annual general meeting was to be held on 7 March 2013, there was no need to convene an extraordinary general meeting. In March 2013, a resolution was passed at a general meeting of the owners corporation approving the legal proceedings. 75Nevertheless, the Developer subsequently sought that the proceedings be struck out or dismissed by reason of the delay in passing that resolution, which it said was contrary to s 80D. There were three overlapping bases on which the primary judge relied to dismiss the Developer's application. First, he rejected the submission that proceedings commenced in breach of the section were a nullity and could not subsequently be cured. Secondly, as an element in reaching that conclusion, he considered that the section as a matter of construction did not require approval before proceedings were commenced: his Honour considered that "the section on its plain wording accommodates fulfilment by subsequent resolution": at [34]. Thirdly, he also considered that if the position were regarded as an action instituted without authority, the subsequent resolution was valid ratification of the commencement of proceedings, which had effect from the time of commencement. In this respect, his Honour followed McEvoy v The Body Corporate for No 9 Port Douglas Road [2013] QCA 168. 76The Developer appeals (pursuant to leave granted on 22 May 2014) from the dismissal of its motion. There are essentially two issues: was s 80D breached, and, if so, what are the consequences.