255 Additional information
(1) If an application for registration of the design of an item of plant does not contain enough information to enable the regulator to make a decision whether or not to grant the registration, the regulator may ask the applicant to provide additional information.
(2) A request for additional information must –
(a) specify the date (not being less than 28 days after the request) by which the additional information is to be given; and
(b) be confirmed in writing.
(3) If an applicant does not provide the additional information by the date specified, the application is taken to have been withdrawn.