CTHIn ForceLegislation
Work Health and Safety Regulations 2011
580Decision on application
Start here
Get a plain-English read of 580
Turn the raw legal text into a practical explanation grounded in Work Health and Safety Regulations 2011.
580 Decision on application
(1) Subject to this regulation, the regulator must grant a major hazard facility licence if satisfied about the matters referred to in subregulation (2).
(b) the safety case for the facility has been prepared in accordance with Division 4 of Part 9.3;
(c) the operator is able to operate the major hazard facility safely and competently;
(d) the operator is able to comply with any conditions that will apply to the licence.
(3) The regulator may refuse to grant a major hazard facility licence if it becomes aware of circumstances that satisfy it that the following persons are not suitable persons to exercise management or control over the major hazard facility:
(a) if the operator is an individual—the operator;
(b) if the operator is a body corporate—any officer of the body corporate.
(4) The regulator must refuse to grant a major hazard facility licence if satisfied that the operator, in making the application, has:
(5) If the regulator decides to grant the licence, it must notify the operator within 14 days after making the decision.
(6) If the regulator does not make a decision within 6 months after receiving the application or the additional information requested under regulation 579, the regulator is taken to have refused to grant the licence applied for.
Note: A refusal to grant a major hazard facility licence (including under subregulation (6)) is a reviewable decision (see regulation 676).