301Safe work method statement—copy to be given to principal contractor
Start here
Get a plain-English read of 301
Turn the raw legal text into a practical explanation grounded in Work Health and Safety Regulations 2011.
301 Safe work method statement—copy to be given to principal contractor
A person conducting a business or undertaking that includes carrying out high risk construction work in connection with a construction project must, before the high risk construction work commences, ensure that a copy of the safe work method statement for the work is given to the principal contractor.
Note: Section 12F of the Act provides that strict liability applies to each physical element of each offence under the Act, unless otherwise stated. The reference in section 12F of the Act includes these Regulations.