557 Emergency plan
(1) The operator of a determined major hazard facility must prepare an
emergency plan for the major hazard facility that:
(a) addresses all health and safety consequences of a major
incident occurring; and
(b) includes all matters specified in Schedule 16; and
(c) provides for testing of emergency procedures, including the
frequency of testing.
Work Health and Safety (National Uniform Legislation) Regulations 2011 440
(2) In preparing an emergency plan, the operator must consult with:
(b) in relation to the off-site health and safety consequences of a
major incident occurring – the local authority.
(3) The operator must ensure that the emergency plan addresses any
recommendation made by the emergency service organisations
consulted under subregulation (2) in relation to:
(a) the testing of the emergency plan, including the manner in
which it will be tested, the frequency of testing and whether or
not the emergency service organisations will participate in the
testing; and
(b) what incidents or events at the major hazard facility should be
notified to the emergency service organisations.
(4) The operator must have regard to any other recommendation or
advice given by a person consulted under subregulation (2).
(5) The operator must:
(a) keep a copy of the plan at the major hazard facility; and
(b) give a copy of the plan to:
(i) the emergency service organisations consulted under
subregulation (2); and
(ii) any other relevant emergency service organisations.
Work Health and Safety (National Uniform Legislation) Regulations 2011 441
(6) The operator must test the emergency plan in accordance with the
recommendations made by the emergency service organisations
consulted under subregulation (2) before applying for a licence for
the major hazard facility.
(7) The operator must immediately implement the emergency plan if:
(a) a major incident occurs in the course of the operation of the
major hazard facility; or
(b) an event occurs that could reasonably be expected to lead to
a major incident.
(8) The operator must notify the emergency service organisations
consulted under subregulation (2) of the occurrence of an incident
or event referred to in subregulation (3)(b).
Note for subregulation (8)
Note for regulation 557
This regulation applies in addition to regulation 43.