WORK HEALTH AND SAFETY (NATIONAL UNIFORM LEGISLATION) REGULATIONS 2011
477Removing friable asbestos
Start here
Get a plain-English read of 477
Turn the raw legal text into a practical explanation grounded in WORK HEALTH AND SAFETY (NATIONAL UNIFORM LEGISLATION) REGULATIONS 2011.
477 Removing friable asbestos
(1) A licensed asbestos removalist removing friable asbestos must
ensure, so far as is reasonably practicable, the following:
(a) the asbestos removal area is enclosed to prevent the release
of respirable asbestos fibres;
(b) subject to subregulation (3), negative pressure is used;
(c) the wet method of asbestos removal is used;
(d) subject to subregulation (3), the asbestos removal work does
not commence until the air monitoring is commenced by a
licensed asbestos assessor;
Work Health and Safety (National Uniform Legislation) Regulations 2011 374
(e) air monitoring is undertaken during the asbestos removal
work, at times decided by the independent licensed asbestos
assessor undertaking the monitoring;
(f) any glove bag used to enclose the asbestos removal area is
dismantled and disposed of safely.
(2) A licensed asbestos removalist must ensure that any enclosure
used in removing friable asbestos is tested for leaks.
(3) Subregulation (1)(b) and (d) do not apply if glove bags are used in
the Class A asbestos removal work.
(4) The licensed removalist must not dismantle an enclosure for a
friable asbestos removal area until the removalist receives results
of air monitoring, showing that the recorded respirable asbestos
fibre level within the enclosure is below 0.01 fibres/ml, from:
(a) if the friable asbestos is removed from residential premises –
the licensed asbestos assessor who undertook the air
(b) in any other case – the person who commissioned the Class A
Work Health and Safety (National Uniform Legislation) Regulations 2011 375
(5) The licensed removalist must ensure that an enclosure for a friable
asbestos removal area is dismantled in a way that, so far as is
reasonably practicable, eliminates the release of respirable
asbestos fibre.
(6) The person who commissioned the removal of the friable asbestos
must obtain a clearance certificate from a licensed asbestos
assessor after the enclosure for the friable asbestos removal area
has been dismantled.