313Copy of WHS management plan must be kept
Start here
Get a plain-English read of 313
Turn the raw legal text into a practical explanation grounded in WORK HEALTH AND SAFETY (NATIONAL UNIFORM LEGISLATION) REGULATIONS 2011.
313 Copy of WHS management plan must be kept
(1) Subject to subregulation (2), the principal contractor for a
construction project must ensure that a copy of the WHS
management plan for the project is kept until the project to which it
relates is completed.
Work Health and Safety (National Uniform Legislation) Regulations 2011 236
(2) If a notifiable incident occurs in connection with the construction
project to which the statement relates, the person must keep the
WHS management plan for at least 2 years after the incident
occurs.
(3) The person must ensure that, for the period for which the WHS
management plan must be kept under this regulation, a copy is
readily accessible to any person who is to carry out construction
work in connection with the construction project.
(4) The person must ensure that for the period for which the WHS
management plan must be kept under this regulation, a copy is
WHS management plan means the initial plan and all revised
versions of the plan.
Work Health and Safety (National Uniform Legislation) Regulations 2011 237