WORK HEALTH AND SAFETY (NATIONAL UNIFORM LEGISLATION) REGULATIONS 2011
313Copy of WHS management plan must be kept
Start here
Get a plain-English read of 313
Turn the raw legal text into a practical explanation grounded in WORK HEALTH AND SAFETY (NATIONAL UNIFORM LEGISLATION) REGULATIONS 2011.
313 Copy of WHS management plan must be kept (1) Subject to subregulation (2), the principal contractor for a construction project must ensure that a copy of the WHS management plan for the project is kept until the project to which it relates is completed.
Work Health and Safety (National Uniform Legislation) Regulations 2011 236 (2) If a notifiable incident occurs in connection with the construction project to which the statement relates, the person must keep the WHS management plan for at least 2 years after the incident occurs. (3) The person must ensure that, for the period for which the WHS management plan must be kept under this regulation, a copy is readily accessible to any person who is to carry out construction work in connection with the construction project. (4) The person must ensure that for the period for which the WHS management plan must be kept under this regulation, a copy is WHS management plan means the initial plan and all revised versions of the plan.
Work Health and Safety (National Uniform Legislation) Regulations 2011 237