164ZBCompletion of dam works under Division 4 permit
Start here
Get a plain-English read of 164ZB
Turn the raw legal text into a practical explanation grounded in Water Management Act 1999.
164ZB Completion of dam works under Division 4 permit
[Section 164ZB Inserted by No. 33 of 2015, s. 20, Applied:01 Jan 2016]
(1) Within 30 days after the dam works under a Division 4 permit have been completed, the permit holder must give to the Minister a notice (the notice of completion), in writing, of the completion of the dam works.
Penalty: Fine not exceeding 200 penalty units.
(2) The notice of completion is to –
(a) be in the approved form; and
(b) include a declaration that the dam works were undertaken and completed in accordance with the Division 4 permit and its conditions; and
(c) include any other information the Minister requires for the purposes of Part 8A .
(3) On receiving a notice of completion, the Minister may, in writing, require the permit holder to do one or more of the following:
(a) provide further information within the time specified in the request;
(b) take further action, within the time specified in the requirement;
(c) notify the Minister, in writing and within the time specified in the requirement (if any), of the completion of the further action the permit holder is required to take under paragraph (b) .
(4) A permit holder must comply with a requirement under subsection (3) .
Penalty: Fine not exceeding 200 penalty units.
(5) On receiving a notice of completion or any further information or notice required under subsection (3)(a) or (c) , or on being notified that further action specified in a requirement under subsection (3)(b) has been taken, the Minister may –
(a) accept the notice of completion; or
(b) notify the permit holder, in writing, that the dam works have not met the requirements for entitlement to a Division 4 permit set out in .