VICIn ForceAct
Building Act 1993
84Notice of building work to be given
Start here
Get a plain-English read of 84
Turn the raw legal text into a practical explanation grounded in Building Act 1993.
84 Notice of building work to be given
(1) An owner who is required by the building regulations to carry out protection work in respect of an adjoining property before or during the carrying out of building work for which a building permit is required must, before commencing the building work, serve on the owner of the adjoining property and the relevant building surveyor notice of the proposed building work.
S. 84(2) substituted by No. 66/2004 s. 9(1).
(2) The notice must include—
(a) prescribed details of the proposed building work as at the date of the notice; and
(b) prescribed details of the proposed protection work setting out the nature, location, time and duration of the protection work; and
(c) any other prescribed information.
S. 84A inserted by No. 43/2024 s. 3.