Utilities Act 2000
235Notice to land-holder
Start here
Get a plain-English read of 235
Turn the raw legal text into a practical explanation grounded in Utilities Act 2000.
235 Notice to land-holder (1) Before the Territory begins territory network operations in relation to national land or private land, it must give the land-holder written notice of the proposed operations. (2) The notice must be given to the land-holder at least 7 days before the operations begin.
(iii) the parts of the land likely to be affected; (b) contain a statement indicating the Territory’s obligations under this part— (i) to take all reasonable steps to ensure that it causes as little inconvenience, detriment and damage as is practicable; and (ii) to remove its property and waste; and (iii) to restore the land. period of notice under subsection (2). (5) Subsection (1) does not apply if the operations are to be carried out or