ACTIn ForceAct
Urban Forest Act 2023
26Approval application—time for referral entity to give
Start here
Get a plain-English read of 26
Turn the raw legal text into a practical explanation grounded in Urban Forest Act 2023.
26 Approval application—time for referral entity to give If an application under section 21 is given to an entity under section 25, the entity must give the decision-maker the entity’s advice on the application not later than— (a) 15 working days after the day the decision-maker gives the application to the entity; or (b) if a regulation prescribes a shorter period—the end of the shorter period.