64 Decision on application
(1) The ACMA must approve an application made under subsection 63(1) if the application is complete, unless the ground set out in paragraph (2)(b) applies.
(2) If the ACMA receives more than one application for allocation of the same smartnumber, the ACMA must:
(a) make a decision on the applications in the order that the applications were received; and
(b) if it approves an application—not approve any later applications.
(3) If the ACMA decides not to approve an application under subsection 63(1), the ACMA must give written notice of the decision to the registered carriage service provider and the EROU applicant.