This Plan sets the local zoning, maps and detailed development rules for specified land in Glebe: it prescribes permitted uses, height and floor‑space controls (including a social‑housing FSR bonus at cl 4.4(2A)), parking maxima, exempt/complying development categories and site‑specific maps (cl 1.3). It affects landowners and developers who meet compliance costs and obtain Council consent (cl 1.6); the Council decides applications. The rules change developer incentives (design excellence cl 6.4, heritage cl 5.10, flood cl 5.14) and create specified exemptions (Sched 2).
This instrument is a local environmental plan (LEP) titled Sydney Local Environmental Plan (Glebe Affordable Housing Project) 2011. It establishes the land-use framework, development standards, and local controls that apply to the land identified on the Land Application Map (cl 1.1; cl 1.3). The Plan:
zones the land R1 General Residential and sets objectives for that zone, including housing diversity and ancillary services (cl 2.1; Land Use Table, Zone R1 Objectives).
prescribes which uses are permitted without consent, permitted with consent and prohibited in that zone (Land Use Table items 2, 3 and 4).
sets floor space ratio and building height controls by reference to maps (cl 4.3; cl 4.4).
creates a local override and interaction regime with State environmental planning policies (cl 1.9).
provides for exempt and complying development types and conditions, including a specific exempt development item for street art (cl 3.1; cl 3.2; sch 2, sch 3).
contains a limited density bonus for social housing premises where total social housing floor area is at least 110 per cent of site area, allowing up to an extra 0.6:1 FSR above the mapped maximum (cl 4.4(2A)).
requires development consent for a variety of activities: subdivision, demolition, disturbance of heritage items or Aboriginal places, works affecting acid sulfate soils, disturbance of public bushland, certain fire alarm conversions and conversion of Crown infrastructure uses (cl 2.6; cl 2.7; cl 5.10; cl 6.1; cl 5.8; cl 5.12).
sets a number of local provisions affecting design excellence (cl 6.4), car parking maxima (cl 6.5), flood planning considerations (cl 5.14) and public utility infrastructure availability (cl 6.3).
Current sections
Direct links to the current provisions in Sydney Local Environmental Plan (Glebe Affordable Housing Project) 2011.
20
Part 1
Preliminary
Part 1 Preliminary
Part 1 Preliminary
Note—
The Standard Instrument (Local Environmental Plans) Order 2006 sets out matters to be included in standard local environmental plans. While this Plan is not a standard local environmental plan, standard clauses have been included in this Plan and the clause numbering from that Order has been retained. This means that the numbering in this Plan may contain some gaps. If additional provisions have been inserted they are numbered accordingly.
State Environmental Planning Policy (Transport and Infrastructure) 2021, Chapter 2— relating to infrastructure facilities, including air transport, correction, education, electricity generating works and solar energy systems, health services, ports, railways, roads, waste management and water supply systems
Land Use tbl: Am 2017 (726), Sch 2.6 [1]; 2022 (72), Sch 1.57[1]; 2022 (629), Sch 3.20[1].
Zone R1 General Residential
3
Permitted with consent
3 Permitted with consent
3 Permitted with consent
Attached dwellings; Bed and breakfast accommodation; Boarding houses; Centre-based child care facilities; Community facilities; Dwelling houses; Food and drink premises; Group homes; Home-based child care; Home industries; Home occupations (sex services); Hostels; Jetties; Markets; Multi dwelling housing; Neighbourhood shops; Places of public worship; Residential flat buildings; Respite day care centres; Roads; Roadside stalls; Semi-detached dwellings; Seniors housing; Shops; Shop top housing; Any other development not specified in item 2 or 4
4
Prohibited
4 Prohibited
4 Prohibited
Agriculture; Air transport facilities; Airstrips; Amusement centres; Animal boarding or training establishments; Boat building and repair facilities; Boat launching ramps; Camping grounds; Car parks; Caravan parks; Charter and tourism boating facilities; Commercial premises; Crematoria; Depots; Eco-tourist facilities; Entertainment facilities; Environmental protection works; Exhibition villages; Extractive industries; Farm buildings; Forestry; Freight transport facilities; Function centres; Heavy industrial storage establishments; Helipads; Highway service centres; Industrial retail outlets; Industrial training facilities; Industries; Mooring pens; Moorings; Mortuaries; Open cut mining; Passenger transport facilities; Port facilities; Recreation facilities (major); Recreation facilities (outdoor); Registered clubs; Research stations; Restricted premises; Rural industries; Rural supplies; Service stations; Sewerage systems; Sex service premises; Storage premises; Tourist and visitor accommodation; Transport depots; Truck depots; Vehicle body repair workshops; Vehicle repair stations; Veterinary hospitals; Warehouse or distribution centres; Waste or resource management facilities; Water recreation structures; Water supply systems; Wharf or boating facilities; Wholesale supplies
Part 3
Exempt and complying development
Part 3 Exempt and complying development
Part 3 Exempt and complying development
Part 4
Principal development standards
Part 4 Principal development standards
Part 4 Principal development standards
Part 5
Miscellaneous provisions
Part 5 Miscellaneous provisions
Part 5 Miscellaneous provisions
5
Relevant acquisition authority
5 Relevant acquisition authority
5.1 Relevant acquisition authority
(1) The objective of this clause is to identify, for the purposes of section 3.15 of the Act, the authority of the State that will be the relevant authority to acquire land reserved for certain public purposes if the land is required to be acquired under Division 3 of Part 2 of the Land Acquisition (Just Terms Compensation) Act 1991 (the owner-initiated acquisition provisions).
Note—
If the landholder will suffer hardship if there is any delay in the land being acquired by the relevant authority, section 23 of the Land Acquisition (Just Terms Compensation) Act 1991 requires the authority to acquire the land.
(2) The authority of the State that will be the relevant authority to acquire land, if the land is required to be acquired under the owner-initiated acquisition provisions, is the authority of the State specified below in relation to the land shown on the Land Reservation Acquisition Map (or, if an authority of the State is not specified in relation to land required to be so acquired, the authority designated or determined under those provisions).
| Type of land shown on Map | Authority of the State |
| Zone RE1 Public Recreation and marked “Local open space” | Council |
| Zone RE1 Public Recreation and marked “Regional open space” | The corporation constituted under section 2.5 of the Act |
| Zone SP2 Infrastructure and marked “Classified road” | Transport for NSW |
| Zone C1 National Parks and Nature Reserves and marked “National Park” | Minister administering the National Parks and Wildlife Act 1974 |
Note—
When this Plan was made, it did not include Zones RE1, SP2 or C1.
(3) Development on land acquired by an authority of the State under the owner-initiated acquisition provisions may, before it is used for the purpose for which it is reserved, be carried out, with development consent, for any purpose.
Note—
When this Plan was made no land in the zones listed in the Table to subclause (2) was included on the Land Reservation Acquisition Map.
cl 5.1: Am 2019 (621), Sch 4.1[9] [10]; 2020 No 30, Sch 4.102[1]; 2024 (42), Sch 1.42.
Part 6
Additional local provisions
Part 6 Additional local provisions
Part 6 Additional local provisions
6
Acid sulfate soils
6 Acid sulfate soils
6.1 Acid sulfate soils
(1) The objective of this clause is to ensure that development does not disturb, expose or drain acid sulfate soils and cause environmental damage.
(2) Development consent is required for the carrying out of works described in the Table to this subclause on land shown on the Acid Sulfate Soils Map as being of the class specified for those works.
| Class of land | Works |
| 1 | Any works. |
| 2 | Works below the natural ground surface.Works by which the watertable is likely to be lowered. |
| 3 | Works more than 1 metre below the natural ground surface.Works by which the watertable is likely to be lowered more than 1 metre below the natural ground surface. |
| 4 | Works more than 2 metres below the natural ground surface.Works by which the watertable is likely to be lowered more than 2 metres below the natural ground surface. |
| 5 | Works within 500 metres of adjacent Class 1, 2, 3 or 4 land that is below 5 metres Australian Height Datum and by which the watertable is likely to be lowered below 1 metre Australian Height Datum on adjacent Class 1, 2, 3 or 4 land. |
(3) Development consent must not be granted under this clause for the carrying out of works unless an acid sulfate soils management plan has been prepared for the proposed works in accordance with the Acid Sulfate Soils Manual and has been provided to the consent authority.
(4) Despite subclause (2), development consent is not required under this clause for the carrying out of works if—
(a) a preliminary assessment of the proposed works prepared in accordance with the Acid Sulfate Soils Manual indicates that an acid sulfate soils management plan is not required for the works, and
(b) the preliminary assessment has been provided to the consent authority and the consent authority has confirmed the assessment by notice in writing to the person proposing to carry out the works.
(5) Despite subclause (2), development consent is not required under this clause for the carrying out of any of the following works by a public authority (including ancillary work such as excavation, construction of access ways or the supply of power)—
(a) emergency work, being the repair or replacement of the works of the public authority required to be carried out urgently because the works have been damaged, have ceased to function or pose a risk to the environment or to public health and safety,
(b) routine maintenance work, being the periodic inspection, cleaning, repair or replacement of the works of the public authority (other than work that involves the disturbance of more than 1 tonne of soil),
(c) minor work, being work that costs less than $20,000 (other than drainage work).
(6) Despite subclause (2), development consent is not required under this clause to carry out any works if—
(a) the works involve the disturbance of less than 1 tonne of soil, such as occurs in carrying out agriculture, the construction or maintenance of drains, extractive industries, dredging, the construction of artificial water bodies (including canals, dams and detention basins), foundations or flood mitigation works, or
(b) the works are not likely to lower the watertable.
Exempt development may be carried out without the need for development consent under the Act. Such development is not exempt from any approval, licence, permit or authority that is required under any other Act and adjoining owners’ property rights and the common law still apply.
sch 2: Am 2017 (751), Sch 1.2; 2020 No 30, Sch 4.102[2]
sch.2-sec
Street art
sch.2-sec Street art
Street art
(1) Must not project more than 30mm from a wall or other surface.
(2) Must not constitute signage.
Note—
Signage includes advertisements and advertising structures.
(3) Must not be located on a heritage item or within a heritage conservation area.
(4) Must not contain material that—
(a) discriminates against or vilifies any person or group, or
(b) is offensive or sexually explicit.
(5) In this clause, street art means art that is painted, marked or otherwise affixed to the outside of a building and that is visible from a public place (within the meaning of the Local Government Act 1993).
Note—
Street art may only be carried out subject to requirements to obtain the approval of the owner of the building on which the street art is located or any statutory authorities (such as Transport for NSW). See also Part 2 of the Graffiti Control Act 2008 for graffiti related offences.
Classification and reclassification of public land
Schedule 4 Classification and reclassification of public land
Schedule 4 Classification and reclassification of public land
(Clause 5.2)
Schedule 5
Environmental heritage
Schedule 5 Environmental heritage
Schedule 5 Environmental heritage
(Clause 5.10)
(When this Plan was made this Schedule was blank)
Source text: opening excerpt
Sourced from legislation.nsw.gov.au, CC BY 4.0.
Part 1 Preliminary
Part 1 Preliminary
Part 1 Preliminary
Note—
The Standard Instrument (Local Environmental Plans) Order 2006 sets out matters to be included in standard local environmental plans. While this Plan is not a standard local environmental plan, standard clauses have been included in this Plan and the clause numbering from that Order has been retained. This means that the numbering in this Plan may contain some gaps. If additional provisions have been inserted they are numbered accordingly.
1 Name of Plan
1 Name of Plan
1.1 Name of Plan
This Plan is Sydney Local Environmental Plan (Glebe Affordable Housing Project) 2011.
1 Commencement
1 Commencement
1.1AA Commencement
This Plan commences on the day on which it is published on the NSW legislation website.
1 Aims of Plan
1 Aims of Plan
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning provisions for certain land in Glebe generally in accordance with the relevant standard environmental planning instrument under section 3.20 of the Act.
(2) The particular aims of this Plan are as follows—
(aa) to protect and promote the use and development of land for arts and cultural activity, including music and other performance arts,
(a) to facilitate the development of affordable housing and social housing on the subject land,
(b) to encourage the growth and diversity of the residential population of the City of Sydney by providing for a range of appropriately located housing, including affordable housing and social housing,
(c) to promote ecologically sustainable development,
(d) to ensure that the pattern of land use and density reflects the existing and future capacity of the transport network and facilitates walking, cycling and the use of public transport,
(e) to achieve a high quality urban form by ensuring that new development exhibits design excellence and reflects the existing or desired future character of the locality,
identifies the consent authority as the Council, subject to the City of Sydney Act note about the Central Sydney Planning Committee exercising functions for major development under the Act (cl 1.6).
Mechanically, the Plan operates by mapping and the schedules. Development is regulated through the development consent regime under the Environmental Planning and Assessment Act (the Act) where the Plan requires consent, and through exempt and complying development pathways where the Plan so provides (cl 3.1; cl 3.2). It also repeals previous local instruments that applied solely to the subject land (cl 1.8). The Plan contains a number of cross-references to State instruments, Guidelines and other Acts (for example Heritage Act 1977, Local Government Act 1993, Fire and Rescue NSW arrangements), which shape when and how certain approvals, notifications and management plans are required (see cl 1.9; cl 5.10; cl 5.8; cl 5.1; cl 6.1).
The stated aims are to facilitate affordable and social housing, protect and promote arts and cultural activities, achieve ecologically sustainable development, align density with transport capacity and require design excellence while protecting heritage (cl 1.2). Those aims inform several substantive provisions in the instrument: the social housing FSR incentive (cl 4.4(2A)), music-related consent protections for licensed premises (cl 5.13), and design excellence requirement for new or externally altered buildings (cl 6.4).
Main concepts
The Plan uses a small set of core mechanisms to regulate land use, development intensity and design on the mapped Glebe land.
Zones and Land Use Table
The Plan adopts standard zone categories and a Land Use Table to allocate permitted, permitted-with-consent and prohibited uses (cl 2.1; cl 2.3; Land Use Table). For the subject land the operative zone is R1 General Residential. The Land Use Table drives what development types may proceed and whether consent is required.
Maps and mapped controls
Primary development standards such as maximum building height and floor space ratio are set by maps referenced in the Plan rather than numerical clauses within the text (cl 4.3; cl 4.4). The Plan relies on the Height of Buildings Map, Floor Space Ratio Map, Land Zoning Map, Lot Size Map, Land Application Map and others (see cl 1.3; cl 1.7; cl 2.2; cl 4.3; cl 4.4).
Permitted pathways: consent, exempt and complying development
The Plan distinguishes development that requires development consent from exempt and complying development (cl 3.1; cl 3.2). Exempt development is limited to items in Schedule 2 and is subject to standards and exclusions, for example exclusion for sites on the State Heritage Register (cl 3.1(2)-(4)). Complying development is set out in Schedule 3 and by cross-reference to the State SEPP for Exempt and Complying Development Codes (cl 3.2).
Development standards and exceptions
Floor space ratio and height operate as mapped maxima. The Plan provides a limited mechanism to exceed mapped FSR by up to 0.6:1 where social housing premises floor area equals or exceeds 110 per cent of the site area (cl 4.4(2A)). The Plan contains an exceptions-to-development-standards clause which permits the consent authority to grant consent for development that contravenes a development standard if the applicant demonstrates that compliance is unreasonable or unnecessary and sufficient planning grounds justify the contravention (cl 4.6). That clause excludes certain standards from its operation, for example BASIX commitments, clause 5.4 standards and complying development standards (cl 4.6(8)).
Heritage and Aboriginal cultural heritage
Development affecting heritage items, conservation areas, Aboriginal places and archaeological sites requires development consent (cl 5.10(2)). The consent authority can require heritage management documents or heritage conservation management plans and must notify and consider responses from the Heritage Council or local Aboriginal communities where appropriate (cl 5.10(4)-(9)).
Environmental risk and special topics
Acid sulfate soils trigger consent and management plan obligations according to mapped classes and the Acid Sulfate Soils Manual, with certain public authority works excepted (cl 6.1).
Environmentally sensitive areas are excluded from exempt and complying development regimes (cl 3.3).
Flood planning is addressed by a clause requiring compatibility with flood function and consideration of climate change projections and evacuation capacity (cl 5.14).
Public bushland is specifically protected with an emphasis on retention of ecological function and restrictions on disturbance unless essential and minimised with remediation measures (cl 5.15).
Design excellence and subjective assessment
The Plan imposes a compulsory design excellence test for new buildings or external alterations, with a list of matters the consent authority must have regard to when forming an opinion (cl 6.4). The criteria include material and detailing, public domain impact, view corridors, bulk, sustainable design, and circulation.
Local-specific items and community land
The Plan contains Schedule 4 classification or reclassification mechanics for public land to operational or community land under the Local Government Act 1993 and notes that some reclassifications require Governor approval (cl 5.2; Schedule 4). The Plan also sets out acquisition authorities for owner-initiated land acquisition under the Land Acquisition (Just Terms Compensation) Act 1991 (cl 5.1).
Protections for live music and licensed premises
The Plan includes a clause preventing the refusal of consent for licensed premises on certain grounds related to music and performance, and requires assessment to focus on whether noise may be managed to an acceptable level rather than on music genre or whether dancing occurs (cl 5.13).
Operational mechanics and saving provisions
The Plan repeals prior local environmental plans that applied to the same land (cl 1.8) and contains savings provisions for development applications made prior to commencement of amendments (cl 1.8A). It is subject to any SEPPs that prevail (cl 1.9(1)).
Across these mechanisms the Plan blends mapped prescriptive controls with discretionary consent assessments, and sets specific local requirements across heritage, environmental risk, affordable/social housing incentives, and arts and culture supporting measures. The Plan ties many assessments to external manuals and Guidelines (for example the Acid Sulfate Soils Manual and Considering Flooding in Land Use Planning Guideline, cl 6.1(3); cl 5.14(4)-(5)).
Who it affects
The Plan affects a defined and mapped set of land in Glebe (cl 1.3). The primary stakeholders and interested parties are:
Landowners and prospective developers of parcels within the mapped area, who must comply with the Plan's zoning, mapped floorspace and height limits, and development consent requirements. Subdivision of land and demolition require consent across the mapped land (cl 2.6; cl 2.7). Developers seeking to exceed mapped FSR may be materially affected by cl 4.4(2A) if proposing social housing premises.
Tenants and prospective residents in the area: the Plan’s objectives include promoting affordable and social housing and a diversity of housing types (cl 1.2). For residential developments, the Plan prescribes maximum ancillary car parking rates (cl 6.5(4)-(5)), which may influence vehicle availability and resident behaviour.
The City of Sydney Council and, for major development, the Central Sydney Planning Committee under the City of Sydney Act 1988. The consent authority is the Council, subject to the Committee's functions for major development (cl 1.6). The Council is responsible for administering consent, design excellence assessments (cl 6.4), heritage notifications and approvals (cl 5.10), and for confirming adequacy of public utility infrastructure for proposed development (cl 6.3).
State agencies and utilities: Transport for NSW, Fire and Rescue NSW and other State bodies are referenced functionally. For example, Fire and Rescue NSW may monitor fire alarm systems; conversions of monitoring arrangements require consent and specify private provider relationships (cl 5.8). Public authority works are excepted from some consent requirements: for instance certain public authority works in acid sulfate soils do not require consent (cl 6.1(5)) and the Plan does not restrict development covered by State SEPP (Transport and Infrastructure) Chapter 2 (cl 5.12).
Heritage stakeholders and Aboriginal communities: heritage items and Aboriginal places attract special consent, consultation and assessment requirements. The consent authority must notify and consider the Heritage Council for archaeological sites and must notify local Aboriginal communities and consider responses for Aboriginal places of heritage significance (cl 5.10(7)-(9)). Schedule 5 may list heritage items, though in the present text Schedule 5 is blank.
Cultural and arts organisations and operators of licensed premises: the Plan’s aims include promotion of arts and cultural activity (cl 1.2(aa)), and the Plan protects licensed premises from refusal on various subjective music and entertainment grounds, subject to noise being manageable (cl 5.13).
Community and environmental interest groups: the Plan contains specific protections for public bushland (cl 5.15) and excludes environmentally sensitive areas from exempt or complying development (cl 3.3), meaning conservation groups will be engaged in consent pathways.
Local Aboriginal communities: where development affects Aboriginal places of heritage significance, the consent authority must notify and consider responses from local Aboriginal communities (cl 5.10(8)).
Owners of buildings where street art is proposed: street art is listed as exempt development in Schedule 2 subject to conditions (sch 2, Street art). Owners must ensure street art does not project beyond 30 mm, is not signage, is not on a heritage place, and does not contain discriminatory, vilifying or offensive material (sch 2, Street art).
Specific groups face particular regulatory hooks:
Applicants seeking to use the social housing FSR uplift must provide evidence showing the building area used as social housing premises equals or exceeds 110 per cent of the site area (cl 4.4(2A)), and social housing is given the definition used in the Residential Tenancies Act 2010 (cl 4.4(2B)).
Applicants proposing works in mapped acid sulfate soils areas must prepare an acid sulfate soils management plan in accordance with the Acid Sulfate Soils Manual and provide it to the consent authority before consent is granted (cl 6.1(2)-(3)), unless a preliminary assessment excludes the requirement and is confirmed by the consent authority (cl 6.1(4)).
Where development affects public utility infrastructure availability, the Council must be satisfied that essential infrastructure is available or arrangements are in place (cl 6.3(1)).
The Plan therefore imposes obligations and opportunities across private developers, public authorities, the Council and interest groups; it changes the compliance and consultation landscape for development on the mapped Glebe land.
Key duties and rights
This section lists the principal duties imposed and rights conferred by the Plan as set out in its clauses.
Consent authority duties and powers
The consent authority is the Council, subject to the City of Sydney Act 1988 note about the Central Sydney Planning Committee’s role on major development. The consent authority must determine applications in accordance with the Plan and have regard to zone objectives when assessing proposals (cl 1.6; cl 2.3(2)). It must keep records of assessments under the exceptions to standards clause (cl 4.6(4)).
Applicant duties
Applicants must obtain development consent where the Plan requires it: for subdivision (cl 2.6), demolition (cl 2.7), many heritage-related works (cl 5.10(2)), works described in the acid sulfate soils table on mapped classes (cl 6.1(2)), development in bushland that will disturb it (cl 5.15(2)), and converting fire alarm monitoring systems (cl 5.8(2)). Applicants proposing development that contravenes a development standard must provide the justification required by cl 4.6(3) and the supporting document required by the Environmental Planning and Assessment Regulation 2021 (cl 4.6(3) Note).
Applicants must provide specialist documentation where required: acid sulfate soils management plans (cl 6.1(3)); heritage management documents or conservation management plans (cl 5.10(5)-(6)); evidence showing that social housing floor area meets the 110 per cent threshold for the FSR uplift (cl 4.4(2A) , the clause sets the outcome but an applicant must provide proof of floor area calculations consistent with cl 4.5).
Council and consent authority procedural duties
For heritage and archaeological matters the consent authority must notify the Heritage Council and consider any response (cl 5.10(7), (9)). For Aboriginal places of heritage significance the consent authority must conduct adequate investigation and notify local Aboriginal communities, taking responses into account (cl 5.10(8)).
Rights and permitted actions
Exempt development: development that meets Schedule 2 standards and the Part 3 requirements is exempt from development consent (cl 3.1(2)). Street art, subject to its conditions, is given as exempt development in Schedule 2 (sch 2, Street art).
Complying development: development in Part 1 of Schedule 3 that meets the specified standards and Part 3 requirements may be carried out as complying development and a complying development certificate may be issued (cl 3.2(2)-(4)).
Social housing FSR uplift: the Plan allows greater floor space ratio than mapped maxima by up to 0.6:1 where social housing premises total floor area equals at least 110 per cent of the site area (cl 4.4(2A)). This is a discretionary right contingent on meeting the social housing threshold and other consent processes.
Design and amenity duties
The consent authority must be satisfied that proposed development exhibits design excellence before granting consent for erection of a new building or external alteration (cl 6.4(3)). The consent authority must have regard to a non-exhaustive list of design matters (cl 6.4(4)).
Environmental and heritage protection duties
The consent authority must refuse consent where development would contravene certain excluded development standards (cl 4.6(8)), and must ensure development affecting heritage items does not adversely affect heritage significance, having regard to heritage management documents, or by requiring conservation works as a condition where appropriate (cl 5.10(4), (10)).
Limitations on refusal grounds for licensed premises
Owners and operators of licensed premises are protected from refusal of consent on certain grounds relating to music, performance, dancing or stage orientation, provided noise can be managed to acceptable levels (cl 5.13(1)-(2)).
Public land classification and acquisition
The Plan sets out which State authority would be the relevant acquisition authority under owner-initiated acquisition provisions for land shown on the Land Reservation Acquisition Map (cl 5.1(2)). Where land is acquired by a State authority, development prior to its reservation use may be carried out with development consent for any purpose (cl 5.1(3)). The Council is enabled to classify or reclassify public land as operational or community land under the Local Government Act (cl 5.2(1)-(3)).
Exclusions and prohibitions
Environmentally sensitive areas are excluded from exempt or complying development (cl 3.3(1)-(2)). Canal estate development is expressly prohibited on land to which the Plan applies (cl 5.16(1)-(2)).
Procedural and evidentiary obligations
The Plan imposes that covenants may be required to prevent "double dipping" of floor area across lots (cl 4.5(9)-(10)). It also requires that complying development certificates for certain fire alarm conversions are subject to time-of-day work restrictions (cl 5.8(4)).
The Plan therefore allocates duties between applicants and the consent authority, creates rights to certain development pathways (exempt, complying), sets mandatory environmental and heritage processes, and establishes local incentives and limitations such as the social housing FSR uplift and the design excellence requirement.
Penalties and enforcement
The Plan itself does not specify penalties in monetary or criminal terms. Enforcement and compliance mechanisms are primarily procedural and operate through the development consent regime and statutory interactions with the Act and other legislation. The Plan provides hooks for enforcement in the following ways:
Development consent as control point
The Plan makes many activities conditional on obtaining development consent. Carrying out development without required consent is regulated by the Act; while the Act and regulations are not reproduced in this Plan, the Plan’s repeated requirement for consent establishes the development consent process as the principal enforcement mechanism (see cl 2.6, cl 2.7, cl 5.10, cl 6.1). The Plan does not itself set penalties but conditions the lawfulness of carrying out activities on obtaining consent.
Conditions and covenants
The Plan empowers the consent authority to impose conditions that may include registration of covenants preventing the creation of floor area on a lot to prevent double counting of site area or floor space (cl 4.5(9)). Such covenants are private legal encumbrances; enforcement of covenants is by legal action in the usual property law channels. The Plan notes reduced permitted floor area on other land where a covenant applies (cl 4.5(10)).
Notification and consultation obligations
The Plan requires notification of the Heritage Council and Aboriginal communities in certain circumstances prior to granting consent (cl 5.10(7)-(9)). Failure to follow statutory consultation processes may be relevant to the lawfulness of a consent decision and hence relevant in administrative review processes under the Act.
Exclusions and invalidity of exempt/compliant classifications
Exempt and complying development regimes are circumscribed by the Plan. Exempt development rules require compliance with the Building Code and must not relate to land on the State Heritage Register (cl 3.1(3)(a)-(d)). If a proponent proceeds under an exempt or complying pathway incorrectly, the consent status may be invalidated, leading to enforcement action under the Act or other statutes. The Plan does not itself specify breach penalties.
Interaction with other Acts
The Plan frequently cross-refers to other statutes that contain enforcement regimes, licences and penalties. For example, heritage offences under the Heritage Act 1977 or graffiti penalties under the Graffiti Control Act 2008 may apply where relevant, and the Plan expressly notes that exempt development is not exempt from approvals, licences or permits required under any other Act (sch 2 Note 2; cl 3.1 Note). Fire and Rescue NSW monitoring arrangements are referenced; conversions of monitoring systems are subject to consent and may require private service provider agreements (cl 5.8).
Administrative records and transparency
The consent authority must keep records of assessments under the exceptions-to-standards clause (cl 4.6(4)). That requirement supports administrative transparency and provides grounds for review or challenge where necessary.
Restrictions with legal effect beyond consent
The Plan enables the registration of covenants as a condition of consent (cl 4.5(9)), and Schedule 4 reclassification consequences can discharge or preserve trusts and reservations affecting public reserves with the Governor’s approval where required (cl 5.2(5) Note). Those mechanisms have enduring legal consequences and create enforceable obligations.
Practical enforcement implications
In practice the Plan places the onus on the consent authority to ensure compliance at the consent stage through conditions, management plans and consultation. It delegates enforcement of building standards to the Building Code of Australia and to the regimes governing exempt and complying development certificates, as well as to other Acts for matters like heritage or graffiti. The Plan does not set fines, infringement notices or prosecution mechanisms within its text; those instruments reside in the Act and other legislation which the Plan references.
Because the Plan defers to the Act and other legislative regimes for penalties, effective enforcement depends on coordination between the Council, State agencies (e.g. Heritage Council, Fire and Rescue NSW), and compliance under other legislative instruments cited by the Plan.
How it interacts with other laws
The Plan is integrated into the broader statutory framework by express cross-references and exclusions. Its text identifies multiple statutory instruments, manuals and SEPPs that affect its operation. The principal interactions are:
Primacy and subject to State SEPPs
The Plan is subject to the provisions of any State environmental planning policy (SEPP) that prevails under section 3.28 of the Act (cl 1.9(1)). The Plan explicitly lists certain SEPPs that do not apply to the land (such as SEPP No 1 and specified parts of other SEPPs) but otherwise defers to SEPPs, meaning State-level policies can override the Plan’s provisions where they prevail (cl 1.9(2)).
Environmental Planning and Assessment Act and Regulation
The Plan operates under the architecture of the Act. It prescribes what requires development consent, what may be exempt or complying development, and how development standards may be flexed under cl 4.6. The Plan also references a requirement under the Environmental Planning and Assessment Regulation 2021 for a document to be provided with applications that rely on cl 4.6(3) justifications (cl 4.6(3) Note).
Heritage Act 1977 and Heritage Council
Where heritage items, Aboriginal objects, heritage conservation areas or archaeological sites are involved, the Plan requires consent and prescribes notification and consultation procedures with the Heritage Council for archaeological sites and State heritage demolition, and with Aboriginal communities for Aboriginal places (cl 5.10(2), (7)-(9)). The Plan also incorporates the Heritage Map and Schedule 5 for heritage listings.
Local Government Act 1993
The Plan enables the Council to classify or reclassify public land as operational or community land in accordance with the Local Government Act 1993, and notes the Governor’s approval requirement for the discharge of trusts when inserting land into Part 2 of Schedule 4 (cl 5.2(1)-(5) and accompanying note). The Plan uses the Local Government Act definition of public place for Schedule 2 Street art and elsewhere (sch 2; cl 4.5(11)).
Building Code of Australia and BASIX
Exempt and complying development must meet relevant deemed-to-satisfy provisions of the Building Code of Australia; BASIX commitments cannot be contravened under cl 4.6(8)(b) (cl 3.1(3)(a); cl 3.2(3)(b); cl 4.6(8)(b)).
Graffiti Control Act 2008
Schedule 2 notes that street art may still engage graffiti offences and cross-references Part 2 of the Graffiti Control Act 2008 for related offences (sch 2 Note).
Land Acquisition (Just Terms Compensation) Act 1991
Clause 5.1 identifies which State authority would be the relevant acquisition authority under the owner-initiated acquisition provisions of the Land Acquisition (Just Terms Compensation) Act 1991, and notes the obligation to acquire where delay would cause hardship referred to in s 23 of that Act (cl 5.1(1)-(3) and Note).
Pipelines Act 1967, Local Land Services Act 2013, Rural Fires Act 1997 and other specialist laws
The Plan references special purpose legislation for exemptions or interactions: pipelines licensed under the Pipelines Act are excepted in public bushland disturbance exemptions (cl 5.15(4)(a)); clearing authorised under the Local Land Services Act 2013 s60O is not captured by cl 5.15(6); bush fire hazard reduction authorised by Rural Fires Act 1997 may be carried out without consent (cl 5.11).
Transport and infrastructure SEPP
The Plan defers to State SEPP (Transport and Infrastructure) Chapter 2 in respect of public authority development and use of Crown buildings (cl 5.12).
Threatened species, wilderness and marine protection laws
The Plan excludes some types of development from the complying development pathway where land is critical habitat for threatened species, wilderness areas, designated development, items on the State Heritage Register, or environmentally sensitive areas, linking back to the Threatened Species Conservation Act 1995, Wilderness Act 1987 and related instruments (cl 3.2 Note; cl 3.3).
Flood and climate adaptation guidance
Flood planning clause refers expressly to the Considering Flooding in Land Use Planning Guideline and the Flood Risk Management Manual (cl 5.14(4)-(5)) and requires consent authorities to consider projected changes to flood behaviour as a result of climate change (cl 5.14(2)-(3)).
Operational effect
The practical effect is that applicants and the Council must navigate multiple statutory regimes when assessing or delivering development: the Plan sets local policy and mapped controls but relies on other statutes for technical standards, enforcement mechanisms, and specialised consultation. The Plan repeatedly states that certain matters are not part of its text, for example maps and schedules must be available and are subject to standard technical requirements (cl 1.7 Note). Where conflicts arise, SEPPs that prevail over the Plan and provisions of the Act and other statutes will determine the legal outcome (cl 1.9(1)).
Amendment history
The Plan text contains inline amendment notes that identify which clauses were amended and when, as recorded in the instrument’s annotations. The following is a clause-by-clause extraction of the amendment notes contained in the provided text.
General commencement and numbering
Clause 1.1 notes the Plan’s name but no amendment note attached. Clause 1.1AA states the Plan commences on publication on the NSW legislation website.
Aims and maps
Clause 1.2 is annotated with amendments: Am 2019 (621), Sch 4.1[1]; 2020 (724), Sch 2[1]. This indicates the aims clause was amended in 2019 and 2020 as noted.
Clause 1.7 contains an amendment note: Am 2019 (621), Sch 4.1[2]. This suggests modifications to the maps provision in 2019.
Repeals, savings and SEPP interaction
Clause 1.8A (savings for development applications) has an extensive amendment history: Am 2018 (488), Sch 1.3 [1]; 2019 (621), Sch 5[1]; 2021 (412), Sch 1[1] [2]; 2023 (524), Sch 1.1[2]; 2023 (609), Sch 2.1. That shows multiple amendments and additions to the savings regime across 2018-2023.
Clause 1.9 was amended: Am 2019 (621), Sch 4.1[3].
Part 2 and Land Use Table
Clause 2.3 amended: Am 2019 (621), Sch 4.1[4].
The Land Use Table notes amendments in 2017, 2022 and 2022 (two items): Am 2017 (726), Sch 2.6[1]; 2022 (72), Sch 1.57[1]; 2022 (629), Sch 3.20[1].
Clause 4.6 amended: Am 2019 (621), Sch 4.1[7]; 2023 (524), Sch 1.1[1]. Note that clauses 4.1 and 4.1AA indicate "Not adopted" or "Not applicable" and show no amendment notes.
Part 5 and miscellaneous
Clause 5.1 has amendment notes: Am 2019 (621), Sch 4.1[9] [10]; 2020 No 30, Sch 4.102[1]; 2024 (42), Sch 1.42.
Clause 5.2 amended: Am 2019 (621), Sch 4.1[11] [12].
Clause 6.3 public utility infrastructure and 6.4 design excellence are present with no explicit amendment tags in the text provided.
Clause 6.5 car parking ancillary was amended: cl 6.5 Am 2017 (493), Sch 1.2 [2].
Schedules and miscellaneous notes
Schedule 2 has amendment notes: sch 2 Am 2017 (751), Sch 1.2; 2020 No 30, Sch 4.102[2]. The Street art item in sch 2 is present.
Schedule 3 amended: sch 3 Am 2017 (269), Sch 3.
Schedule 4 and 5 are present; cl 5.2 notes amendments in 2019. Schedule 5 (heritage) was blank when the Plan was made.
These inline notes are the only amendment history supplied in the Plan text. No consolidated history, commencement dates for the original instrument or explanatory materials are included in the supplied text. The amendment notes indicate an active amendment pattern across 2017-2024 covering items such as exempt and complying development, SEPP interactions, heritage, flood planning and public bushland provisions.
Litigation history
The Plan text contains no citations to court decisions or litigation. It does not list any judicial consideration of its provisions, nor does it reference case law. Schedule 5 is blank with respect to heritage listings and no legal proceedings are recorded in the text. Where the Plan requires consultation or notification (for example to the Heritage Council or local Aboriginal communities, cl 5.10(7)-(9)), it prescribes procedural steps but does not include any recorded litigation outcomes.
Because the instrument does not supply a litigation history or references to judicial interpretation, users seeking to understand how the Plan has been interpreted in courts or tribunals must consult external sources: administrative review decisions, tribunal or court judgments and appeal records under the Environmental Planning and Assessment Act. Those materials are not part of the Plan text supplied and are not described here.
Gotchas
The Plan contains numerous specific provisions and cross-references whose practical effects can be surprising or create traps for practitioners and applicants. This section sets out concrete "gotchas" drawn from the Plan text.
Mapped controls govern key outcomes
Height and FSR are determined by maps (cl 4.3; cl 4.4). Applicants must check the Height of Buildings Map and Floor Space Ratio Map; there are no numerical maxima in the text itself. Failure to read the maps or to apply the mapped numbers correctly will undermine a development application.
FSR uplift is conditional and specific
The Plan allows FSR to exceed the mapped maximum by up to 0.6:1 only when the total floor area used as social housing premises is equal to or greater than 110 per cent of the site area (cl 4.4(2A)). Social housing premises references the Residential Tenancies Act 2010 (cl 4.4(2B)). Applications seeking to rely on this uplift must provide verifiable floor area calculations and ensure the social housing definition is met; partial or mixed-use arrangements that do not satisfy the 110 per cent threshold will not qualify.
Exempt development is limited and excludes sensitive sites
Schedule 2 provides limited additional exempt development but cl 3.1(3)(d) excludes exempt development on land listed on the State Heritage Register or under an interim heritage order. Environmentally sensitive areas are excluded from exempt or complying development (cl 3.3). Developers cannot assume a state-wide exempt category applies if a local map or Schedule excludes it.
Street art is exempt but narrowly constrained
Street art is an exempt activity but must not project more than 30 mm, must not be signage, cannot be on a heritage item or in a heritage conservation area, and must not contain discriminatory or offensive material (sch 2). Owners and artists must still obtain any necessary permissions from building owners and statutory authorities; the Plan’s exemption does not override other laws such as the Graffiti Control Act 2008 (sch 2 Note).
Clause 6.4 requires the consent authority to be satisfied the development "exhibits design excellence" and lists matters to have regard to (cl 6.4(3)-(4)). That standard is evaluative and leaves scope for discretionary assessment. Projects must be prepared with comprehensive design documentation addressing the matters listed to reduce risk of refusal on subjective grounds.
Music protections are limited to licensed premises and noise
Clause 5.13 prevents refusal of consent on certain music and entertainment grounds for licensed premises but does not permit unconstrained noise. The consent authority must still be satisfied that noise can be managed to an acceptable level (cl 5.13(2)). The protection does not remove the need for acoustic strategies or compliance with noise standards.
Heritage and Aboriginal consultation can delay approvals
The consent authority must notify the Heritage Council for certain archaeological sites and nominated State heritage items and must notify and consider local Aboriginal community responses for Aboriginal places (cl 5.10(7)-(9)). These requirements can add strict timeframes (for example a 28 day consultation window is specified for Heritage Council responses) and may necessitate heritage management documents or conservation management plans (cl 5.10(5)-(6)).
Acid sulfate soils management plan requirement
Works in mapped acid sulfate soils classes require an acid sulfate soils management plan in accordance with the Acid Sulfate Soils Manual and its provision to the consent authority before consent is granted (cl 6.1(2)-(3)). A preliminary assessment can negate the requirement but must be confirmed by the consent authority (cl 6.1(4)). Public authority emergency and minor works are excepted but with monetary thresholds and measures (cl 6.1(5)).
Subdivision limits for secondary dwellings and lot sizes
A subdivision creating separate lots such that a principal dwelling and a secondary dwelling are separated is prohibited unless resultant lots are at least the minimum size shown on the Lot Size Map (cl 2.6(2)). Secondary dwellings cannot be separated from principal dwellings without observing mapped lot size minima.
Car parking maxima are low
The car parking rates for residential accommodation are low by typical suburban standards (for example 0.4 spaces per one bedroom dwelling; 0.8 per two bedroom; 1.1 for all other dwellings, cl 6.5(4)(a)). Developers who plan on providing more private parking will face a maximum cap and possible pressure to provide alternative transport measures.
Exclusions from exceptions-to-development-standards
Clause 4.6 allows the consent authority to permit contraventions of development standards on grounds of unreasonableness or unnecessary compliance, but specifically excludes development standards for complying development, BASIX commitments and clause 5.4 standards (cl 4.6(8)). Applicants cannot use cl 4.6 to vary those excluded standards.
Maps and technical datasets required
Clause 1.7 ties maps to Standard technical requirements for LEP maps and LEP GIS data. Practitioners must ensure they are referencing the current electronic or paper maps as amended from time to time (cl 1.7(1)-(3)).
Saving provisions can lock applications to an earlier policy
Clause 1.8A contains multiple savings provisions tying development applications lodged before certain amendments to the rules as they stood at that time. Applicants and advisers must check whether a DA was made before the commencement of a specific SEPP amendment to determine which version applies to that DA (cl 1.8A(1)-(6)).
Public land reclassification consequences
Reclassification of public reserves as operational land can discharge trusts except where Column 3 of Part 2 of Schedule 4 preserves them, and Governor approval is required for certain discharges (cl 5.2(4)-(5) and accompanying note). The note warns that reclassification may have legal consequences beyond planning.
Canal estate prohibition
Canal estate development is explicitly prohibited (cl 5.16). Even where a developer might argue a different classification, the Plan explicitly forbids that specific form of development.
These are concrete, textually grounded items in the Plan that can create unexpected compliance, timing, consultation or design obligations for applicants, owners and the consent authority.
How to comply
This section sets out practical steps, documentary requirements and checkpoints drawn directly from the Plan’s provisions. It is written as a compliance checklist for practitioners advising applicants, Council officers preparing assessments or community groups monitoring proposals.
Identify the site and all applicable maps
Confirm the precise land parcel(s) and consult the Land Application Map, Land Zoning Map, Floor Space Ratio Map, Height of Buildings Map, Lot Size Map, Land Reservation Acquisition Map, Heritage Map, Acid Sulfate Soils Map and any other maps referenced by the Plan (cl 1.3; cl 1.7; cl 4.3; cl 4.4; cl 4.5; cl 5.1; cl 6.1). The Plan’s controls are map-based for key standards.
Determine applicable zoning and permissibility
Check the Land Use Table for Zone R1 General Residential to determine whether the proposed use is permitted without consent, permitted with consent or prohibited (cl 2.3; Land Use Table). If the use is not listed, item 3 of the Land Use Table covers "Any other development not specified in item 2 or 4".
Establish the correct approval pathway
If the development matches an exempt item in Schedule 2 and meets the Part 3 criteria (including Building Code compliance and not on State Heritage Register) it can proceed as exempt development (cl 3.1(2)-(5); sch 2).
If the development fits a Part 1 item in Schedule 3 and meets its standards and Part 3 conditions, assess whether a complying development certificate is appropriate (cl 3.2(2)-(4); sch 3).
If not exempt or complying, lodge a development application for development consent under the Act as the Plan requires for many works (cl 2.6; cl 2.7; cl 5.10(2)).
Check for special site constraints and required management plans
Heritage: If the site is or is near a heritage item, heritage conservation area, Aboriginal place or archaeological site, plan to provide a heritage management document or heritage conservation management plan if requested (cl 5.10(4)-(6)). For archaeological sites and State heritage items, prepare for notification to the Heritage Council and factor in a 28 day response period (cl 5.10(7), (9)). For Aboriginal places, undertake adequate investigation and notify local Aboriginal communities, allowing time for responses (cl 5.10(8)).
Acid sulfate soils: If the Acid Sulfate Soils Map classifies the land, a preliminary assessment or an acid sulfate soils management plan is required and must be provided before consent is granted unless the Council confirms no plan is required (cl 6.1(2)-(4)). Public authority works may be excepted if urgent or minor (cl 6.1(5)).
Environmentally sensitive areas: Exempt and complying development may be unavailable if the site is within an environmentally sensitive area (cl 3.3).
Public bushland: If development will disturb public bushland, ensure the proposal minimises disturbance, demonstrates essential purpose and provides remediation measures (cl 5.15(2)-(5)). For recreational uses without consent, a plan of management adopted by Council is required (cl 5.15(5)).
Address design excellence
For new buildings or external alterations, prepare a design statement and drawings that address the matters listed in cl 6.4(4): material quality, public domain improvement, view corridors, bulk and modulation, shadowing, sustainable design, and access. The consent authority must be satisfied the proposal exhibits design excellence (cl 6.4(3)-(4)).
Prepare noise and performance management where relevant
For licensed premises, although refusal cannot be founded on the type of music, dancing or similar grounds (cl 5.13(1)), the consent authority must be satisfied noise can be managed to an acceptable level (cl 5.13(2)). Provide acoustic reports and noise management strategies.
Address infrastructure availability and car parking
Demonstrate that essential public utility infrastructure (water, electricity, sewerage) is available or that adequate arrangements exist for availability when required (cl 6.3(1)). For car parking, calculate the maximum permitted number of on-site spaces (cl 6.5(2)-(4)) and, if proposing additional reserved spaces, apply the reserved car parking rules in cl 6.5(5).
Floor space ratio and site area calculations
Apply the Plan’s rules for calculation of floor space ratio and site area, including exclusion rules and the treatment of strata lots, community land and public places (cl 4.5(2)-(7)). Anticipate a covenant condition preventing "double dipping" of floor space when development spans multiple lots (cl 4.5(9)-(10)). If seeking the social housing uplift, document that the social housing floor area equals or exceeds 110 per cent of the site area and confirm the units meet the Residential Tenancies Act social housing definition (cl 4.4(2A)-(2B)).
If proposing to contravene a development standard
Where proposing development that would contravene a development standard, prepare the written demonstration required by cl 4.6(3), showing that compliance is unreasonable or unnecessary and that sufficient environmental planning grounds justify the contravention. Attach the document mandated by the EPA Regulation as noted in cl 4.6(3) Note. Be aware that cl 4.6 does not apply to excluded standards in cl 4.6(8).
Heritage demolition and removal
If proposing demolition or substantial alteration of a heritage item or Aboriginal place, ensure the application includes heritage justification and consult requirements are met; the consent authority can require conservation works as conditions and must consider heritage impacts (cl 5.10(2)-(6), (10)).
Consult early with the consent authority and other agencies
Given the Plan’s notification requirements, consult early with the Council and, where necessary, the Heritage Council, local Aboriginal communities, Fire and Rescue NSW and utility providers. Early engagement can clarify whether a management plan is needed and may prevent avoidable delays (cl 5.8; cl 5.10; cl 6.1; cl 6.3).
Check saving provisions for existing DAs
If a development application was lodged before a particular amendment commenced, determine whether that application is protected by the Plan’s saving provisions in cl 1.8A. The clause lists several cases where amendments do not apply to DAs made but not determined before commencement.
Register covenants and discharge trusts where required
Be prepared for consent conditions that require covenant registration to prevent creation of floor area on a restricted lot (cl 4.5(9)-(10)) or, if proposing changes to classification of public reserves, for Governor approval and the legal mechanisms to discharge trusts to be navigated (cl 5.2(5) Note).
Timing and work-hour conditions
For specific complying development such as certain fire alarm conversions, note that building work may be limited by time-of-day conditions in the complying development certificate (cl 5.8(4)).
Retain cross-checks against other statutes
Ensure compliance with Building Code of Australia requirements (cl 3.1(3)(a); cl 3.2(3)(b)), BASIX commitments, the Heritage Act, Graffiti Control Act and other referenced laws; exempt or complying classification under this Plan does not relieve compliance with other Acts or local approvals.
Following these steps aligns a proposal with the Plan’s mapped controls, procedural obligations and documentary expectations. Practitioners should rely on the Council for confirmation of map status and staging, and should record all submissions, notifications and confirmations that the Plan requires before consent is granted.
The Dictionary at the end of this Plan defines words and expressions for the purposes of this Plan.
1 Notes
1 Notes
1.5 Notes
Notes in this Plan are provided for guidance and do not form part of this Plan.
1 Consent authority
1 Consent authority
1.6 Consent authority
The consent authority for the purposes of this Plan is (subject to the Act) the Council.
Note—
The City of Sydney Act 1988 constitutes the Central Sydney Planning Committee which has and may exercise the functions of the Council under Parts 4, 5, 6 and 8 of the Act in relation to the carrying out of major development, to the exclusion of the Council.
1 Maps
1 Maps
1.7 Maps
(1) A reference in this Plan to a named map adopted by this Plan is a reference to a map by that name—
(a) approved by the local plan-making authority when the map is adopted, and
(b) as amended or replaced from time to time by maps declared by environmental planning instruments to amend or replace that map, and approved by the local plan-making authority when the instruments are made.
(2) Any 2 or more named maps may be combined into a single map. In that case, a reference in this Plan to any such named map is a reference to the relevant part or aspect of the single map.
(3) Any such maps are to be kept and made available for public access in accordance with arrangements approved by the Minister.
(4) For the purposes of this Plan, a map may be in, and may be kept and made available in, electronic or paper form, or both.
Note—
The maps adopted by this Plan are to be made available on the official NSW legislation website in connection with this Plan. Requirements relating to the maps are set out in the documents entitled Standard technical requirements for LEP maps and Standard requirements for LEP GIS data which are available on the Department of Planning’s website.
cl 1.7: Am 2019 (621), Sch 4.1[2].
1 Repeal of planning instruments applying to land
1 Repeal of planning instruments applying to land
1.8 Repeal of planning instruments applying to land
(1) All local environmental plans and deemed environmental planning instruments applying only to the land to which this Plan applies are repealed.
(2) All local environmental plans and deemed environmental planning instruments applying to the land to which this Plan applies and to other land cease to apply to the land to which this Plan applies.
Note—
The Leichhardt Local Environmental Plan 2000 ceases to apply to land to which this Plan applies as a consequence of this Plan.
1 Savings provisions relating to development applications
1 Savings provisions relating to development applications
1.8A Savings provisions relating to development applications
(1) If a development application has been made before the commencement of this Plan in relation to land to which this Plan applies and the application has not been finally determined before that commencement, the application must be determined as if this Plan had not commenced.
Note—
However, under Division 3.5 of the Act, a development application may be made for consent to carry out development that may only be carried out if the environmental planning instrument applying to the relevant development is appropriately amended or if a new instrument, including an appropriate principal environmental planning instrument, is made, and the consent authority may consider the application. The Division requires public notice of the development application and the draft environmental planning instrument allowing the development at the same time, or as closely together as is practicable.
(2) The amendments made to this Plan by State Environmental Planning Policy Amendment (Artisan Food and Drink Industries) 2018 and State Environmental Planning Policy Amendment (Land Use Terms) 2018 do not apply to a development application made but not determined before the commencement of those amendments.
(3) The amendments made to this plan by State Environmental Planning Policy Amendment (Flood Planning) 2021 do not apply to a development application made but not finally determined before 14 July 2021.
(4) The amendments made to this plan by Sydney Local Environmental Plan Amendment (Flood Planning) 2021 extend to a development application made on or after 14 July 2021.
(5) A development application made, but not finally determined, before the commencement of State Environmental Planning Policy Amendment (Exceptions to Development Standards) 2023 must be determined as if that policy had not commenced.
(6) A development application made, but not finally determined, before the commencement of State Environmental Planning Policy Amendment (Flood Planning) 2023 must be determined as if that policy had not commenced.
(1) This Plan is subject to the provisions of any State environmental planning policy that prevails over this Plan as provided by section 3.28 of the Act.
(2) The following State environmental planning policies (or provisions) do not apply to the land to which this Plan applies—
State Environmental Planning Policy No 1—Development Standards
State Environmental Planning Policy No 4—Development Without Consent and Miscellaneous Exempt and Complying Development (clause 6 and Parts 3 and 4)
State Environmental Planning Policy No 60—Exempt and Complying Development
Direction—
Additional instruments (or provisions of instruments) may be added if the relevant instrument or provision is covered by this Plan.
cl 1.9: Am 2019 (621), Sch 4.1[3].
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
Part 2 Permitted or prohibited development
2 Land use zones
2 Land use zones
2.1 Land use zones
The land use zones under this Plan are as follows—
Residential Zones
R1 General Residential
2 Zoning of land to which Plan applies
2 Zoning of land to which Plan applies
2.2 Zoning of land to which Plan applies
For the purposes of this Plan, land is within the zones shown on the Land Zoning Map.
2 Zone objectives and Land Use Table
2 Zone objectives and Land Use Table
2.3 Zone objectives and Land Use Table
(1) The Land Use Table at the end of this Part specifies for each zone—
(a) the objectives for development, and
(b) development that may be carried out without development consent, and
(c) development that may be carried out only with development consent, and
(d) development that is prohibited.
(2) The consent authority must have regard to the objectives for development in a zone when determining a development application in respect of land within the zone.
(3) In the Land Use Table at the end of this Part—
(a) a reference to a type of building or other thing is a reference to development for the purposes of that type of building or other thing, and
(b) a reference to a type of building or other thing does not include (despite any definition in this Plan) a reference to a type of building or other thing referred to separately in the Land Use Table in relation to the same zone.
(4) This clause is subject to the other provisions of this Plan.
Notes—
cl 2.3: Am 2019 (621), Sch 4.1[4].
2
1
Schedule 1 sets out additional permitted uses for particular land.
2
2
Schedule 2 sets out exempt development (which is generally exempt from both Parts 4 and 5 of the Act). Development in the land use table that may be carried out without consent is nevertheless subject to the environmental assessment and approval requirements of Part 5 of the Act.
2
3
Schedule 3 sets out complying development (for which a complying development certificate may be issued as an alternative to obtaining development consent).
2
4
Clause 2.6 requires consent for subdivision of land.
2
5
Part 5 contains other provisions which require consent for particular development.
2 Unzoned land
2 Unzoned land
2.4 Unzoned land
(1) Development may be carried out on unzoned land only with development consent.
(2) Before granting development consent, the consent authority—
(a) must consider whether the development will impact on adjoining zoned land and, if so, consider the objectives for development in the zones of the adjoining land, and
(b) must be satisfied that the development is appropriate and is compatible with permissible land uses in any such adjoining land.
2 Additional permitted uses for particular land
2 Additional permitted uses for particular land
2.5 Additional permitted uses for particular land
(1) Development on particular land that is described or referred to in Schedule 1 may be carried out—
(a) with development consent, or
(b) if the Schedule so provides—without development consent,
in accordance with the conditions (if any) specified in that Schedule in relation to that development.
(2) This clause has effect despite anything to the contrary in the Land Use Table or other provision of this Plan.
2 Subdivision—consent requirements
2 Subdivision—consent requirements
2.6 Subdivision—consent requirements
(1) Land to which this Plan applies may be subdivided, but only with development consent.
Note—
If a subdivision is identified as exempt development in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, the Act enables it to be carried out without development consent.
(2) Development consent must not be granted for the subdivision of land on which a secondary dwelling is situated if the subdivision would result in the principal dwelling and the secondary dwelling being situated on separate lots, unless the resulting lots are not less than the minimum size shown on the Lot Size Map in relation to that land.
Note—
The definition of secondary dwelling in the Dictionary requires the dwelling to be on the same lot of land as the principal dwelling.
2 Demolition requires development consent
2 Demolition requires development consent
2.7 Demolition requires development consent
The demolition of a building or work may be carried out only with development consent.
Note—
If the demolition of a building or work is identified in an applicable environmental planning instrument, such as this Plan or State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, as exempt development, the Act enables it to be carried out without development consent.
2 Temporary use of land
2 Temporary use of land
2.8 Temporary use of land
(1) The objective of this clause is to provide for the temporary use of land if the use does not compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land.
(2) Despite any other provision of this Plan, development consent may be granted for development on land in any zone for a temporary use for a maximum period of 52 days (whether or not consecutive days) in any period of 12 months.
(3) Development consent must not be granted unless the consent authority is satisfied that—
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with this Plan and any other applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition in which it was before the commencement of the use.
(4) Despite subclause (2), th