State Environmental Planning Policy (Exempt and Complying Development Codes) 2008
Schedule 9Conditions applying to complying development certificates under the Demolition Code
Start here
Get a plain-English read of Schedule 9
Turn the raw legal text into a practical explanation grounded in State Environmental Planning Policy (Exempt and Complying Development Codes) 2008.
Schedule 9 Conditions applying to complying development certificates under the Demolition Code
Schedule 9 Conditions applying to complying development certificates under the Demolition Code
(Clause 7.3)
Note 1.
Complying development under the Demolition Code must comply with the requirements of the Act, the Environmental Planning and Assessment Regulation 2000 and the conditions listed in this Schedule.
Note 2.
Division 2A of Part 7 of the Environmental Planning and Assessment Regulation 2000 specifies conditions to which certain complying development certificates are subject.
Note 3.
In addition to the requirements specified for development to be complying development under this Policy, adjoining owners’ property rights, applicable common law and other legislative requirements for approvals, licences, permits and authorities still apply.
Note 4.
If the development is in the proximity of infrastructure (including water, stormwater or sewer mains, electricity power lines and telecommunications facilities), the relevant infrastructure authority should be contacted before commencing the development.
Note 5.
Under section 4.29 of the Environmental Planning and Assessment Act 1979 a complying development certificate lapses 5 years after the date endorsed on the certificate, unless the development has physically commenced on the land during that period.
sch 9: Ins 2013 (706), Sch 1 [184]. Am 2017 (270), Sch 1 [59] [60]; 2018 (68), Sch 2 [1]; 2021 (16), Sch 1[133] [134].