CTHIn ForceLegislation
Renewable Energy (Electricity) Regulations 2001
15AElectricity omitted from calculation
Start here
Get a plain-English read of 15A
Turn the raw legal text into a practical explanation grounded in Renewable Energy (Electricity) Regulations 2001.
#### 15A Electricity omitted from calculation
When determining the amount of electricity generated by an accredited power station, the following electricity is to be omitted from all calculations under regulation 14:
(a) electricity that was generated by using an eligible renewable energy source that is not ecologically sustainable;
(b) electricity that was not used to directly meet demand for electricity;
(c) electricity generated in a power station where an approval to use an eligible energy source:
(i) is required by a Commonwealth, State, Territory or local government authority; and
(ii) the nominated person for the power station is unable to give evidence of that approval;
(d) if certificates have been created in relation to a small generation unit under section 23A of the Act—electricity that was generated by the small generation unit.
> Note: Ecologically sustainable is defined in subsection 5(1) of the Act.