This Determination replaces the 2012 rules and sets technical tests for when a transmitter operating under a 2.5 GHz spectrum licence causes “unacceptable” interference. It prescribes power and antenna-height limits, a precise device‑boundary calculation using propagation models and digital elevation data, and special rules for active antenna systems (AAS).
Who is affected: spectrum licensees and any party operating transmitters in the 2.5 GHz band — they must design, register and operate equipment so device boundaries, power, height and emission limits are met or the ACMA can refuse or amend registration.
This instrument, the Radiocommunications (Unacceptable Levels of Interference - 2.5 GHz Band) Determination 2023, replaces the 2012 Determination (see section 4) and prescribes technical criteria the Australian Communications and Media Authority (ACMA) must use when deciding whether operation of a radiocommunications transmitter under a 2.5 GHz spectrum licence could cause an “unacceptable level of interference” for the purposes of subsection 145(4) of the Radiocommunications Act 1992 (the Act) (see section 3). It commences at the start of the day after registration on the Federal Register of Legislation (section 2).
Mechanically, the instrument:
Defines the 2.5 GHz lower band (2500 MHz to 2570 MHz) and upper band (2620 MHz to 2690 MHz) and other core terms used in the calculations (section 5).
Sets quantitative thresholds and an algorithmic method to determine a “device boundary” for a transmitter (Schedule 2, item 1 and item 2). The device boundary is computed by evaluating 360 radials (0 to 359 degrees), at 100-metre increments up to 400 increments (i.e. up to 40 km), and finding the first point on each radial where a device boundary criterion (RP - MP) ≤ 0, or else the 400th increment (Schedule 2, item 1).
Specifies the device boundary criterion as RP - MP, where RP is horizontally radiated power in dBm EIRP per 30 kHz and MP comprises propagation loss, a level-of-protection constant (LOP), and a nominal receiver antenna gain (Schedule 2, item 2). The instrument requires different LOP values for Active Antenna Systems (AAS) versus other transmitters (−108 dBm/30 kHz for AAS; −116 dBm/30 kHz otherwise) (Schedule 2, item 2).
Prescribes a propagation-loss model using geodetic and terrain data (DEM-3S) and iterative Vincenty geodesic formulae to obtain exact latitude/longitude positions at each increment (Schedule 2, item 3; Schedule 3 items on effective antenna height and average ground height).
Current sections
Direct links to the current provisions in Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2023.
12
1
Name
1 Name
This is the Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2023.
2
Commencement
2 Commencement
This instrument commences at the start of the day after the day it is registered on the Federal Register of Legislation.
Note: The Federal Register of Legislation may be accessed free of charge at www.legislation.gov.au.
3
Authority
3 Authority
This instrument is made under subsection 145(4) of the Act.
4
Repeal of the Radiocommunications (Unacceptable Levels of Interference — 2.5 GHz Band) Determination 2012
4 Repeal of the Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2012
The Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2012 [F2012L02545] is repealed.
5
Definitions
5 Definitions
(1) In this instrument, unless the contrary intention appears:
2.5 GHz band means the 2.5 GHz lower band and the 2.5 GHz upper band.
2.5 GHz lower band means the frequency band 2500 MHz to 2570 MHz.
2.5 GHz spectrum licence means a spectrum licence that authorises the operation of radiocommunications devices in the 2.5 GHz band.
2.5 GHz upper band means the frequency band 2620 MHz to 2690 MHz.
AAS means a base station antenna system where the amplitude and/or phase between antenna elements is continually adjusted, resulting in an antenna pattern that varies in response to short term changes in the radio environment.
Note: AAS stands for active antenna system.
Act means the Radiocommunications Act 1992.
Australian Spectrum Map Grid means the Australian Spectrum Map Grid 2012, published by the ACMA.
Note: The Australian Spectrum Map Grid is available, free of charge, from the ACMA’s website at www.acma.gov.au.
Australian territorial sea baseline means the baseline from which the breadth of the territorial sea, or any part of the territorial sea, is to be measured under section 7 of the Seas and Submerged Lands Act 1973.
centre frequency, in relation to a radiocommunications transmitter, means the frequency midway between the lower and upper frequency limits of the transmitter’s occupied bandwidth.
DEM-3S means the dataset:
(a) with the citation “Gallant, J., Wilson, N., Tickle, P.K., Dowling, T., Read, A. 2009. 3 Second SRTM Derived Digital Elevation Model (DEM) Version 1.0. Record 1.0. Geoscience Australia, Canberra”; and
(b) given the persistent identifier [http://pid.geoscience.gov.au/dataset/ga/69888](http://pid.geoscience.gov.au/dataset/ga/69888);
published by Geoscience Australia.
Note: DEM-3S is available, free of charge, from Geoscience Australia using the persistent identifier. More information about DEM-3S is available, free of charge, from the Geoscience Australia website at www.ga.gov.au.
DEM-3S cell means an individual height element of the DEM-3S.
device boundary: see item 1 of Schedule 2.
device boundary criterion: see item 2 of Schedule 2.
effective antenna height: see Schedule 3.
EIRP, in relation to a radiocommunications device, means the equivalent isotropically radiated power of the device.
emission designator: see section 7.
fixed receiver means a radiocommunications receiver:
(a) located at a fixed point on land or sea; and
(b) not designed or intended for use while in motion.
fixed transmitter means a radiocommunications transmitter:
(a) located at a fixed point on land or sea; and
(b) not designed or intended for use while in motion.
GDA94 means the geodetic datum designated as the “Geocentric Datum of Australia (GDA)”, gazetted in the Commonwealth of Australia Gazette No. GN 35 on 6 September 1995, as existing on that date.
Note: Gazette No. GN 35 is available, free of charge, from the Federal Register of Legislation at www.legislation.gov.au.
geographic area, for a spectrum licence, means the area within which operation of a radiocommunications device is authorised under the licence.
group of radiocommunications receivers: see section 9.
group of radiocommunications transmitters: see section 8.
horizontally radiated power, for a radiocommunications device, means the sum of:
(a) the maximum true mean power, in dBm per specified rectangular bandwidth, at the antenna connector, that is located within the frequency band of the spectrum licence authorising the operation of the radiocommunications device; and
(b) the antenna gain relative to an isotropic antenna in a specified direction in the horizontal plane containing the phase centre of the antenna used with the radiocommunications device, in dBi.
location: see Schedule 1.
maximum true mean power means the true mean power measured in a specified rectangular bandwidth that is located within a specified frequency band, such that the true mean power is the maximum of the true mean powers produced.
Note: The power within the specified rectangular bandwidth is normally established by taking measurements using either an adjacent channel power meter or a spectrum analyser. Estimation of the accuracy of the measuring equipment, the measurement protocol and any adjustments made to measurements to take account of practical filter shape factors should be in accordance with good engineering practice.
mean power means the average power measured during an interval of time that is at least 10 times the period of the lowest modulation frequency.
occupied bandwidth, in relation to a radiocommunications transmitter, means the width of a frequency band having upper and lower limits that contain 99% of the true mean power of the transmitter’s emission at any time.
Radio Regulations means the document titled ‘Radio Regulations’, published by the International Telecommunication Union.
Note 1: The Radio Regulations are not regulations made by the Governor-General under the Act.
Note 2: The Radio Regulations are available, free of charge, from the International Telecommunication Union’s website at www.itu.int.
true mean power means:
(a) if an unmodulated carrier is present – the mean power measured while the unmodulated carrier is present; or
(b) if an unmodulated carrier is not present – the mean power measured while transmitted information is present.
Note: A number of other expressions used in this instrument are defined in the Act, including the following:
(2) In this instrument, unless otherwise specified, a reference to a part of the spectrum or a frequency band includes all frequencies that are greater than but not including the lower frequency, up to and including the higher frequency.
Note: This subsection means the lower number in a part of the spectrum or a frequency band is not included in the part of the spectrum or the frequency band.
6
References to other instruments
6 References to other instruments
In this instrument, unless the contrary intention appears:
(a) a reference to any other legislative instrument is a reference to that other legislative instrument as in force from time to time; and
(b) a reference to any other kind of instrument or writing is a reference to that other instrument or writing as in force or existence from time to time.
Note 1: For references to Commonwealth Acts, see section 10 of the Acts Interpretation Act 1901; and see also subsection 13(1) of the Legislation Act 2003 for the application of the Acts Interpretation Act 1901 to legislative instruments.
Note 2: All Commonwealth Acts and legislative instruments are registered on the Federal Register of Legislation.
Note 3: See section 314A of the Act.
7
Emission designator
7 Emission designator
(1) For the purpose of this instrument, the designation of a radiocommunications transmitter’s emission (emission designator) is determined using the methods specified in the Radio Regulations.
(2) For the purpose of determining the emission designator of a radiocommunications transmitter using the methods specified in the Radio Regulations, references in the Radio Regulations to “necessary bandwidth” for a given class of emission are taken to be references to the occupied bandwidth of the transmitter.
Note: At the time the ACMA made this instrument, Appendix 1 of the Radio Regulations set out the method to be used for determining the designation of a radiocommunications transmitter’s emission.
8
Group of radiocommunications transmitters
8 Group of radiocommunications transmitters
(1) For the purposes of this instrument, and subject to subsection (2), two or more fixed transmitters are a group of radiocommunications transmitters if:
(a) each transmitter has the same centre frequency and emission designator; and
(b) each transmitter is operated for the purpose of communicating with the same radiocommunications receiver or group of radiocommunications receivers; and
(c) each transmitter has an antenna of the same type, model and manufacture; and
(d) the antenna used with each transmitter is located on the same structure and within 20 metres of the phase centre of all antennas for the other transmitters within the group of radiocommunications transmitters; and
(e) the identification number assigned by the ACMA to the antenna used with each radiocommunications transmitter is the same.
Note: See section 144 of the Act, and any instrument made under that section, for the information that must be included in the Register about a spectrum licence and each radiocommunications device operated under a spectrum licence.
(2) A radiocommunications transmitter must not belong to more than one group of radiocommunications transmitters.
Note: If a radiocommunications transmitter is capable of belonging to more than one group of radiocommunications transmitters, the spectrum licensee or authorised third party may nominate one group for the transmitter.
9
Group of radiocommunications receivers
9 Group of radiocommunications receivers
(1) For the purposes of this instrument, and subject to subsection (2), two or more fixed receivers are a group of radiocommunications receivers if:
(a) each receiver is operated for the purpose of communicating with the same radiocommunications transmitter or group of radiocommunications transmitters; and
(b) each receiver has an antenna of the same type, model and manufacture; and
(c) the antenna used with each receiver is located on the same structure and within 20 metres of the phase centre of all antennas for the other receivers within the group of radiocommunications receivers; and
(d) the identification number assigned by the ACMA to the antenna used with each radiocommunications receiver is the same.
Note: See section 144 of the Act, and any instrument made under that section, for the information that must be included in the Register about a spectrum licence and each radiocommunications device operated under a spectrum licence.
(2) A radiocommunications receiver must not belong to more than one group of radiocommunications receivers.
Note: If a radiocommunications receiver is capable of belonging to more than one group of radiocommunications receivers, the spectrum licensee or authorised third party may nominate one group for the receiver.
10
Unacceptable level of interference
10 Unacceptable level of interference
(1) A level of interference caused by a radiocommunications transmitter operated under a 2.5 GHz spectrum licence is unacceptable if:
(a) the operation of the transmitter results in a contravention of a core condition of the licence relating to the maximum permitted level of radio emission from the transmitter:
(i) outside the parts of the spectrum the use of which is authorised under the licence; or
(ii) outside the geographic area of the licence; or
(b) subject to subsection (2), any part of the device boundary of the transmitter lies outside of the geographic area of the licence; or
(c) the device boundary of the transmitter cannot be calculated in accordance with item 1 of Schedule 2.
(2) A level of interference mentioned in paragraph (1)(b) is not unacceptable in relation to a part of the device boundary of the radiocommunications transmitter that:
(a) lies outside the geographic area of the licence; and
(b) is connected to a radial that:
(i) is mentioned in item 1 of Schedule 2; and
(ii) does not cross over land outside the geographic area of the licence that is permanently above the Australian territorial sea baseline.
(3) A level of interference caused by a radiocommunications transmitter operated under a 2.5 GHz spectrum licence is unacceptable if the operation of the transmitter results in emissions above the horizontal plane greater than 45 dBm/30 kHz EIRP.
(4) A level of interference caused by a radiocommunications transmitter operated under a 2.5 GHz spectrum licence is unacceptable if the transmitter:
(a) operates in the 2.5 GHz lower band; and
(b) has an effective antenna height greater than 10 metres.
(5) This section does not apply in relation to a radiocommunications transmitter to which section 12 applies.
Note Subsection 145(1) of the Act provides that the ACMA may refuse to include in the Register details of a radiocommunications transmitter if the ACMA is satisfied that operation of the transmitter could cause an unacceptable level of interference to the operation of other radiocommunications devices. However, some radiocommunications transmitters are exempt from the requirement to be registered in the Register under their 2.5 GHz band spectrum licence – see subsection 69(2) of the Act.
11
Accuracy
11 Accuracy
Unless otherwise specified, the value of a parameter in Schedules 2 and 3 must be estimated with a level of confidence not less than 95 percent that the true value of the parameter will always remain below the requirement specified in this instrument.
12
Transitional — radiocommunications transmitter registered before commencement of this instrument
12 Transitional – radiocommunications transmitter registered before commencement of this instrument
(1) If a radiocommunications transmitter was included in the Register in relation to a 2.5 GHz band spectrum licence before the commencement of this instrument (relevant transmitter), this section applies in relation to that transmitter.
(2) Subject to subsection (3), for the purposes of subsection 145(4) of the Act, a level of interference caused by a relevant transmitter is unacceptable if it would have been unacceptable under the Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2012, as in force at the time the relevant transmitter was included in the Register.
Note: The Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2012 is available, free of charge, from the Federal Register of Legislation at www.legislation.gov.au.
(3) For the purposes of subsection 145(4) of the Act, if:
(a) after the commencement of this instrument, both:
(i) a detail of a relevant transmitter changes (relevant change); and
(ii) the change to the detail is recorded in the Register; and
(b) the distance of the new device boundary of the relevant transmitter is, on each radial mentioned in item 1 of Schedule 2, equal to or less than the distance of the old device boundary of the relevant transmitter on that radial; and
(c) but for the effect of this subsection, a level of interference caused by the relevant transmitter, immediately after the change time, would be unacceptable;
the level of interference caused by the relevant transmitter, immediately after the change time, is not unacceptable because of the relevant change.
(4) In subsection (3):
change time, for a relevant transmitter, means the time the relevant change is recorded in the Register.
new device boundary, of a relevant transmitter, means the device boundary of the transmitter established immediately after the change time, in accordance with this instrument as in force at the change time.
old device boundary, of a relevant transmitter, means the device boundary of the transmitter established immediately before the change time, in accordance with the Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2012, as in force at the registration time.
registration time, for a relevant transmitter, means the time the transmitter was included in the Register.
Source text: opening excerpt
Sourced from the Federal Register of Legislation (legislation.gov.au), CC BY 4.0.
1 Name
1 Name
This is the Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2023.
2 Commencement
2 Commencement
This instrument commences at the start of the day after the day it is registered on the Federal Register of Legislation.
Note: The Federal Register of Legislation may be accessed free of charge at www.legislation.gov.au.
3 Authority
3 Authority
This instrument is made under subsection 145(4) of the Act.
4 Repeal of the Radiocommunications (Unacceptable Levels of Interference — 2.5 GHz Band) Determination 2012
4 Repeal of the Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2012
The Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2012 [F2012L02545] is repealed.
5 Definitions
5 Definitions
(1) In this instrument, unless the contrary intention appears:
2.5 GHz band means the 2.5 GHz lower band and the 2.5 GHz upper band.
2.5 GHz lower band means the frequency band 2500 MHz to 2570 MHz.
2.5 GHz spectrum licence means a spectrum licence that authorises the operation of radiocommunications devices in the 2.5 GHz band.
2.5 GHz upper band means the frequency band 2620 MHz to 2690 MHz.
AAS means a base station antenna system where the amplitude and/or phase between antenna elements is continually adjusted, resulting in an antenna pattern that varies in response to short term changes in the radio environment.
Note: AAS stands for active antenna system.
Act means the Radiocommunications Act 1992.
Australian Spectrum Map Grid means the Australian Spectrum Map Grid 2012, published by the ACMA.
Note: The Australian Spectrum Map Grid is available, free of charge, from the ACMA’s website at www.acma.gov.au.
Australian territorial sea baseline means the baseline from which the breadth of the territorial sea, or any part of the territorial sea, is to be measured under section 7 of the Seas and Submerged Lands Act 1973.
Deems interference unacceptable where operation results in contravention of licence core conditions relating to emissions outside authorised spectrum or geographic area, where any part of the device boundary lies outside the licence geographic area (subject to a narrow exception), where emissions above the horizontal plane exceed 45 dBm/30 kHz EIRP, or where a transmitter in the lower band has effective antenna height greater than 10 metres (section 10).
Imposes measurement and model accuracy requirements: parameter estimates in Schedules 2 and 3 must be made with at least 95% confidence that the true value will remain below the requirement (section 11); location measurement error must be less than 10 metres (Schedule 1, location); and antenna vertical height hgt must be measured with error less than 5 parts in 100 (Schedule 3, item 1(1)(a)).
Preserves transitional protection for transmitters registered against the 2012 Determination: for transmitters registered prior to commencement, the 2012 test applies unless a change is recorded in the Register and the new device boundary is on each radial equal to or less than the old device boundary (section 12).
In short, the Determination creates a prescriptive, computational procedure (terrain-informed, geodetic and radiometric) to produce a device boundary and a set of bright-line limits (EIRP above horizontal, effective antenna height in the lower band, device boundary crossing geographic area) that trigger a finding of “unacceptable interference” under s145(4) of the Act. The ACMA’s Register and its powers under the Act are the enforcement locus referenced in the instrument (notes to sections 8, 9 and 10; section 3).
Main concepts
The instrument’s core technical concepts are device boundary, device boundary criterion (RP - MP), horizontally radiated power (RP), mean protection level (MP), effective antenna height, DEM-3S-based terrain averaging, AAS treatment, and rigorous geodesic positioning. The definitions in section 5 and the Schedules define these precisely.
Device boundary: For each fixed transmitter (or group treated as one transmitter), the device boundary is the polygon formed by a set of radial end points, one per degree (n = 0 to 359). Along each radial the instrument evaluates up to 400 increments of m×100 metres; the end point is the first increment where the device boundary criterion RP - MP ≤ 0, or the 400th increment otherwise (Schedule 2, item 1). The device boundary therefore depends on power, antenna gain pattern, propagation loss, nominal receiver gain, and the LOP.
Device boundary criterion, RP - MP: RP is horizontally radiated power in dBm EIRP per 30 kHz for each bearing σn. The instrument specifies how RP is calculated for conventional systems and for AAS (Schedule 2, item 2). MP equals PL(lmn, Lmn) + LOP − Gr where PL is the propagation loss calculated via the propagation-loss model (Schedule 2, item 2). LOP is a fixed level-of-protection: −108 dBm/30 kHz for systems that incorporate an AAS, −116 dBm/30 kHz otherwise (Schedule 2, item 2).
Horizontally radiated power (RP): RP is defined in the Schedule 2 table (item 2). It sums the true mean power at the antenna connector within the licence band and the antenna gain relative to an isotropic antenna in a specified horizontal-plane direction containing the antenna phase centre (section 5 definition). For AAS, Note 1 to Schedule 2 defines RP as antenna gain towards the horizontal plane and azimuth σn plus total radiated power in dBm, and explicitly states that this assumes dynamic control of beams and/or power to ensure RP is not exceeded.
Propagation-loss model: Schedule 2 item 3 prescribes calculation of PL(lmn, Lmn) using effective antenna height (Schedule 3) and Vincenty’s direct formulae (Schedule 3, item 3) to determine geodesic coordinates for each increment; Schedule 3 further details the average ground height calculation using DEM-3S (3-second SRTM derived DEM) aggregated by a 3 × 3 cell matrix at the DEM resolution. There are special rules for cells at particular grid alignments (modulus conditions) and for groups of transmitters (use the highest hgt in the group).
AAS distinction: The instrument treats Active Antenna Systems differently in two ways: a higher LOP (less stringent protection number, −108 dBm vs −116 dBm), and an RP definition that accounts for dynamic beamforming under the assumption the system can control beam pointing and power to keep RP below limits (Schedule 2, item 2 Note 1). The instrument thus embeds an engineering assumption about AAS controllability.
Geodetic and measurement precision: Location must be given in latitude/longitude referenced to GDA94 and measured with error under 10 metres (Schedule 1). For hgt the permitted measurement error is less than 5 parts in 100 (Schedule 3, item 1). Schedule 3 requires use of Vincenty’s formulae (GRS80 parameters) for positional calculations.
Unacceptable-interference triggers: Section 10 sets multiple independent triggers: contravention of core licence conditions regarding emissions outside authorised spectrum or geographic area; any part of the device boundary outside the licence geographic area (with a narrow exception for radials that do not cross land outside the geographic area permanently above the territorial sea baseline); emissions above the horizontal plane greater than 45 dBm/30 kHz EIRP; and operation in the lower 2.5 GHz band with effective antenna height above 10 metres. Section 12 covers transitional application for transmitters registered before commencement.
Accuracy/confidence requirement: Section 11 requires that, unless otherwise specified, parameter values in Schedules 2 and 3 be estimated with at least 95% confidence that the true value will remain below required limits. This invokes statistical confidence in modelling and measurement outputs.
Interaction with Register and other Act provisions: The instrument operates in the Register context. Notes reference section 144 (information to be included in the Register) and section 145(1) (ACMA may refuse to include transmitter details in the Register if operation could cause unacceptable interference). Section 6 states references to other instruments are to be read as in force from time to time.
Collectively, these concepts produce a deterministic, terrain-aware method to map where a transmitter’s calculated signal will meet the protection threshold (MP) and thereby define the boundary of authorised operation for interference assessment.
Who it affects
The instrument affects spectrum licence holders and authorised third parties operating radiocommunications transmitters in the 2.5 GHz band (section 5 definitions of “2.5 GHz spectrum licence” and repeated references throughout). It also affects other radiocommunications licence holders and receivers in and adjacent to the 2.5 GHz band by defining the protection levels and device boundary that govern registration and interference findings (section 10 and Schedule 2).
More specifically, affected parties include:
Operators of fixed transmitters and fixed receivers (section 5 definitions of fixed transmitter and fixed receiver): the instrument’s device boundary and effective antenna height rules apply to devices “located at a fixed point on land or sea” and “not designed or intended for use while in motion” (section 5).
Owners/operators of Active Antenna Systems (AAS): the instrument contains bespoke provisions for AAS in Schedule 2 (different LOP, explicit calculation of RP for AAS, assumption of dynamic beam/power control), so AAS operators must document and model dynamic performance to show RP compliance.
Groups of transmitters and groups of receivers: spectrum licensees that operate clusters of identical transmitters or receivers on the same structure may choose or be required to treat them as a single group under section 8 (group of radiocommunications transmitters) and section 9 (group of radiocommunications receivers). The grouping rules require same centre frequency, emission designator, same antenna model and co-location within 20 metres of each antenna phase centre, and identical ACMA antenna identification numbers (sections 8(1)(a)-(e) and 9(1)(a)-(d)). A transmitter cannot belong to more than one group (sections 8(2), 9(2)).
Parties preparing Register entries or amendments: section 12 provides a transitional regime for transmitters included in the Register before commencement. Where Register details change and the new device boundary is on each radial equal to or less than the old device boundary, the change will not make interference unacceptable if it would otherwise be (section 12(3)). Thus those seeking to change registered details must compute device boundaries before and after changes to rely on transitional protection.
Equipment vendors and testing/calculation service providers: the instrument’s technical prescription,100-metre radial increments, up to 400 increments, DEM-3S terrain height averaging, Vincenty formulas, 95% confidence estimation requirements,imposes modelling and measurement tasks that vendors and consultants will perform for licensees to demonstrate compliance.
Who pays: the instrument’s burdens fall to spectrum licensees and their authorised third parties. They must supply accurate site coordinates (measured to <10 m error), antenna heights (hgt measured to <5% error), RP values, and terrain inputs (DEM-3S). Costs include modelling, measurement, potentially lower antenna mounts or reduced power, and Register administration. The ACMA decides whether to record a transmitter on the Register and may refuse registration where operation could cause an unacceptable level of interference (note to section 10 referring to subsection 145(1) of the Act).
Geographic constraints: the device boundary must lie within the geographic area of the licence, subject to the limited exception in section 10(2). The exception concerns portions of the device boundary connected to a radial that does not cross land outside the licence area that is permanently above the Australian territorial sea baseline. The presence of this exception means coastal deployments and areas over sea/territorial waters interact with the geographic-area test, thereby affecting coastal network planning and border cases.
In short, the instrument affects technical operators, spectrum licence holders, their contractors, and other radio users whose protection depends on the device boundary and the LOPs set here.
Key duties and rights
Duties under the instrument fall primarily on 2.5 GHz spectrum licensees and authorised third parties who operate transmitters. Rights are largely procedural and protective, tied to registration status and transitional protections.
Duties (what operators must do):
Compute and record accurate transmitter location and device boundary: the location must be provided in latitude/longitude referenced to GDA94 and measured with error less than 10 metres (Schedule 1). The device boundary must be calculated per Schedule 2 item 1, evaluating the RP - MP criterion at m×100 metre increments along n-degree radials (Schedule 2 item 1).
Use specified datasets and formulas: operators must use DEM-3S (as cited in section 5 definitions) for terrain height and apply Schedule 3 procedures to compute effective antenna height and average ground height (Schedule 3, items 1 and 2). The geodesic calculations must be implemented using Vincenty’s Direct Formulae as specified (Schedule 3, item 3).
Apply the RP - MP device boundary criterion: calculate RP in dBm EIRP per 30 kHz for each bearing, determine PL(lmn, Lmn) via the propagation-loss steps, apply LOP and Gr as given, and find the radial end point where RP - MP ≤ 0 (Schedule 2 items 2 and 3).
Meet measurement and modelling accuracy/confidence requirements: parameter values in Schedules 2 and 3 are to be estimated with at least 95% confidence that the true value will remain below the requirement (section 11). Antenna height measurement error must be less than 5 parts in 100 (Schedule 3 item 1(1)(a)).
Observe bright-line operational limits: do not operate with emissions above the horizontal plane greater than 45 dBm/30 kHz EIRP (section 10(3)); do not operate in the lower 2.5 GHz band with effective antenna height greater than 10 metres (section 10(4)). Ensure operation does not cause contravention of a licence core condition regarding emissions outside authorised spectrum or geographic area (section 10(1)(a)).
Rights and procedural features for operators:
Transitional protection for previously-registered transmitters: where a transmitter was included in the Register before commencement, the instrument applies the 2012 Determination to that transmitter unless a change is recorded that increases the device boundary on any radial (section 12(2)-(3)). In effect, an operator who does not increase device boundary distances is insulated from the new Determination making interference unacceptable immediately after a change is recorded (section 12(3)).
Grouping nomination: where a transmitter could belong to more than one group, the spectrum licensee or authorised third party may nominate one group for the transmitter (notes to sections 8(2) and 9(2)). This is a procedural right to avoid overlapping group assignments.
Use of AAS rules: AAS operators have a different LOP and an explicit RP formula which allows representation of beamforming gains in the horizontal plane, subject to the instrument’s assumption that dynamic control will ensure RP is not exceeded (Schedule 2, item 2 Note 1).
Enforcement-related duties:
Register accuracy and timely notification of changes: because the ACMA’s refusal powers under s145 of the Act relate to whether operation could cause unacceptable interference, licensees must ensure Register details remain accurate and that any planned change is reflected with computed device boundaries consistent with the instrument (notes to sections 8, 9 and section 12).
Measurement protocols consistent with “good engineering practice” when measuring power and bandwidth: section 5’s definition of “maximum true mean power” refers to measurement via adjacent channel power meters or spectrum analysers and states that estimation of measuring equipment accuracy and measurement protocol should be in accordance with good engineering practice (section 5 definition note).
Decision-makers and their responsibilities:
ACMA: responsible for including transmitter details in the Register and for deciding, under s145(4) of the Act (the instrument’s authority per section 3), whether operation could cause unacceptable interference using this Determination. The instrument does not allocate new enforcement powers beyond the Act but supplies the technical test the ACMA is to apply.
In sum, operators must implement technically prescriptive modelling, measurement and record-keeping steps; they have limited procedural protections if they maintain or reduce device boundaries compared with earlier registration; and the ACMA has the decision rights under the Act, with this Determination supplying the calculus.
Penalties and enforcement
The Determination itself does not create criminal offences or civil penalty provisions; it prescribes technical criteria the ACMA will use to assess whether operation of a transmitter could cause an “unacceptable level of interference” for the purposes of subsection 145(4) of the Radiocommunications Act 1992 (sections 3 and 10). Enforcement consequences therefore derive from the Act (as noted in the instrument), not from the Determination’s text.
Key enforcement mechanisms and consequences identified in or implied by the instrument and its notes:
Register inclusion/refusal: The instrument is expressly made under subsection 145(4) of the Act (section 3). The instrument’s note to section 10 quotes subsection 145(1) of the Act: the ACMA may refuse to include details of a radiocommunications transmitter in the Register if the ACMA is satisfied that operation of the transmitter could cause an unacceptable level of interference. The Register is the statutory mechanism through which transmission operation under a spectrum licence is made known to the regulator and third parties (see the notes to sections 8 and 9 referencing section 144 of the Act for Register information requirements). Refusal to include transmitter details in the Register under the Act has practical enforcement effect because registered device details are necessary for authorised operation under a spectrum licence and for the ACMA’s control of spectrum use.
Licence core condition contraventions: Section 10(1)(a) treats as unacceptable any interference where operation results in contravention of a core condition of the licence relating to the maximum permitted level of radio emission outside authorised spectrum parts or geographic area. Contravention of core conditions of spectrum licences can attract enforcement under the Act, including notices, directions, or other remedies available to the ACMA (the Determination does not restate those remedies).
Technical prohibitions with immediate operational effect: Section 10(3) and (4) create bright-line technical triggers,emissions above the horizontal plane greater than 45 dBm/30 kHz EIRP, and operation in the 2.5 GHz lower band with effective antenna height greater than 10 metres. If operation would meet these triggers, the Determination treats that level of interference as unacceptable. ACMA would apply that finding under the Act to refuse Register inclusion or take other action authorised by the Act.
Transitional effect on enforcement: Section 12 provides a transition for transmitters registered under the 2012 Determination: until a relevant change is recorded that increases device boundary distances, the prior determination’s standards continue to govern whether interference is unacceptable. This restricts immediate application of the 2023 criteria to pre-existing registered transmitters unless they change details and thereby lose the transitional protection in section 12(3).
What the instrument does not supply:
The instrument does not set out civil penalty or criminal sanction provisions itself. It relies on the Act’s regulatory framework for enforcement. Readers must consult the Act for the specific enforcement powers, penalty regimes, and administrative processes available to the ACMA.
There is no procedural detail in the Determination on how the ACMA will audit, test, or verify modelling outputs, nor does it provide a compliance timetable or grace period for unregistered but operating transmitters other than the transitional rule in section 12.
Implementation and evidentiary implications:
The Determination imposes technically precise computation and measurement requirements (DEM-3S, Vincenty formulae, 95% confidence estimates). In enforcement contexts, the ACMA can compare declared device boundaries and associated calculations against the Determination’s procedures. That implies an evidentiary need for licensees to retain modelling inputs, measurement data, and documentation demonstrating compliance with the Accuracy rule (section 11), the location/hgt measurement tolerances (Schedule 1 and Schedule 3), and DEM-3S processing steps (Schedule 3).
The AAS assumption (Schedule 2 Note 1) that beam pointing and power can be controlled dynamically to ensure RP is not exceeded creates a compliance boundary: if an AAS operator claims the AAS meets RP limits through dynamic control, the ACMA could require method documentation or measurement evidence consistent with the Determination.
In short, the Determination supplies the technical yardstick ACMA will use within its statutory enforcement toolbox under the Act. The instrument itself leaves the actual sanctions and administrative processes to the Act and to ACMA practice.
How it interacts with other laws
The Determination is a legislative instrument made under subsection 145(4) of the Radiocommunications Act 1992 (section 3). Its legal effect is to establish the technical test the ACMA applies in relation to subsection 145(4) , whether it is satisfied that operation of a transmitter could cause an unacceptable level of interference. Interaction with other laws and instruments appears in multiple places in the Determination.
Primary interactions with the Act:
Register and ACMA powers: The Determination is tied into the Act’s Register framework. Notes to sections 8, 9 and 10 refer to section 144 (information that must be included in the Register) and subsection 145(1) (the ACMA may refuse to include details where operation could cause unacceptable interference). Thus the Determination operates as the technical standard the ACMA applies when exercising statutory powers under the Act.
Exemptions under the Act: The note to section 10 acknowledges subsection 69(2) of the Act, which exempts some transmitters from the requirement to be registered in the Register under their 2.5 GHz spectrum licence. That means the Determination’s practical effect depends in part on registration obligations and exemptions under the Act.
Cross-references to other legislative instruments and documents:
The Determination requires application of the International Telecommunication Union’s Radio Regulations when determining emission designators (section 7). It explicitly notes the Radio Regulations are not regulations made under the Act (section 5 note), and that Appendix 1 of the Radio Regulations sets out the method for emission designation (section 7 note). The Radio Regulations are therefore an external technical standard referenced by the Determination.
Section 6 adopts a conventional statutory cross-reference rule: references to other legislative instruments are to be read as in force from time to time, and references to other writings are to be read as in force or existence from time to time (section 6(a)-(b)). It explicitly points readers to the Acts Interpretation Act 1901 for Commonwealth Acts references and to section 314A of the Act.
Interaction with geodetic and terrain data regimes:
The Determination mandates use of the DEM-3S dataset (section 5 definition and Schedules). DEM-3S is a dataset published by Geoscience Australia; the Determination requires its use to compute average ground heights and thus effective antenna heights and propagation loss (Schedule 3 item 2). This embeds an interaction with the Commonwealth’s geospatial data outputs and the standards used by Geoscience Australia.
Geodetic datum: location and coordinates are required to be referenced to GDA94 (section 5). Schedule 3 states Vincenty’s Direct Formulae are to use GRS80 parameters as referenced by GDA94. This ties the Determination to specific geodetic standards used in Commonwealth mapping and cadastral systems.
Regulatory overlap and boundary areas:
Territorial sea baseline reference: section 10(2) excludes certain parts of device boundary from being unacceptable where the radial “does not cross over land outside the geographic area of the licence that is permanently above the Australian territorial sea baseline.” This creates an interaction with maritime law definitions found in the Seas and Submerged Lands Act 1973 (section 5 definition of Australian territorial sea baseline references section 7 of that Act). Coastal deployments and operations over sea therefore interact with maritime boundary definitions when applying the device boundary geographic-area test.
References to the ACMA Register and the need to include antenna identification numbers (sections 8(1)(e), 9(1)(d) and note references to section 144 of the Act) mean the Determination operates alongside ACMA’s Register rules and any instruments made under section 144 guidance.
What the Determination does not change:
It does not alter licence conditions themselves , it provides the test the ACMA applies to decide if inclusion in the Register is appropriate and whether operation would cause unacceptable interference. Enforcement and sanctions remain governed by the Act and any subsidiary regulatory instruments made under it.
It does not modify the Radio Regulations themselves; it instructs how to use the Radio Regulations for emission designators (section 7), but the international instrument remains external.
Practical consequence of these interactions:
Parties must apply the Determination in the context of the Act’s registration and enforcement regime, use the specified geodetic and terrain datasets and methods (GDA94, DEM-3S, Vincenty), and be aware that maritime/territorial sea definitions influence geographic-area assessments. The Determination’s references to other instruments mean that changes to those external instruments (for example, updates to DEM-3S or to the Radio Regulations) may affect practical application unless specifically otherwise provided.
Amendment history
This Determination expressly repeals the Radiocommunications (Unacceptable Levels of Interference - 2.5 GHz Band) Determination 2012 (see section 4). The 2012 instrument is therefore replaced for transmitters included in the Register after commencement, subject to the transitional protections in section 12 for transmitters included in the Register prior to commencement.
Key points drawn from the instrument concerning amendment and transitional arrangements:
Repeal: section 4 makes a straight repeal of the 2012 Determination [F2012L02545]. The operative text of the 2012 Determination therefore no longer applies to new registration actions after this instrument commences, unless transitional rules preserve its application for certain registered transmitters (section 12).
Commencement timing: section 2 states the instrument commences at the start of the day after the day it is registered on the Federal Register of Legislation. The Determination itself does not record the date of registration; the Register entry will therefore determine the precise commencement date.
Transitional protection for existing registered transmitters: section 12(2) provides that for radiocommunications transmitters that were included in the Register before commencement (relevant transmitters), the level of interference is unacceptable only if it would have been unacceptable under the 2012 Determination as in force at the time the transmitter was included in the Register. This preserves the earlier standard for pre-existing registered transmitters.
Change-induced re-evaluation: section 12(3) creates a conditional rule where, if a relevant change to a registered transmitter’s detail is recorded after commencement, and the new device boundary is on each of the radials equal to or less than the old device boundary, then even if the new details would otherwise cause the transmitter to be unacceptable under the new Determination immediately after the change, that level of interference is not unacceptable because of the change. This provides a degree of protection for changes that do not expand device boundary distances.
Definitions relevant to transitions: section 12(4) defines change time, new device boundary, old device boundary and registration time for the transitional rule.
What is not in the instrument’s amendment history:
The Determination does not record any previous amendments between 2012 and 2023; it simply repeals the 2012 instrument. No other prior versions or amendments are mentioned in the text supplied.
There are no amendments to the Act recorded in this instrument; it is a legislative instrument under the Act.
Practical implications for amendment treatment:
Operators with transmitters registered under the 2012 Determination should compare pre-commencement device boundaries and the post-change device boundary calculations, because the transitional rule operates on a per-radial comparison. If any radial’s device boundary increases compared with the old device boundary, transitional protection may be lost for that transmitter after a change is recorded.
The repeal and replacement approach means that the ACMA has updated its technical standard. Licence holders and third parties must check whether their registered transmitters remain compliant under the new computational method when they make changes or when registering new transmitters.
The instrument’s repeal-and-replace amendment history is therefore straightforward: 2012 Determination repealed; 2023 Determination in force from registration date; transitional rules preserve earlier standards for pre-existing registered transmitters except where changes increase device boundary distances.
Litigation history
The Determination text supplied contains no litigation history. It does not cite any cases or judicial decisions, and it does not record any litigation relating to the 2012 Determination or its application. The instrument references statutory provisions of the Act and external technical documents (DEM-3S, Radio Regulations), but no court or tribunal decisions are mentioned.
Implications for practitioners:
There is no precedent or case law in the Determination text to guide interpretation of its technical terms or transitional protections. That means the primary sources for interpretation are the Determination’s text, the Act (particularly sections 144 and 145, which are referenced in notes), and any ACMA policy or administrative guidance that may accompany the Determination (not supplied in this instrument).
Where disputes arise over how the device boundary calculations are to be carried out, or whether a transmitter’s operation causes unacceptable interference under section 10, the Determination provides detailed technical steps. Disputes will most likely turn on (1) whether an operator applied the specified DEM-3S, Vincenty and propagation-loss calculations correctly; (2) whether measurement and modelling met the Accuracy requirement in section 11; and (3) how AAS dynamic behaviour is represented relative to the assumption in Schedule 2 Note 1. Absent litigation history in the instrument, parties will need to rely on the text and, if necessary, test its interpretation before an administrative tribunal or court under existing Act-based appeal paths.
Practitioners should check ACMA’s publications and regulatory guidance (outside this Determination) for any interpretative materials, and review the Act for appeal avenues. The Determination itself makes no comment about dispute resolution or adjudicative pathways.
In summary, the instrument contains no litigation history. Any legal challenges or interpretive disputes will need to be addressed through the Act’s mechanisms and, if litigated, will create new jurisprudence not reflected in the 2023 Determination text.
Gotchas
The Determination’s technical precision produces several operationally significant edge cases and compliance traps that practitioners and operators should note. The instrument’s own text contains many of these nuances.
Lower band effective-antenna-height limit (section 10(4)): Operation in the 2.5 GHz lower band (2500-2570 MHz) with effective antenna height greater than 10 metres is deemed to cause unacceptable interference. The effective antenna height is calculated via Schedule 3 with particular DEM-3S averaging rules. A seemingly small increase in mast height or the choice of DEM cell averaging can move a transmitter from acceptable to unacceptable.
45 dBm/30 kHz EIRP above horizontal plane (section 10(3)): The Determination treats any emissions above the horizontal plane exceeding 45 dBm/30 kHz EIRP as unacceptable interference. For systems with elevation radiation (e.g. tall towers, downtilting antennas), careful measurement and control of power and antenna patterns are necessary to avoid this bright-line threshold.
Device boundary calculation granularity (Schedule 2 item 1): The device boundary uses 1-degree radials and 100-metre increments up to 400 increments. This discrete grid can produce small but material differences in calculated device boundaries depending on implementation precision, how the first increment where RP - MP ≤ 0 is identified (edge interpolation is not specified), and rounding/conversion of coordinates. Implementations must apply the prescribed Vincenty formulae (Schedule 3) and the DEM-3S cell selection rules precisely.
DEM-3S cell edge rule and modulus condition (Schedule 3 items 1(3) and 2(2)): Special handling applies where the seconds component of latitude or longitude plus 1.5 has a modulus of zero when divided by 3; then hs is sum of hgt and maximum height of adjacent DEM-3S cells, or the DEM cell to use is the adjacent cell with minimum height. These grid-alignment rules can change average-ground-height outputs for sites on certain coordinate grids, producing sudden changes in effective antenna height and device boundary outcomes.
AAS assumptions (Schedule 2 item 2 Note 1): For Active Antenna Systems the Determination defines RP on the basis that beam pointing angles and/or power can be controlled dynamically to ensure RP is not exceeded. That is an engineering assumption; an AAS operator claiming compliance on that basis must be able to evidence control logic and worst-case beam/power states. The Determination does not detail what evidence suffices.
Accuracy/confidence requirement (section 11): Parameter values in Schedules 2 and 3 must be estimated with not less than 95% confidence that the true value will always remain below the requirement. This imposes a statistical modelling burden. The Determination does not prescribe a statistical method or sampling plan; operators must adopt modelling practices that can substantiate 95% confidence levels in measurements and predictions.
Grouping constraints (sections 8 and 9): The rules for grouping transmitters/receivers require identical emission designator, centre frequency and antenna make/model, co-location within 20 metres and identical ACMA antenna identification numbers. Small differences in antenna model or placement can prevent grouping and change RP and device boundary calculations substantially for multi-antenna sites.
Lower frequency endpoints excluded per section 5(2): The instrument specifies that a reference to a part of the spectrum or frequency band includes all frequencies greater than but not including the lower frequency. This means the lower bound (e.g. 2500 MHz) is excluded. Edge-case emissions centred exactly at the lower boundary require careful interpretation to determine whether they fall within the band as applied.
Transitional protection is limited and per-radial (section 12): The transitional rule preserves the 2012 standard for previously registered transmitters unless a change increases device boundary distances on any radial. The per-radial comparison means small changes that extend the device boundary on even a single radial can expose the transmitter to the new Determination immediately.
No explicit verification or audit process set out: The Determination specifies calculation and measurement methods but does not set out ACMA’s verification process, collection of evidence, or timelines for audit. Operators should assume the ACMA may request underlying data and models to check compliance.
Maritime / territorial sea baseline nuance (section 10(2)): The exception to device boundary being outside geographic area triggers a test involving whether a radial “does not cross over land outside the geographic area of the licence that is permanently above the Australian territorial sea baseline”. That language is spatially and legally technical , coastal licensees should check maritime baseline definitions under the Seas and Submerged Lands Act 1973 and confirm whether radials are considered to cross land outside the geographic area.
External dependencies: Use of the Radio Regulations for emission designators (section 7) and reliance on DEM-3S (section 5 definitions) means changes to those external documents or their availability can affect compliance. Operators must ensure they use the versions and persistent identifiers specified.
Each of these points is grounded in the Determination text. The combination of discrete computational rules, precise geodetic and DEM processing, and bright-line operational thresholds means operators must execute calculations and measurements to the instrument’s letter to avoid unexpected findings of unacceptable interference.
How to comply
Compliance requires a disciplined combination of measurement, modelling, record-keeping and operational controls tied to the Determination’s text. Below are concrete steps an operator or compliance officer should follow, citing the relevant instrument provisions for each task.
Confirm scope and classify device type
Confirm the transmitter is a fixed transmitter in the 2.5 GHz band as defined (section 5 definitions of fixed transmitter, 2.5 GHz lower band, upper band). If mobile or exempt under subsection 69(2) of the Act, different rules may apply (note to section 10).
Determine whether the transmitter incorporates an Active Antenna System (AAS). This affects LOP (Schedule 2, item 2) and RP calculation (Schedule 2, item 2 Note 1).
Obtain authoritative datasets and standards
Use the DEM-3S dataset cited in the Determination (section 5 definition of DEM-3S) and obtain the persistent-identifier dataset from Geoscience Australia.
Use GDA94 for geodetic coordinates (section 5).
Use the Radio Regulations to determine emission designators where required (section 7).
Accurately measure site location and antenna height
Measure the location (latitude and longitude, GDA94) of the antenna phase centre to an error less than 10 metres (Schedule 1 item 3(3)).
Measure vertical antenna height hgt with an error less than 5 parts in 100 (Schedule 3 item 1(1)(a)). Document the measurement method and instrument calibrations.
Calculate effective antenna height (he) per Schedule 3
Compute hs = DEM-3S cell height at location + hgt (Schedule 3 item 1(1)(b)), with the special modulus rule if the seconds component plus 1.5 has modulus zero when divided by 3 (Schedule 3 item 1(3)).
Compute average ground height hagm at each m-increment and radial per Schedule 3 item 2: identify DEM-3S cell, bound with adjacent 8 cells, average the 3 × 3 grid heights. Apply the modulus exception in Schedule 3 item 2(2) where applicable.
Compute he per Schedule 3 item 1(1)(d)-(e). For groups of transmitters, use the greatest hgt among the group (Schedule 3 item 1(2)).
Prepare RP inputs
Determine maximum true mean power and occupied bandwidth within the licence band using good engineering practice measurement methods described in section 5 definition notes (adjacent channel power meter or spectrum analyser).
Determine antenna gain pattern in the horizontal plane (dBi) at each azimuth σn. For AAS, calculate the RP using the sum of total radiated power and the antenna gain towards the horizontal plane and azimuth σn, and ensure there is operational control to prevent RP exceedance (Schedule 2, item 2 Note 1).
Compute propagation loss PL(lmn, Lmn)
For each radial n = 0...359 and each increment m = 1...400 (i.e. 100 m, 200 m, ... 40 km), compute the geodesic coordinate (lmn, Lmn) using Vincenty’s Direct Formulae per Schedule 3 item 3. Use the specified GRS80 parameters.
For each increment, compute the propagation-loss value PL(lmn, Lmn) following Schedule 2 item 3’s steps (including the required parameter calculations and the propagation-loss formula steps supplied in the Schedule).
Apply device boundary criterion and determine device boundary
For each radial, evaluate RP - MP at each m×100 m increment, with MP = PL(lmn, Lmn) + LOP − Gr (Schedule 2 item 2).
Use LOP = −108 dBm/30 kHz for AAS, −116 dBm/30 kHz for others (Schedule 2 item 2).
Gr is the nominal receiver antenna gain including feeder loss set to 0 dBi (Schedule 2 item 2).
Identify the first increment where RP - MP ≤ 0; that increment’s latitude/longitude is the radial end point. If none is found within 400 increments, the 400th increment is the end point (Schedule 2 item 1).
Assemble the 360 end points to form the device boundary polygon (Schedule 2 item 1).
Check geographic area and bright-line limits
Confirm the device boundary lies within the licence geographic area. If any part lies outside, section 10(1)(b) deems the interference unacceptable unless the narrow exception in section 10(2) applies.
Ensure emissions above the horizontal plane are ≤ 45 dBm/30 kHz EIRP (section 10(3)).
If operating in the lower band (2500-2570 MHz), ensure effective antenna height ≤ 10 metres (section 10(4)).
Document statistical confidence and measurement uncertainty
For parameters in Schedules 2 and 3, produce evidence that estimates meet not less than 95% confidence that the true value will remain below the specified requirement (section 11). Document methodology, sample sizes, model assumptions, uncertainty quantification, and instrument calibration certificates.
Register compliance and manage changes
Provide the ACMA with Register entries in accordance with the Act and section 144 requirements (notes to sections 8 and 9). Include antenna identification numbers and other required fields.
For transmitters included in the Register before commencement, note transitional protection (section 12). If you intend to change registered details, calculate old and new device boundaries on each radial before recording the change , if new boundaries are equal to or less than old on each radial, transitional protection is preserved (section 12(3)).
Operational controls and AAS-specific steps
If using an AAS and relying on the Determination’s AAS assumptions, document control logic and worst-case beam/power states that demonstrate RP will not be exceeded under any permitted operating state (Schedule 2 item 2 Note 1).
Implement power control and beam management workflows to prevent transient exceedance of RP and to avoid emissions above the horizontal plane exceeding 45 dBm/30 kHz EIRP (section 10(3)).
Maintain records for potential ACMA review
Retain modelling inputs (DEM-3S extracts, geodetic calculations, Vincenty formula implementations), measurement raw data, calibration certificates, and the uncertainty analyses substantiating the 95% confidence statement (section 11). The Determination does not describe ACMA’s audit process, so keep complete documentation.
Where advice is needed
If in doubt about the interpretation of the modulus exceptions, the DEM-3S cell selection rules, the implementation of Vincenty formulae, or the AAS assumptions, seek technical advice from RF consultants experienced with the Determination’s exact methods, and seek legal advice on Register and Act compliance, since enforcement stems from the Act.
Following these steps aligns operational practice with the Determination’s detailed prescriptions (section 5, Schedule 2 and Schedule 3) and positions licensees to demonstrate to the ACMA that their transmitters do not cause an “unacceptable level of interference” as defined in section 10.
centre frequency, in relation to a radiocommunications transmitter, means the frequency midway between the lower and upper frequency limits of the transmitter’s occupied bandwidth.
DEM-3S means the dataset:
(a) with the citation “Gallant, J., Wilson, N., Tickle, P.K., Dowling, T., Read, A. 2009. 3 Second SRTM Derived Digital Elevation Model (DEM) Version 1.0. Record 1.0. Geoscience Australia, Canberra”; and
(b) given the persistent identifier [http://pid.geoscience.gov.au/dataset/ga/69888](http://pid.geoscience.gov.au/dataset/ga/69888);
published by Geoscience Australia.
Note: DEM-3S is available, free of charge, from Geoscience Australia using the persistent identifier. More information about DEM-3S is available, free of charge, from the Geoscience Australia website at www.ga.gov.au.
DEM-3S cell means an individual height element of the DEM-3S.
device boundary: see item 1 of Schedule 2.
device boundary criterion: see item 2 of Schedule 2.
effective antenna height: see Schedule 3.
EIRP, in relation to a radiocommunications device, means the equivalent isotropically radiated power of the device.
emission designator: see section 7.
fixed receiver means a radiocommunications receiver:
(a) located at a fixed point on land or sea; and
(b) not designed or intended for use while in motion.
fixed transmitter means a radiocommunications transmitter:
(a) located at a fixed point on land or sea; and
(b) not designed or intended for use while in motion.
GDA94 means the geodetic datum designated as the “Geocentric Datum of Australia (GDA)”, gazetted in the Commonwealth of Australia Gazette No. GN 35 on 6 September 1995, as existing on that date.
Note: Gazette No. GN 35 is available, free of charge, from the Federal Register of Legislation at www.legislation.gov.au.
geographic area, for a spectrum licence, means the area within which operation of a radiocommunications device is authorised under the licence.
group of radiocommunications receivers: see section 9.
group of radiocommunications transmitters: see section 8.
horizontally radiated power, for a radiocommunications device, means the sum of:
(a) the maximum true mean power, in dBm per specified rectangular bandwidth, at the antenna connector, that is located within the frequency band of the spectrum licence authorising the operation of the radiocommunications device; and
(b) the antenna gain relative to an isotropic antenna in a specified direction in the horizontal plane containing the phase centre of the antenna used with the radiocommunications device, in dBi.
location: see Schedule 1.
maximum true mean power means the true mean power measured in a specified rectangular bandwidth that is located within a specified frequency band, such that the true mean power is the maximum of the true mean powers produced.
Note: The power within the specified rectangular bandwidth is normally established by taking measurements using either an adjacent channel power meter or a spectrum analyser. Estimation of the accuracy of the measuring equipment, the measurement protocol and any adjustments made to measurements to take account of practical filter shape factors should be in accordance with good engineering practice.
mean power means the average power measured during an interval of time that is at least 10 times the period of the lowest modulation frequency.
occupied bandwidth, in relation to a radiocommunications transmitter, means the width of a frequency band having upper and lower limits that contain 99% of the true mean power of the transmitter’s emission at any time.
Radio Regulations means the document titled ‘Radio Regulations’, published by the International Telecommunication Union.
Note 1: The Radio Regulations are not regulations made by the Governor-General under the Act.
Note 2: The Radio Regulations are available, free of charge, from the International Telecommunication Union’s website at www.itu.int.
true mean power means:
(a) if an unmodulated carrier is present – the mean power measured while the unmodulated carrier is present; or
(b) if an unmodulated carrier is not present – the mean power measured while transmitted information is present.
Note: A number of other expressions used in this instrument are defined in the Act, including the following:
(2) In this instrument, unless otherwise specified, a reference to a part of the spectrum or a frequency band includes all frequencies that are greater than but not including the lower frequency, up to and including the higher frequency.
Note: This subsection means the lower number in a part of the spectrum or a frequency band is not included in the part of the spectrum or the frequency band.
6 References to other instruments
6 References to other instruments
In this instrument, unless the contrary intention appears:
(a) a reference to any other legislative instrument is a reference to that other legislative instrument as in force from time to time; and
(b) a reference to any other kind of instrument or writing is a reference to that other instrument or writing as in force or existence from time to time.
Note 1: For references to Commonwealth Acts, see section 10 of the Acts Interpretation Act 1901; and see also subsection 13(1) of the Legislation Act 2003 for the application of the Acts Interpretation Act 1901 to legislative instruments.
Note 2: All Commonwealth Acts and legislative instruments are registered on the Federal Register of Legislation.
Note 3: See section 314A of the Act.
7 Emission designator
7 Emission designator
(1) For the purpose of this instrument, the designation of a radiocommunications transmitter’s emission (emission designator) is determined using the methods specified in the Radio Regulations.
(2) For the purpose of determining the emission designator of a radiocommunications transmitter using the methods specified in the Radio Regulations, references in the Radio Regulations to “necessary bandwidth” for a given class of emission are taken to be references to the occupied bandwidth of the transmitter.
Note: At the time the ACMA made this instrument, Appendix 1 of the Radio Regulations set out the method to be used for determining the designation of a radiocommunications transmitter’s emission.
8 Group of radiocommunications transmitters
8 Group of radiocommunications transmitters
(1) For the purposes of this instrument, and subject to subsection (2), two or more fixed transmitters are a group of radiocommunications transmitters if:
(a) each transmitter has the same centre frequency and emission designator; and
(b) each transmitter is operated for the purpose of communicating with the same radiocommunications receiver or group of radiocommunications receivers; and
(c) each transmitter has an antenna of the same type, model and manufacture; and
(d) the antenna used with each transmitter is located on the same structure and within 20 metres of the phase centre of all antennas for the other transmitters within the group of radiocommunications transmitters; and
(e) the identification number assigned by the ACMA to the antenna used with each radiocommunications transmitter is the same.
Note: See section 144 of the Act, and any instrument made under that section, for the information that must be included in the Register about a spectrum licence and each radiocommunications device operated under a spectrum licence.
(2) A radiocommunications transmitter must not belong to more than one group of radiocommunications transmitters.
Note: If a radiocommunications transmitter is capable of belonging to more than one group of radiocommunications transmitters, the spectrum licensee or authorised third party may nominate one group for the transmitter.
9 Group of radiocommunications receivers
9 Group of radiocommunications receivers
(1) For the purposes of this instrument, and subject to subsection (2), two or more fixed receivers are a group of radiocommunications receivers if:
(a) each receiver is operated for the purpose of communicating with the same radiocommunications transmitter or group of radiocommunications transmitters; and
(b) each receiver has an antenna of the same type, model and manufacture; and
(c) the antenna used with each receiver is located on the same structure and within 20 metres of the phase centre of all antennas for the other receivers within the group of radiocommunications receivers; and
(d) the identification number assigned by the ACMA to the antenna used with each radiocommunications receiver is the same.
Note: See section 144 of the Act, and any instrument made under that section, for the information that must be included in the Register about a spectrum licence and each radiocommunications device operated under a spectrum licence.
(2) A radiocommunications receiver must not belong to more than one group of radiocommunications receivers.
Note: If a radiocommunications receiver is capable of belonging to more than one group of radiocommunications receivers, the spectrum licensee or authorised third party may nominate one group for the receiver.
10 Unacceptable level of interference
10 Unacceptable level of interference
(1) A level of interference caused by a radiocommunications transmitter operated under a 2.5 GHz spectrum licence is unacceptable if:
(a) the operation of the transmitter results in a contravention of a core condition of the licence relating to the maximum permitted level of radio emission from the transmitter:
(i) outside the parts of the spectrum the use of which is authorised under the licence; or
(ii) outside the geographic area of the licence; or
(b) subject to subsection (2), any part of the device boundary of the transmitter lies outside of the geographic area of the licence; or
(c) the device boundary of the transmitter cannot be calculated in accordance with item 1 of Schedule 2.
(2) A level of interference mentioned in paragraph (1)(b) is not unacceptable in relation to a part of the device boundary of the radiocommunications transmitter that:
(a) lies outside the geographic area of the licence; and
(b) is connected to a radial that:
(i) is mentioned in item 1 of Schedule 2; and
(ii) does not cross over land outside the geographic area of the licence that is permanently above the Australian territorial sea baseline.
(3) A level of interference caused by a radiocommunications transmitter operated under a 2.5 GHz spectrum licence is unacceptable if the operation of the transmitter results in emissions above the horizontal plane greater than 45 dBm/30 kHz EIRP.
(4) A level of interference caused by a radiocommunications transmitter operated under a 2.5 GHz spectrum licence is unacceptable if the transmitter:
(a) operates in the 2.5 GHz lower band; and
(b) has an effective antenna height greater than 10 metres.
(5) This section does not apply in relation to a radiocommunications transmitter to which section 12 applies.
Note Subsection 145(1) of the Act provides that the ACMA may refuse to include in the Register details of a radiocommunications transmitter if the ACMA is satisfied that operation of the transmitter could cause an unacceptable level of interference to the operation of other radiocommunications devices. However, some radiocommunications transmitters are exempt from the requirement to be registered in the Register under their 2.5 GHz band spectrum licence – see subsection 69(2) of the Act.
11 Accuracy
11 Accuracy
Unless otherwise specified, the value of a parameter in Schedules 2 and 3 must be estimated with a level of confidence not less than 95 percent that the true value of the parameter will always remain below the requirement specified in this instrument.
12 Transitional — radiocommunications transmitter registered before commencement of this instrument
12 Transitional – radiocommunications transmitter registered before commencement of this instrument
(1) If a radiocommunications transmitter was included in the Register in relation to a 2.5 GHz band spectrum licence before the commencement of this instrument (relevant transmitter), this section applies in relation to that transmitter.
(2) Subject to subsection (3), for the purposes of subsection 145(4) of the Act, a level of interference caused by a relevant transmitter is unacceptable if it would have been unacceptable under the Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2012, as in force at the time the relevant transmitter was included in the Register.
Note: The Radiocommunications (Unacceptable Levels of Interference – 2.5 GHz Band) Determination 2012 is available, free of charge, from the Federal Register of Legislation at www.legislation.gov.au.
(3) For the purposes of subsection 145(4) of the Act, if:
(a) after the commencement of this instrument, both:
(i) a detail of a relevant transmitter changes (relevant change); and
(ii) the change to the detail is recorded in the Register; and
(b) the distance of the new device boundary of the relevant transmitter is, on each radial mentioned in item 1 of Schedule 2, equal to or less than the distance of the old device boundary of the relevant transmitter on that r