This instrument allocates digital radio spectrum for the Darwin RA1 area: it designates DAB frequency blocks, sets which categories and numbers of digital multiplex licences may be issued, and fixes technical parameters (centre frequencies, ERP caps, antenna height, transmitter site). It affects broadcasters applying for or holding digital multiplex licences and the ACMA’s technical oversight, including ACMA’s power to require demonstrations of ERP compliance (see s.6). An advisory notes possible power limits to avoid interference with Department of Defence facilities.
This instrument, titled the Radiocommunications (Digital Radio Channels - Northern Territory) Plan 2017 (s 1), is a legislative channel plan made under subsection 44A(1) of the Radiocommunications Act 1992 (s 3). Its legal effect is to specify a digital radio channel plan for the designated BSA radio area "Darwin RA1" by way of the Schedule and Attachments (s 5(1)). Mechanically, it:
allots frequency blocks for use by digital radio multiplex transmitter licensees in the Darwin RA1 designated BSA radio area (s 5(2)(a), Schedule Table 1);
reserves a frequency block for a category 3 digital radio multiplex transmitter licence to be issued in accordance with subsection 102E(2) of the Act (s 5(2)(b), Schedule Table 1, Table 2);
determines which licence categories are to be issued for the area and how many licences of each category (s 5(2)(c)-(d), Schedule Table 2);
fixes technical specifications for multiplex transmitters for the area by reference to Attachments to the Schedule (s 5(2)(e); note in s 5).
Key elements of the Schedule and Attachments for Darwin RA1 are: Table 1 lists two multiplex transmitter entries, Darwin 1 and Darwin 2, with frequency blocks 9A and 9C respectively, centre frequencies 202.928 MHz and 206.352 MHz, and specified technical specification numbers (TS12000070 and TS12000072) linked to Attachment 1.1 and Attachment 1.2. Table 2 records that one category 1 licence and one category 3 licence are to be issued for the area, with no category 2 licences (Schedule Table 2).
The Attachments specify transmitter particulars that a licensee must observe. For both Darwin 1 (Attachment 1.1) and Darwin 2 (Attachment 1.2) the mode is DAB, polarisation vertical, nominal location "Broadcast Australia Site 100 Deloraine Rd SHOAL BAY" with nominal coordinates Latitude 12.414473º S, Longitude 130.969253º E. For both attachments the maximum effective radiated power (ERP) is stated as 20 kW at all angles of azimuth (Attachments, Output Radiation Pattern). Maximum antenna height is shown in the Attachments as "10 5 m" which, on the face of the instrument text, is presented with internal spacing and therefore requires careful reading or confirmation (Attachment columns).
Current sections
Direct links to the current provisions in Radiocommunications (Digital Radio Channels – Northern Territory) Plan 2017.
12
1
Name
1 Name
This is the Radiocommunications (Digital Radio Channels – Northern Territory) Plan 2017.
2
Commencement
2 Commencement
This instrument commences at the start of the day after it is registered on the Federal Register of Legislation.
This instrument is made under subsection 44A(1) of the Radiocommunications Act 1992.
4
Definitions
4 Definitions
(1) In this instrument:
Act means the Radiocommunications Act 1992.
category means a category of digital radio multiplex transmitter licence described in section 5 of the Act.
DAB means digital audio broadcasting.
ERP means effective radiated power.
frequency block means a frequency channel of 1.536 MHz bandwidth.
maximum antenna height means the maximum permitted height above ground level of the electrical centre of an antenna.
Note: A number of expressions used in this instrument are defined in the Act, including the following:
Note: (a) category 1 digital radio multiplex transmitter licence;
Note: (b) category 2 digital radio multiplex transmitter licence;
Note: (c) category 3 digital radio transmitter licence; and
Note: (d) designated BSA radio area.
Note: (2) In this instrument, unless the contrary intention appears:
Note: (a) a reference to any other legislative instrument is a reference to that other legislative instrument as in force from time to time; and
Note: (b) a reference to any other kind of instrument or writing is a reference to that other kind of instrument or writing as in existence from time to time.
Note 1: For references to Commonwealth Acts, see section 10 of the Acts Interpretation Act 1901; and see also subsection 13(1) of the Legislation Act 2003 for the application of the Acts Interpretation Act 1901 to legislative instruments,
Note 2: All Commonwealth Acts and legislative instruments are registered on the Federal Register of Legislation.
5
Digital radio channel plans
5 Digital radio channel plans
(1) For subsection 44A (1) of the Act, the Schedule to this instrument is a digital radio channel plan for the designated BSA radio area specified in that Schedule.
(2) The digital radio channel plan specified in the Schedule:
(a) allots a frequency block or blocks in relation to the designated BSA radio area for use by digital radio multiplex transmitter licensees; and
(b) reserves a frequency block for a category 3 digital radio multiplex transmitter licence for the designated BSA radio area to be issued in accordance with subsection 102E(2) of the Act; and
(c) determines which of the following types of licences, or which combination of the following types of licences, are to be issued for the designated BSA radio area:
(i) category 1 digital radio multiplex transmitter licence;
(ii) category 2 digital radio multiplex transmitter licence; and
(d) if a particular type of licence mentioned in paragraph (c) is to be issued for the designated BSA radio area — determines whether:
(i) a single licence of that type is to be issued for the designated BSA radio area; or
(ii) 2 or more licences of that type are to be issued for the designated BSA radio area; and
(e) determines technical specifications of multiplex transmitters operated under digital radio multiplex transmitter licences for the designated BSA radio area.
Note: The relevant technical specifications are set out in Attachments to the Schedule.
6
Maximum ERP limits
6 Maximum ERP limits
(1) For each digital radio multiplex transmitter, the ERP of that transmitter in any part of a sector or bearing must not exceed the maximum ERP specified in the output radiation pattern table for that sector or bearing in the relevant Attachment.
(2) The licensee of a digital radio multiplex transmitter must, if requested by the ACMA to do so, demonstrate, to the satisfaction of the ACMA, that the ERP of a transmitter in any part of a sector or bearing specified by the ACMA complies with this section.
7
Co-channel transmitters
7 Co-channel transmitters
The technical specifications for a co-channel transmitter licensed under a relevant digital radio multiplex transmitter licence are those specified in the licence.
This instrument is made under subsection 44A(1) of the Radiocommunications Act 1992.
4 Definitions
4 Definitions
(1) In this instrument:
Act means the Radiocommunications Act 1992.
category means a category of digital radio multiplex transmitter licence described in section 5 of the Act.
DAB means digital audio broadcasting.
ERP means effective radiated power.
frequency block means a frequency channel of 1.536 MHz bandwidth.
maximum antenna height means the maximum permitted height above ground level of the electrical centre of an antenna.
Note: A number of expressions used in this instrument are defined in the Act, including the following:
Note: (a) category 1 digital radio multiplex transmitter licence;
Note: (b) category 2 digital radio multiplex transmitter licence;
Note: (c) category 3 digital radio transmitter licence; and
Note: (d) designated BSA radio area.
Note: (2) In this instrument, unless the contrary intention appears:
Note: (a) a reference to any other legislative instrument is a reference to that other legislative instrument as in force from time to time; and
Note: (b) a reference to any other kind of instrument or writing is a reference to that other kind of instrument or writing as in existence from time to time.
Operational constraints are expressed in the instrument itself. Section 6 mandates that for each digital radio multiplex transmitter the ERP in any part of a sector or bearing must not exceed the maximum ERP specified in the relevant Attachment (s 6(1)). The ACMA may require the licensee to demonstrate compliance with that limit to the ACMA’s satisfaction (s 6(2)). Section 7 provides that technical specifications for a co-channel transmitter licensed under a relevant digital radio multiplex transmitter licence are those specified in the licence (s 7).
The instrument commences at the start of the day after registration on the Federal Register of Legislation (s 2), and includes a definitions provision which imports key terms and cross-references the Act (s 4). In short, the Plan constrains spectrum access, fixes location and technical parameters for the two multiplexes in Darwin RA1, reserves one block for future issue under the Act, and creates ACMA-enforceable ERP limits to those specifications.
Main concepts
The instrument deploys a handful of legal and technical concepts to create binding constraints on spectrum use in the Darwin RA1 designated BSA radio area. These concepts are definitional, allocative and technical.
Definitional concept: The instrument imports and relies on the definitions in the Radiocommunications Act 1992 for categories of digital radio multiplex transmitter licences and the notion of a designated BSA radio area (s 4, notes). The instrument also defines its own terms for its operation: frequency block, DAB, ERP, maximum antenna height, and centre frequency; and it states that a frequency block is a channel of 1.536 MHz bandwidth (s 4). Those definitions set the unit of allocation and the technical frame for the rest of the plan.
Allocative concept: Section 5 makes explicit that the Schedule is a digital radio channel plan and that it allots and reserves discrete frequency blocks for particular licence categories and quantities (s 5(1) and s 5(2)(a)-(d)). The Schedule operationalises this by naming specific multiplex licence entries (Darwin 1, Darwin 2), assigning frequency blocks (9A, 9C), and indicating which are reserved. Table 2 then records the number of licences of each category to be issued for the area (one category 1 and one category 3, zero category 2). The instrument therefore functions as an allocation map: it converts generic regulatory powers under s 44A of the Act into a concrete set of spectrum allotments and the number and categories of licences that can be issued for Darwin RA1.
Technical concept: The Attachments set transmitter technical specifications. They identify a nominal transmitter site (Broadcast Australia Site 100 Deloraine Rd Shoal Bay) and coordinates, polarisation, mode (DAB), maximum antenna height, and an output radiation pattern table providing maximum ERP values (Attachments, Columns). Section 6 binds licensees to those ERP maxima and creates an evidentiary obligation to demonstrate compliance to the ACMA on request (s 6(1)-(2)). Section 7 clarifies that co-channel transmitters must meet the technical specifications set in their licences rather than the Schedule per se (s 7). The Attachments also carry an advisory note that transmissions may need to operate with a power limitation to limit interference to adjacent facilities managed by the Department of Defence, which introduces an additional practical constraint beyond the stated maximum ERP.
Regulatory mechanism: The instrument does not itself issue licences. Instead, it establishes the plan within which the ACMA, exercising powers under the Act, will issue licences consistent with the plan. It also reserves at least one block for issuance under s 102E(2) of the Act (s 5(2)(b)), signalling that the procedure and criteria for that reserved issuance are governed by the Act provision referenced rather than by the Plan itself.
Compliance and enforcement mechanism: The primary compliance obligation is to not exceed the ERP values specified in the Attachments (s 6(1)). The instrument gives the ACMA an information and inspection-style power to require a licensee to demonstrate that ERP levels comply with the plan (s 6(2)). For co-channel transmitters, the licence itself is the reference for technical requirements (s 7), so compliance may stem from both the plan and the licence.
Taken together, these concepts create a binding spectrum allocation and technical control regime for Darwin RA1 that constrains transmitter characteristics, the number and category of licences that can operate within the Plan, and the evidential relationship between licensees and the ACMA in enforcing those constraints.
Who it affects
Primary affected parties
Prospective and actual digital radio multiplex transmitter licensees seeking to operate in the Darwin RA1 designated BSA radio area. The Schedule specifies that one category 1 and one category 3 licence are to be issued for that area (Schedule Table 2). Applicants for those licences will be subject to the technical constraints listed in the Attachments if and when a licence is issued under the Act (s 5(2)(c)-(d), s 5(2)(e)).
Current spectrum users at or near the nominal transmitter site. The Attachments name the nominal site as Broadcast Australia Site 100 Deloraine Rd Shoal Bay and give precise coordinates (Attachments 1.1 & 1.2). Entities operating adjacent or co-located radio facilities may be affected by new multiplex transmissions and any Defence-imposed power limitations referenced in the advisory note.
Regulator and government agencies
The Australian Communications and Media Authority (ACMA) is a central decision maker and enforcer. Section 6(2) empowers the ACMA to request demonstration that a transmitter’s ERP complies with the Plan. The ACMA also manages the administrative process to issue licences under the Act, and issuance of the reserved category 3 licence is to be in accordance with subsection 102E(2) of the Act (s 5(2)(b)).
The Department of Defence is an external stakeholder with operational interests. Both Attachments include an advisory note that transmissions may need to operate with a power limitation to limit interference to adjacent Defence-managed facilities. That advisory note does not itself change the ERP maxima set in the Attachment, but it signals that Defence concerns may cause additional constraints on operations.
Indirectly affected parties
Broadcast infrastructure owners and site providers, such as the operator of the nominal Broadcast Australia site, since the Attachments assume a specific site location and antenna height limit (Attachments).
Service providers and broadcasters that would use multiplex capacity. The instrument fixes the number and category of multiplex licences. The number of multiplexes and their technical parameters affect the supply of multiplex carriage, which in turn affects independent content providers’ access to DAB carriage within Darwin RA1.
Equipment manufacturers and installers. Technical requirements for polarisation, antenna height and ERP constrain the hardware and installation specifications for transmitters deployed under licence.
Who pays, who decides
Licensees bear the direct compliance costs: capital investments to meet site and transmitter specifications, operational costs to maintain ERP limits, measurement and recordkeeping expenses to demonstrate compliance when requested by ACMA (s 6(2)), and any costs arising from Defence-driven power limitations noted in the Attachments.
The ACMA decides compliance status and enforces the Act and the Plan’s operational constraints. The Plan sets the shape of the decision space but the Act governs licence issue, conditions and enforcement, including the issuance process for the reserved category 3 licence (s 5(2)(b)).
Behavioural effects
Applicants will structure applications to match the category and quantity constraints in Table 2 (one category 1, one category 3) and to satisfy the technical specifications in the Attachments.
Licensees will design and operate transmissions to meet ERP limits in the output radiation pattern table and to keep antenna height and polarisation within the stated parameters.
Potential entrants who would have sought category 2 licences have no allocation in this Plan for Darwin RA1, as Table 2 records zero category 2 licences; they must look elsewhere or at other processes under the Act for market entry.
Geographic and technical limits are concrete. The instrument’s scope is the Darwin RA1 designated BSA radio area (Schedule heading). Its technical constraints (frequency block definitions at 1.536 MHz bandwidth, centre frequencies, ERP maxima, antenna height, polarisation and coordinates) narrow the physical and technical design space available to market participants and adjacent users.
Key duties and rights
Duties established by the instrument
Duty to comply with technical specifications in the Schedule Attachments: Section 5(2)(e) empowers the Plan to determine technical specifications of multiplex transmitters, and the Attachments set those specifications for the Darwin RA1 entries. A licensee operating a digital radio multiplex transmitter must operate in accordance with those Attachment specifications insofar as they are applied by the licence and the Plan (s 5).
Duty not to exceed maximum ERP: Section 6(1) places an explicit numerical duty on each digital radio multiplex transmitter that its ERP in any part of a sector or bearing must not exceed the maximum ERP specified in the output radiation pattern table for that sector or bearing in the relevant Attachment. For both Attachments the stated maximum ERP is 20 kW at all angles of azimuth.
Duty to demonstrate compliance on request: Section 6(2) requires a licensee to demonstrate to the satisfaction of the ACMA, if requested, that the ERP of a transmitter in any part of a sector or bearing specified by the ACMA complies with section 6(1). This creates an evidential burden on licensees to retain measurement records, modelling or other proof that demonstrates compliance.
Duty to observe licence-specific technical specifications for co-channel transmitters: Section 7 specifies that the technical specifications for a co-channel transmitter licensed under a relevant digital radio multiplex transmitter licence are those specified in the licence. If a licensee operates or authorises a co-channel transmitter, the licence will define technical obligations that the licensee must meet.
Rights and entitlements created or signalled by the instrument
Right to be issued a licence only in the categories and numbers specified: The Schedule determines which types and combinations of licences are to be issued for Darwin RA1 and whether a single licence or multiple licences of a particular type are to be issued (s 5(2)(c)-(d); Schedule Table 2). For Darwin RA1, the Plan signals entitlement to the issuance of one category 1 licence and one category 3 licence.
Reservation for future issuance under Act procedures: The Plan reserves a frequency block for a category 3 licence to be issued in accordance with subsection 102E(2) of the Act (s 5(2)(b)). That reservation creates a procedural pathway under the Act for a category 3 licence to be issued, rather than making immediate administrative allocation within the Plan itself.
Right to operate within the Plan’s specified technical envelope: Once a licence is issued consistent with the Plan, the licensee has the right to operate the multiplex within the technical envelope established by the Attachments (subject to compliance and any Defence-imposed limitations).
Discretion and allocation mechanisms
The instrument is prescriptive about quantity and category of licences (Schedule Table 2), but the process for issuing licences, including competitive allocation or administrative criteria, remains governed by the Act. The Plan therefore confines the ACMA’s power to the pre-specified categories and numbers but does not itself set the procedural allocation mechanism.
Section 6(2) grants the ACMA discretionary power to require a licensee to demonstrate compliance. That discretion creates a supervisory role for the ACMA in verifying and enforcing ERP limits.
Operational obligations for licensees
Operate at the nominal transmitter site and coordinates specified in the Attachment, or as set in the licence (Attachments).
Maintain ERP at or below the maximum ERP values in the output radiation pattern table for all sectors or bearings (s 6(1)).
Maintain physical parameters such as polarisation (vertical) and maximum antenna height as specified in the Attachments.
Be prepared to demonstrate ERP compliance to ACMA on request, which implies a duty to keep records, measurement data or modelling that the ACMA can inspect or demand (s 6(2)).
What the instrument does not itself do
It does not set licence fees, conditions beyond technical specifications, or penalties. Those matters are governed by the Act and by the licences issued under the Act. The Plan provides the allocation and technical envelope; enforcement and ancillary licence conditions fall under the Act’s wider regulatory framework.
All duties referenced above derive from explicit provisions in this instrument, principally sections 5, 6 and 7, and the Attachments to the Schedule.
Penalties and enforcement
Enforcement powers referenced in the instrument
The instrument itself creates a clear compliance mechanism for ERP limits: section 6(2) allows the ACMA to request that a licensee demonstrate, to the ACMA’s satisfaction, that a transmitter’s ERP in any part of a sector or bearing complies with the ERP limit set out in the Attachment (s 6(2)). That is an administrative enforcement mechanism tied to evidence and demonstration. The instrument does not itself specify fines or criminal penalties.
Location of penalties and sanctions
The instrument does not prescribe specific penalties or sanctions for noncompliance. It sits within the Radiocommunications Act 1992 framework and therefore enforcement and penalty measures applicable to noncompliance with radiocommunications licences and plans will be those set out in the Act. The Plan deliberately limits itself to allocation and technical specification, deferring to the Act for sanctioning mechanisms.
Practical enforcement pathways and actors
ACMA as the enforcement actor: The ACMA is the regulator empowered to request demonstrations of compliance under s 6(2). In practice, the ACMA will be the primary agency to investigate suspected noncompliance with the Plan’s ERP limits and the technical specifications in Attachments, and to enforce remedial measures or commence action under the Act as necessary.
Defence coordination: The Attachments include an advisory note that transmissions may need to operate with a power limitation to limit interference to adjacent facilities managed by the Department of Defence. While that advisory note is not itself a statutory penalty, it signals that Defence concerns may lead to operational constraints or coordination requirements that the ACMA or licensees must observe. The practical enforcement of Defence-imposed limitations will depend on inter-agency arrangements under the Act and Defence’s role as an affected party.
Types of regulatory outcomes possible under the Act (as the Plan interfaces with the Act)
Compliance verification and corrective directions: ACMA can request information and evidence; if a licensee cannot demonstrate compliance, ACMA can take administrative measures under the Act which may include directions to remedy interference, alter operations, or vary licence conditions. The Plan provides the technical benchmarks the ACMA will use to determine compliance (s 6(1)-(2)).
Licence variation, suspension or revocation: While the Plan does not itself set out these sanctions, the Act contains powers for the ACMA to vary or revoke licences for cause. The Plan’s ERP limits and technical specifications would be central to any ACMA determination about whether a licensee is complying with licence conditions and the Plan.
Interference mitigation and coordination: The advisory note on Defence facilities implies that ACMA may require power limitations or other mitigation measures to address interference. Those measures may be agreed or directed, and failures to remedy harmful interference could lead to further regulatory action.
Evidentiary and compliance burden
The instrument erects an evidentiary burden on licensees. Section 6(2) requires demonstration to the ACMA’s satisfaction upon request. That creates an ongoing compliance cost of monitoring ERP, retaining measurement records, or maintaining propagation models and test results capable of demonstrating compliance at the sector or bearing granularity required by the Attachment output radiation pattern tables.
Limitations of enforcement detail in the instrument
The Plan does not specify the form or timing of ACMA’s requests for demonstrations, the standards for satisfactory proof, nor the precise remedies available upon noncompliance. Those operational enforcement details are left to the ACMA’s regulatory practice and the enforcement provisions in the Radiocommunications Act 1992. Parties must therefore consult the Act and ACMA guidance for the full enforcement regime.
In short, enforcement is administrative and evidence-driven: the Plan sets technical ceilings and gives ACMA the right to verify compliance; penalties and remedial measures are available under the Act, not within this instrument.
How it interacts with other laws
Primary statutory interface
Radiocommunications Act 1992: This Plan is made under subsection 44A(1) of the Act (s 3), and its operation is explicitly tied to the Act. Several provisions of the Plan refer to or defer to provisions in the Act. For example, the Plan reserves a frequency block for a category 3 digital radio multiplex transmitter licence to be issued in accordance with subsection 102E(2) of the Act (s 5(2)(b)). The categories of licences referred to in the Plan are those defined by the Act (s 4 notes). The Plan therefore functions as a subordinate instrument that allocates spectrum and sets technical parameters within the Act’s licensing and enforcement framework.
Administrative law and regulatory practice
The ACMA’s exercise of powers under the Act will be governed by administrative law principles. The Plan gives ACMA power to request compliance demonstrations (s 6(2)); the manner in which ACMA exercises that power will be subject to procedural fairness, reasonableness and any statutory review or merits review rights contained in the Act or other statutes. The Plan does not itself create administrative law remedies or review rights; those are contained in primary legislation and administrative law.
Inter-agency interactions
Department of Defence interests: The Attachments contain an advisory note cautioning that transmissions may need to operate with a power limitation to limit interference to adjacent facilities managed by the Department of Defence (Attachments advisory note). That places the Plan in practical interface with Defence operational needs. Decisions about mitigating interference or imposing Defence-driven constraints will involve inter-agency coordination, typically led by ACMA under the Act’s interference management powers.
Technical standards and electromagnetic spectrum policy
Spectrum planning and international coordination: The Plan specifies centre frequencies in MHz and frequency block definitions (s 4, Schedule Table 1). Frequency use is often subject to international allocations and technical standards. The Plan does not restate such international obligations, but in practice ACMA will ensure the Plan is consistent with Australia’s international spectrum commitments and technical standards in the Act’s administration.
Licence conditions and other legislation
Licence-specific obligations: Section 7 states that technical specifications for co-channel transmitters are those specified in the licence. Licences issued under the Act may contain conditions that interact with the Plan’s Attachments. Other legislation that applies to telecommunications infrastructure (planning and environmental law, aviation safety for tall structures, local government approvals for transmission sites) will also apply to the physical deployment of antennas and sites referenced in the Attachments but are not addressed in this instrument.
Statutory definitions and interpretation
The Plan imports definitions from the Act (s 4 notes). Where the Plan uses terms defined in the Act, those Act definitions will apply for the Plan’s construction. The Plan also cross-references subsection 102E(2) of the Act for the issuance of the reserved category 3 licence, so the criteria, process and eligibility set out in that Act provision will govern the reserved issuance.
Limits of the Plan’s legal reach
The Plan is an instrument that sets spectrum allocations and technical parameters. It does not itself create licence entitlements that bypass the Act’s licensing procedures, fee regimes, enforcement sanctions or allocation processes. The Plan provides the predetermined allocation map and technical envelope within which the Act’s machinery operates.
Practitioners and affected parties should therefore treat the Plan as a technical and allocative subordinate measure that must be read alongside the Radiocommunications Act 1992 and relevant ACMA practice notes and processes to understand fully how licences are allocated, varied, enforced and reviewed.
Amendment history
Instrument identity and date
The instrument is named the Radiocommunications (Digital Radio Channels - Northern Territory) Plan 2017 (s 1). That identifies the instrument’s creation year as 2017 in its title, but the instrument’s commencement is governed by section 2 which states it commences at the start of the day after it is registered on the Federal Register of Legislation (s 2). The instrument text as provided includes that commencement rule.
Amendments within the instrument
The Plan as supplied contains no textual amendments or schedules indicating subsequent amendments. It establishes the Schedule and Attachments as the operative plan for Darwin RA1. The instrument does not itself record prior versions or a history of changes.
Procedure for amending the Plan
Section 4(1)(a) notes that references to other legislative instruments are references to those instruments as in force from time to time. The Plan itself is a legislative instrument made under s 44A(1) of the Act (s 3). Any amendments to the Plan would ordinarily be made by subsequent legislative instrument under the same statutory power (subsection 44A(1) of the Act) and registered on the Federal Register of Legislation. The Plan does not set an internal amendment mechanism or timetable; amendment authority remains with the regulator or Minister under the enabling Act.
Linked statutory changes
Any change to the Radiocommunications Act 1992 or to sections referred to in the Plan (for example subsection 102E(2)) may change the practical operation of the Plan by altering the licensing process or the categories of licences. The Plan’s s 4 notes make clear that Act definitions and referenced provisions are to be read as amended from time to time, which means the Plan is designed to operate alongside a potentially changing statutory environment.
Practical note for practitioners
To establish the amendment history for this Plan in a comprehensive manner one must consult the Federal Register of Legislation entry for this instrument. The Plan itself does not contain a record of subsequent amendments or disallowance. Users should check the online register for any instruments that have varied the Plan since its registration or for notices that the Plan has been superseded by a later instrument.
Absence of amendment entries in this instrument
The instrument as provided contains no historical amendment schedule and no notes of revocation. The attachment and tables appear as operative content without versioning within the document. Accordingly, as of the document provided, there is no internal record of amendment; external checking against the Federal Register is necessary to confirm whether later instruments have amended or replaced this Plan.
Litigation history
No cases or litigation referenced in the instrument
The Plan contains no references to judicial decisions, tribunal determinations, or litigation arising from it. There are no case citations in the text, no footnotes pointing to litigation, and no explanatory material in the instrument that records prior disputes.
Practical dispute vectors the instrument creates
Although the Plan itself contains no litigation history, it establishes several factual and legal vectors along which disputes or litigation could occur, drawing on the Act’s dispute and enforcement pathways. Those vectors include:
Compliance disputes about whether a licensee’s ERP actually exceeds the limits set in the Attachment output radiation pattern. Section 6(2) requires demonstration to the ACMA’s satisfaction, and disagreement over sufficiency of evidence or measurement methodology could give rise to administrative review or judicial review under the Act’s framework.
Disputes about issuance of the reserved category 3 frequency block under subsection 102E(2) of the Act. The Plan reserves the block but defers to the Act for issuance. If parties contest the procedure or criteria applied by the ACMA or the Minister when issuing the reserved licence, that could lead to administrative review litigation under the Act.
Interference and mitigation conflicts involving the Department of Defence. The Attachments flag potential Defence-related power limitations. If Defence requests or the ACMA directs a power limitation that a licensee disputes, that could result in procedural or merits review of ACMA decisions.
Licence condition disputes where licence-specific technical specifications for co-channel transmitters differ from Plan expectations. Section 7 assigns co-channel transmitter specifications to the licence; conflicts between licence terms and the Plan or between competing licence-holders about co-channel operations could provoke enforcement action and dispute resolution.
How disputes would be resolved in principle
The Plan does not specify dispute resolution fora. Disputes about ACMA decisions arising from the Plan would be resolved under the Radiocommunications Act 1992, applicable administrative law remedies and any merits review processes specified by law or available through tribunals such as the Administrative Appeals Tribunal, if those bodies have jurisdiction under the Act. The Plan itself does not create separate judicial processes.
Why no litigation history is recorded here
The absence of litigation references in the instrument may reflect that either no relevant litigation existed at the time of drafting, or that the instrument is simply a technical allocation plan and not a document typically annotated with litigation history. To determine whether litigation has arisen in practice concerning this Plan, practitioners must search case law databases and ACMA administrative records and cross-check the Federal Register of Legislation for any related notices or decisions.
In summary, the instrument contains no embedded litigation history. It does, however, create multiple plausible dispute channels tied to ERP compliance, licence issuance for the reserved block, and Defence-related interference mitigation where litigation or administrative review could arise under the Radiocommunications Act 1992.
Gotchas
Ambiguities in numeric presentation
Maximum antenna height is shown in each Attachment as "10 5 m". The instrument presents that figure with a space between numerals. The instrument text does not explicitly correct or annotate the spacing. Practitioners should not assume what numeric value was intended without checking the official registered instrument on the Federal Register of Legislation or consulting ACMA for clarification. Small typographic anomalies in technical figures can materially alter permissible height limits and therefore require confirmation (Attachments).
Reserved block is not the same as immediate entitlement
The Schedule marks the Darwin 2 frequency block as "Yes" in the Reserved frequency block column and records that a category 3 licence is to be issued in accordance with subsection 102E(2) of the Radiocommunications Act 1992 (s 5(2)(b), Schedule Table 1, Table 2). A reserved block does not equate to immediate licence issuance. The process, eligibility, timing and any competitive allocation or eligibility criteria are contained in the Act provision referenced. Applicants should therefore not treat the reservation as an automatic right to a licence or assume the criteria are those of the Plan.
ERP compliance is sector- or bearing-specific
Section 6(1) requires that the ERP of a transmitter in any part of a sector or bearing must not exceed the maximum ERP specified in the output radiation pattern table for that sector or bearing. Licence holders must therefore be prepared to demonstrate compliance at the sector or bearing granularity that the ACMA requests. Engineering assessments that report only aggregate ERP values or average measures may be insufficient; the ACMA’s request could require per-sector measurements or modelling (s 6(1)-(2)).
Advisory note has practical bite
Both Attachments include an advisory note that "Transmissions may need to operate with a power limitation to limit interference to adjacent facilities managed by the Department of Defence." While labelled advisory, this note signals that Defence constraints or coordination requirements can impose further operational limits beyond the Plan’s ERP maxima. Licensees should treat Defence proximity as a material operational risk that could require reduced power, tighter patterns or other mitigation measures.
Co-channel specifications are licence-specific
Section 7 states that technical specifications for a co-channel transmitter licensed under a relevant digital radio multiplex transmitter licence are those specified in the licence. This means that co-channel operation may be governed by licence conditions that diverge from the Plan’s Attachments. Practitioners must check both the Plan and the licence text to identify the controlling technical requirements for any co-channel transmitter.
Frequency block width constrains multiplex capacity
The instrument defines a frequency block as a 1.536 MHz channel (s 4). That fixed spectrum width constrains the total capacity available to a multiplex. Multiplex operators and potential content providers should factor the limited spectral resource into business planning; it is not adjustable by the Plan and any change to block bandwidth would require a Plan amendment or broader spectrum policy change.
Licence categories and counts are binding for the area
Table 2 prescribes one category 1 licence and one category 3 licence for Darwin RA1, with zero category 2 licences. Applicants seeking a category 2 slot will find none available under this plan and must look to other areas or await a Plan amendment that changes those counts.
Nominal site and coordinate specificity
The Attachments specify a single nominal location for both multiplexes and supply identical coordinates for both attachments. Licensees relying on different sites, different coordinates, or significantly different antenna heights should expect to need a licence variation and ACMA approval; operating in a materially different location or at a higher antenna height without authorisation risks noncompliance.
No fees, penalties or allocation procedures in the Plan
The Plan contains no provisions addressing licence fees, allocation procedures (such as auctions or comparative evaluations), or the specific penalties for noncompliance. Practitioners must refer to the Radiocommunications Act 1992 and ACMA policy for those procedural and financial details.
Commencement is registration-dependent
The Plan commences at the start of the day after registration on the Federal Register of Legislation (s 2). The date in the instrument title (2017) is not a substitute for confirming the actual registration date and the commencement date on the Federal Register.
Document-check practice
Because the Plan cross-references the Act for definitions and the issuance process for the reserved block (s 4 notes; s 5(2)(b)), practitioners must read this Plan side-by-side with the Radiocommunications Act 1992 and the relevant ACMA licensing materials. Do not treat the Plan as a stand-alone operational manual.
In sum, the principal "gotchas" are numeric presentation ambiguities, the reserved-but-not-issued nature of the category 3 block, sectoral granularity of ERP obligations, Defence-related power limitations flagged as advisory, and the need to reconcile licence conditions with Plan specifications for co-channel transmitters.
How to comply
Step 1 , Confirm status and timing
Check the Federal Register of Legislation entry for the instrument to confirm the registration and commencement date (s 2). The instrument commences at the start of the day after registration. Confirm whether any subsequent amending instruments have altered the Schedule, Attachments or licensee counts. Do not rely solely on the title year.
Step 2 , Identify which licence category and whether a licence is available
Consult Schedule Table 2 which records that for Darwin RA1 one category 1 licence and one category 3 licence are to be issued and that category 2 licences are not to be issued (Schedule Table 2). If you are an applicant, determine whether your business model fits category 1 or is eligible for category 3 under subsection 102E(2) of the Act. For the reserved category 3 slot, consult subsection 102E(2) of the Radiocommunications Act 1992 to determine process and eligibility (s 5(2)(b)).
Step 3 , Design technical deployment to Attachment parameters
Use the Attachments to determine the technical envelope: mode DAB, frequency block (9A or 9C), centre frequency (202.928 MHz for 9A, 206.352 MHz for 9C), polarisation (vertical), nominal site, coordinates (Latitude 12.414473º S, Longitude 130.969253º E), and the maximum antenna height shown in the Attachment (note formatting) (Attachments 1.1 & 1.2).
Ensure transmitter equipment is capable of operating within the specified 1.536 MHz frequency block and DAB emissions.
Step 4 , Respect and document ERP limits
Section 6(1) requires ERP in any part of a sector or bearing not to exceed the maximum ERP specified in the Attachment. The Attachments show 20 kW maximum ERP at all azimuths. Ensure that transmitter configuration, transmitters, combiners, cables and antenna gain together do not produce ERP that exceeds these maxima in any sector or bearing.
Implement measurement and monitoring processes capable of producing sector- or bearing-specific ERP evidence. Maintain propagation models and measurement records that can demonstrate compliance to the ACMA’s satisfaction (s 6(2)).
Step 5 , Prepare for ACMA compliance checks
Section 6(2) places an onus on licensees to demonstrate compliance on request. Establish procedures for timely, auditable responses to ACMA requests including: site test plans, calibrated measurement equipment, independent test reports, and retained logs of power settings and transmission parameters.
Keep installation drawings, antenna pattern files and maintenance records available to show the relationship between installed hardware and permitted ERP.
Step 6 , Account for Defence-related constraints
The Attachments carry an advisory note that transmissions may need to operate with a power limitation to limit interference to adjacent Department of Defence facilities. Before committing to capital expenditure, consult relevant Defence coordination channels via ACMA, and plan for the possibility of having to operate at reduced power or to implement pattern nulling or other mitigation measures.
Step 7 , Ensure co-channel compliance via licence terms
If operating co-channel transmitters, check that the licence specifies the technical specifications governing co-channel operation (s 7). Do not assume co-channel obligations are identical to the Plan’s Attachments; the licence may impose additional or differing technical conditions.
Step 8 , Obtain all non-spectrum approvals
The Plan does not remove obligations under planning, building, environmental, aviation safety or local government laws relating to towers, masts and civil works. Confirm and obtain necessary development approvals before site modification or antenna erection.
Confirm safety and occupational health compliance for installation and maintenance.
Step 9 , Budget for ongoing costs and potential constraints
Account for ongoing monitoring, measurement and reporting costs to satisfy ACMA’s section 6(2) requests, potential costs of Defence-mandated power limitations, and the cost of any mitigation measures required to avoid interference with adjacent facilities.
Factor in the limited spectral resource of the 1.536 MHz block when pricing or contracting multiplex capacity for broadcast clients.
Step 10 , Coordinate with ACMA and stakeholders early
Engage early with ACMA on proposed technical plans, particularly where site specifics or antenna heights would differ materially from the nominal coordinates and heights in the Attachments. Seek pre-application advice or a technical assessment from ACMA to reduce the risk of later noncompliance findings.
Coordinate with infrastructure providers (eg Broadcast Australia site operators) and Defence where proximity or interference issues are foreseeable.
Step 11 , Check licence and Plan consistency
On receipt of a licence, compare licence-specified technical conditions with the Plan Attachments to identify conflicts or additional obligations, especially for co-channel transmitters (s 7). If the licence imposes conditions not contemplated by the Plan, consider whether amendment processes or ACMA consultation are required.
Step 12 , Keep records and legal advice
Maintain a compliance file that includes: the Plan and Attachments, the issued licence and its conditions, measurement reports, ACMA correspondence, site plans, and any Defence coordination records. Where important legal or technical ambiguities appear (for example the "10 5 m" antenna height formatting), obtain formal clarification from ACMA and record it.
Consider obtaining specialist radio-engineering advice for modelling ERP at sector granularity and legal advice on interpreting the Plan alongside the Radiocommunications Act 1992.
Following these steps will align practical deployment, contractual arrangements and compliance systems with the instrument’s technical and allocative requirements. Practical compliance requires integrating the Plan’s technical envelope with the Act’s licensing procedures and ACMA’s supervisory processes.
Note 1: For references to Commonwealth Acts, see section 10 of the Acts Interpretation Act 1901; and see also subsection 13(1) of the Legislation Act 2003 for the application of the Acts Interpretation Act 1901 to legislative instruments,
Note 2: All Commonwealth Acts and legislative instruments are registered on the Federal Register of Legislation.
5 Digital radio channel plans
5 Digital radio channel plans
(1) For subsection 44A (1) of the Act, the Schedule to this instrument is a digital radio channel plan for the designated BSA radio area specified in that Schedule.
(2) The digital radio channel plan specified in the Schedule:
(a) allots a frequency block or blocks in relation to the designated BSA radio area for use by digital radio multiplex transmitter licensees; and
(b) reserves a frequency block for a category 3 digital radio multiplex transmitter licence for the designated BSA radio area to be issued in accordance with subsection 102E(2) of the Act; and
(c) determines which of the following types of licences, or which combination of the following types of licences, are to be issued for the designated BSA radio area:
(i) category 1 digital radio multiplex transmitter licence;
(ii) category 2 digital radio multiplex transmitter licence; and
(d) if a particular type of licence mentioned in paragraph (c) is to be issued for the designated BSA radio area — determines whether:
(i) a single licence of that type is to be issued for the designated BSA radio area; or
(ii) 2 or more licences of that type are to be issued for the designated BSA radio area; and
(e) determines technical specifications of multiplex transmitters operated under digital radio multiplex transmitter licences for the designated BSA radio area.
Note: The relevant technical specifications are set out in Attachments to the Schedule.
6 Maximum ERP limits
6 Maximum ERP limits
(1) For each digital radio multiplex transmitter, the ERP of that transmitter in any part of a sector or bearing must not exceed the maximum ERP specified in the output radiation pattern table for that sector or bearing in the relevant Attachment.
(2) The licensee of a digital radio multiplex transmitter must, if requested by the ACMA to do so, demonstrate, to the satisfaction of the ACMA, that the ERP of a transmitter in any part of a sector or bearing specified by the ACMA complies with this section.
7 Co-channel transmitters
7 Co-channel transmitters
The technical specifications for a co-channel transmitter licensed under a relevant digital radio multiplex transmitter licence are those specified in the licence.
Schedule 1 Darwin RA1
(subsection 5 (1))
Designated BSA radio area Designated BSA radio area
Designated BSA radio area
Darwin RA1
Table 1 Frequency channels Table 1 Frequency channels