Compliance with the class licence involves a series of checks and ongoing obligations. The following steps provide a practical framework.
First, confirm that the station is eligible. The station must not be on a space object (i.e., it must be an earth station) and must not hold an apparatus licence for substantially the same purpose. If an apparatus licence exists, decide whether to surrender it and rely solely on the class licence. Document this decision.
Second, verify that the station will operate only in the frequency bands listed in section 8 for transmission and reception. Ensure that the occupied bandwidth and any spurious emissions do not extend outside the authorised band edges, noting the exclusive lower bound rule. Use spectrum analysers or equipment certification data to confirm.
Third, determine the device compliance day for the station. Identify the date of manufacture (if Australian), import, or last material alteration. If before 17 June 2021, the station must comply with the relevant standard as defined by the Act at that time. If on or after 17 June 2021, the station must comply with the applicable equipment rules. Obtain a copy of the applicable standard or rules from the ACMA. Keep records of the compliance day and the standard/rules version.
Fourth, assess compliance with the ARPANSA Standard. The electromagnetic energy emitted by the station (or group of stations at the same location) must not exceed the general public exposure limits in any place accessible by the public. This requires a prediction of power density at ground level and any accessible structures. Use modelling or measurements. Ensure that antenna patterns are considered (e.g., a highly directional antenna may have low exposure off‑beam). For mobile stations (aircraft, ships), exposure scenarios are more complex but still required.
Fifth, ensure the station does not interfere with the operation of any radiocommunications receiver. This is a broad duty. Practical steps include using filters, adhering to emission masks, and avoiding known sensitive receivers. The safe harbour for area‑wide receive stations in section 10(2) applies only in certain frequency/geographic conditions; do not rely on it unless those conditions are met. For frequencies adjacent to radio astronomy, follow the advice‑seeking process in section 10(3) if within 20 km of an observatory. For the 1660‑1660.5 MHz and 1668‑1670 MHz bands, do not operate at all if within 500 km of an AUS87 observatory or on an airborne aircraft. Check the spectrum plan for current observatory locations.
Sixth, for the 2005‑2010 MHz band, ensure the transmitter is not airborne. Measure EIRP: out‑of‑band emissions above 2010 MHz must not exceed -66 dBW/MHz. If operating in a metropolitan area, comply with the strict EIRP, duty cycle, and transmission duration limits. Consider whether the band is suitable for the intended application; the metropolitan restrictions may be prohibitive.
Seventh, for the 27.5‑28.3 GHz band on land, identify if the station is inside a 26 GHz band spectrum licence area. If so, do not operate in 27.5‑28.1 GHz at all. If operating in 28.1‑28.3 GHz within such an area, ensure the transmit frequency is more than 50 MHz above 28.1 GHz (or twice the occupied bandwidth, whichever is greater). If outside such an area but within 30 km, limit EIRP to the horizon to -17.8 dBW in a 1 MHz bandwidth in the 27.5‑28.1 GHz band. Also respect the 27.5‑27.7 GHz guard band rule (50 MHz or twice occupied bandwidth above 27.5 GHz). For airborne operation, comply with the power flux density limits from ITU‑R Resolution 169 Annex 3. For ship operation, ensure power flux density on shore does not exceed -112.2 dBW/m²/MHz at 30 m above ground. Obtain RALI SM 26 maps to identify spectrum licence areas.
Eighth, check the location against the Australian Radio Quiet Zone Western Australia Frequency Band Plan 2023. If the station will operate in the inner quiet zone, note that the ACMA may consider Murchison Radioastronomy Observatory objections. It may be prudent to coordinate with the observatory in advance, even if not strictly required by the class licence.
Ninth, if using the receive bands in section 11 (10.7‑11.7 GHz, 18.2‑18.8 GHz, 19.3‑19.7 GHz), accept that the station receives no protection from point‑to‑point stations. Perform a risk assessment: are there existing point‑to‑point links in those bands? Could future licensing occur? Consider using alternative bands or implementing mitigations (e.g., frequency agility, filtered low‑noise amplifiers).
Tenth, maintain records. There is no registration requirement under the class licence, but good practice suggests keeping a compliance folder containing:
- Station description and device compliance day evidence.
- Equipment certification or test reports showing compliance with applicable standards/rules.
- ARPANSA exposure assessment.
- Frequency coordination records (e.g., advice from radio astronomy observatory).
- Maps showing distance from 26 GHz spectrum licence areas and quiet zones.
- Duty cycle and EIRP records for restricted bands (2005‑2010 MHz, 27.5‑28.3 GHz).
Eleventh, monitor for changes. Because the class licence references external instruments that change over time (e.g., ARPANSA Standard, equipment rules, RALI SM 26, ITU‑R resolutions, frequency band plans), operators should periodically review whether any updates affect their compliance. The ACMA website and the Federal Register of Legislation are the primary sources.
Finally, if any condition cannot be met, do not operate under the class licence. Seek an individual apparatus licence or apply for a variation of the class licence (the ACMA may consider, but the instrument itself is fixed). Operating outside the class licence conditions is unlicensed and carries significant penalties. Compliance is the operator’s responsibility, and ignorance of a condition is no defence.