(1) A PIRM plan must be tested—
(a) routinely at least once every 12 months, and
(b) if a pollution incident occurred during an activity to which an environment protection licence relates, which caused or threatened material harm to the environment, within the meaning of the Act, section 147—within 1 month of the incident occurring.
(2) The test must be carried out in a way to ensure the following—
(a) the information included in the PIRM plan is accurate and up to date,
(b) the PIRM plan is capable of being implemented in a workable and effective way.