VICIn ForceAct
Pipelines Act 2005
139Review of Environment Management Plan
Start here
Get a plain-English read of 139
Turn the raw legal text into a practical explanation grounded in Pipelines Act 2005.
139 Review of Environment Management Plan
A licensee must—
(a) review its Environment Management Plan before the end of each period of 5 years after the date the Plan was accepted; and
(b) report the results of each review to the Minister within 28 days after the completion of the review.
Part 10—Rehabilitation and compensation
Division 1—Rehabilitation bond
140 What is a rehabilitation bond?
For the purposes of this Part a ***rehabilitation bond*** is an instrument securing the payment of a specified amount of money for any rehabilitation work, clean-up work or pollution prevention work that may be necessary as a result of—
(a) the construction of a pipeline; or
(b) the decommissioning or removal of a pipeline.