Schedule 9 — Weekly survey report
[r. 74(1)]
| 4. | The name of the contractor conducting the survey. | | 5. | The name of the vessel or aircraft being used to conduct the survey. | | 6. | A map showing where the survey was conducted during the week. | | 7. | The number of kilometres or square kilometres for which data was acquired during the week. | | 8. | The number of points at which data was acquired during the week. | | 9. | The number of lines of data acquired during the week. | | 10. | The amount of downtime during the week due to equipment problems, bad weather or other circumstances. | | 11. | The percentage of the survey completed at the end of the week. |