Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations 1996
38Acceptance or rejection of a revised safety case
Start here
Get a plain-English read of 38
Turn the raw legal text into a practical explanation grounded in Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations 1996.
38 Acceptance or rejection of a revised safety case
(1) The Safety Authority must accept a revised safety case if:
(a) the revised safety case is appropriate to the facility and to the activities conducted at the facility; and
(b) the revised safety case complies with Subdivisions A, B and C of Division 1 for each stage in the life of the facility in respect of which the revision is submitted; and
(c) the revised safety case complies with Subdivision D of Division 1; and
(d) in a case on which the Safety Authority has required a validation relating to a proposed modification:
(i) the person, or each person, undertaking the validation meets the criteria specified in subregulation 44 (5); and
(ii) the validation complies with regulation 44.
(2) If a safety case is revised in relation to more than 1 stage in the life of the facility, the Safety Authority may accept the revised safety case for 1 or more stages in the life of the facility and reject the revised safety case for 1 or more stages in the life of the facility.
(3) If the Safety Authority rejects a safety case because the Safety Authority is not satisfied with any of the matters mentioned subregulation (1), the Safety Authority must give the operator a reasonable opportunity to change the safety case and resubmit it.
(a) the Safety Authority has given an operator a reasonable opportunity to change and resubmit a revised safety case or a revised part of a safety case; and
(b) the operator resubmits the revised safety case or revised part of the safety case; and
(c) the Safety Authority is not satisfied with any of the matters mentioned in subregulation (1);
the Safety Authority must reject the revised safety case.
(5) When accepting a revised safety case for a facility, the Safety Authority may impose limitations or conditions on the acceptance in respect of the facility or activities at the facility.