96Commencement of works
Start here
Get a plain-English read of 96
Turn the raw legal text into a practical explanation grounded in Petroleum (Submerged Lands) Act 1967.
#### 96 Commencement of works
(1AA) This section does not apply to permits granted under section 22 or such permits renewed under section 32.
(1) Where a permit, lease, licence, infrastructure licence or pipeline licence is granted subject to a condition that works or operations specified in the permit, lease, licence, infrastructure licence or pipeline licence are to be carried out, the permittee, lessee, licensee, infrastructure licensee or pipeline licensee, as the case may be, shall commence to carry out those works or operations within a period of 6 months after the day on which the permit, lease, licence, infrastructure licence or pipeline licence, as the case may be, comes into force.
(2) The Designated Authority may, for reasons that he thinks sufficient, by instrument in writing served on a permittee, lessee, licensee, infrastructure licensee or pipeline licensee:
(a) exempt him from compliance with the requirements of subsection (1); and
(b) direct him to commence to carry out the works or operations specified in the permit, lease, licence, infrastructure licence or pipeline licence, as the case may be, within such period after the day on which the permit, lease, licence, infrastructure licence or pipeline licence, as the case may be, comes into force as is specified in the instrument.
(3) A person to whom a direction is given under subsection (2) shall comply with the direction.
Penalty: 100 penalty units.