PETROLEUM REGULATIONS 2020
29Application to Tribunal – determination of access agreement
Start here
Get a plain-English read of 29
Turn the raw legal text into a practical explanation grounded in PETROLEUM REGULATIONS 2020.
29 Application to Tribunal – determination of access agreement (1) If an ADR process is terminated under regulation 26(1)(a) or (b), the interest holder may apply to the Tribunal for a determination as to the provisions that should form the contents of an access agreement so as to allow the interest holder to gain access to the relevant land. (2) The Tribunal may, on an application under subregulation (1), determine the provisions. (3) The Tribunal must, in exercising its jurisdiction under this regulation, take into account (and apply) the requirements of regulation 14. (4) The provisions determined by the Tribunal under this regulation have effect as if those provisions were embodied in an access agreement that has been signed by each of the parties.