sec.95 Prescribed matters for giving gas compliance certificate for installation not at operating plant— Act , s 734
This section applies if the holder of a gas work licence or gas work authorisation installs all or part of a gas system other than at an operating plant or proposed operating plant.
For section 734 (3) of the Act , the holder must give the gas compliance certificate to—
the owner, operator or proposed operator of the gas system when the holder completes the installation; and
the relevant network operator for the gas system within 5 business days after the holder completes the installation.
(sec.95-ssec.1) This section applies if the holder of a gas work licence or gas work authorisation installs all or part of a gas system other than at an operating plant or proposed operating plant.
(sec.95-ssec.2) For section 734 (3) of the Act , the holder must give the gas compliance certificate to— the owner, operator or proposed operator of the gas system when the holder completes the installation; and the relevant network operator for the gas system within 5 business days after the holder completes the installation.
- (a) the owner, operator or proposed operator of the gas system when the holder completes the installation; and
- (b) the relevant network operator for the gas system within 5 business days after the holder completes the installation.