sec.29 Survey plan to be submitted to chief executive
If a survey of a petroleum well required under section 28 is completed, the holder of the petroleum tenure must lodge a survey plan for the survey with the chief executive. The plan must be lodged as soon as practicable, but not later than 3 months, after the survey is completed. The plan must— accurately represent the survey carried out; and be accompanied by a certificate, signed by the person who carried out the survey, that states— the name of the person; and that the survey was carried out as required under the Act ; and that the plan accurately represents the survey carried out. If the chief executive considers a lodged survey plan or certificate does not comply with subsection (3) , the chief executive may— require the survey plan or certificate to be amended to comply within a stated period; or reject the survey plan. (sec.29-ssec.1) If a survey of a petroleum well required under section 28 is completed, the holder of the petroleum tenure must lodge a survey plan for the survey with the chief executive. (sec.29-ssec.2) The plan must be lodged as soon as practicable, but not later than 3 months, after the survey is completed. (sec.29-ssec.3) The plan must— accurately represent the survey carried out; and be accompanied by a certificate, signed by the person who carried out the survey, that states— the name of the person; and that the survey was carried out as required under the Act ; and that the plan accurately represents the survey carried out. (sec.29-ssec.4) If the chief executive considers a lodged survey plan or certificate does not comply with subsection (3) , the chief executive may— require the survey plan or certificate to be amended to comply within a stated period; or reject the survey plan.
- (a) accurately represent the survey carried out; and
- (b) be accompanied by a certificate, signed by the person who carried out the survey, that states— (i) the name of the person; and (ii) that the survey was carried out as required under the Act ; and (iii) that the plan accurately represents the survey carried out.
- (i) the name of the person; and
- (ii) that the survey was carried out as required under the Act ; and
- (iii) that the plan accurately represents the survey carried out.
- (i) the name of the person; and
- (ii) that the survey was carried out as required under the Act ; and
- (iii) that the plan accurately represents the survey carried out.
- (a) require the survey plan or certificate to be amended to comply within a stated period; or
- (b) reject the survey plan.